{"id":"spain","rid":"ES","name":"Spain","flag":"🇪🇸","group":"europe","type":"market","parent":null,"regions":null,"tier_range":null,"tier":2,"tier_name":"Strong","score":60,"pillar_score":67,"pillar_tier":2,"pillar_tier_name":"Strong","tier_cap":null,"reliability":{"assessed":true,"level":"elevated","dock":7,"provisional":false,"confidence":"High","delivery_transmission":{"level":"elevated","measure":"event-based","note":"The April 28, 2025 Iberian blackout cut power across peninsular Spain for about ten hours, one of the most significant blackouts in European history, driven by voltage and reactive-power control failures and cascading generator disconnections. Grid-code reform and remediation are underway.","sources":[{"label":"2025 Iberian blackout, ENTSO-E expert panel","url":"https://www.entsoe.eu/news/2025/10/03/28-april-blackout-in-spain-and-portugal-expert-panel-releases-comprehensive-factual-report/"}]},"delivery_distribution":{"level":"none"},"forward_capacity":{"level":"watch","measure":"modelled","note":"High renewable share with evolving voltage and inertia management; reforms in progress after the 2025 event."},"read":"Reliability flags found","level_means":"reviewed; flags found"},"reliability_dock":7,"regulatory_momentum":{"level":"adverse","direction":"improving","why":"Nearly 90 percent of Spain's transmission has little or no spare demand capacity, and Red Electrica's first demand access-capacity maps (2 February 2026) show only about a quarter of nodes with room; Royal Decree-Law 7/2026 is now forcing paper projects to pay a capacity-reservation charge or release their permits, while REE's 2026-2030 plan adds 27.7 GW of new demand access.","what_would_change_it":"RDL 7/2026 clearing speculative permits and REE's new capacity actually freeing nodes for real large loads.","scope":"The regulatory and permitting environment for connecting a new large load. An opinion on a dated record, not a measurement.","vocabulary_version":"regulatory-momentum-1.0"},"scheduled_changes":null,"queue":null,"friction":{"level":"High","wait":"permit-gated","measure":"measured","has_detail":true},"connection_pathway":null,"service_evidence":{"contractual_service_held":false,"local_capacity_state":"not_assessed","local_capacity_depth":0,"cost_basis":"triangulated","territory_count":0},"reliability_metrics":null,"forward_cost":null,"tariff":null,"realized_cost":{"low_usd_per_mwh":82,"mid_usd_per_mwh":98,"high_usd_per_mwh":118,"aggregation":"band","estimate_usd_per_mwh":null,"estimate_kind_note":null,"total_derivation":"compiled_band_allocated_across_categories","total_derivation_note":"The band is the compiled result and the component lines apportion its midpoint, which is why they sum exactly.","tariff_basis":null,"scenarios":null,"confidence":"triangulated","public_fragments":2,"contributed_points":0,"basis":"USD per MWh recurring, delivered to the standard 100 MW high-load-factor case, excluding customer-funded connection capital and excluding refundable taxes","cost_components":[{"name":"Wholesale energy","usd_per_mwh":60,"source":null,"provenance":{"provenance_state":"estimated_allocation","provenance_state_label":"Estimated allocation","provenance_state_means":"Apportioned from a compiled total or midpoint by analyst judgement. Not independently calculated, and not corroborated by anything outside the band it came from.","derivation":"allocation_of_compiled_midpoint","derivation_note":"This line apportions the compiled midpoint. Its value was not separately observed.","source_of_band_not_line":"EU electricity price components (Eurostat)","source_url_of_band_not_line":"https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics","band_as_of":"2026","customer_applicability":"100 MW contracted demand, 95% load factor, HV service","band_confidence":"triangulated","as_of":"2026","method":"analyst apportionment of the compiled midpoint across categories","confidence":"allocation","confidence_note":"Apportioned from the compiled delivered-cost midpoint by analyst judgement. Not separately observed.","covers_categories":["energy"],"corroborated_by":null,"state_vocabulary_version":"provenance-state-1.0","what_would_upgrade_it":"A separately sourced figure for this category with its own date, method and confidence. Until then the band's provenance establishes the total only, not this line.","version":"line-provenance-1.1"},"evidence":"estimated_allocation"},{"name":"Network charges","usd_per_mwh":30,"source":null,"provenance":{"provenance_state":"estimated_allocation","provenance_state_label":"Estimated allocation","provenance_state_means":"Apportioned from a compiled total or midpoint by analyst judgement. Not independently calculated, and not corroborated by anything outside the band it came from.","derivation":"allocation_of_compiled_midpoint","derivation_note":"This line apportions the compiled midpoint. Its value was not separately observed.","source_of_band_not_line":"EU electricity price components (Eurostat)","source_url_of_band_not_line":"https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics","band_as_of":"2026","customer_applicability":"100 MW contracted demand, 95% load factor, HV service","band_confidence":"triangulated","as_of":"2026","method":"analyst apportionment of the compiled midpoint across categories, covering transmission, distribution in one line","confidence":"bundled_allocation","confidence_note":"Apportioned, and covering more than one cost category in a single line. Neither the total nor the split within it was separately observed.","covers_categories":["transmission","distribution"],"corroborated_by":null,"state_vocabulary_version":"provenance-state-1.0","what_would_upgrade_it":"A separately sourced figure for this category with its own date, method and confidence. Until then the band's provenance establishes the total only, not this line.","version":"line-provenance-1.1"},"evidence":"estimated_allocation"},{"name":"Taxes & levies","usd_per_mwh":8,"source":null,"provenance":{"provenance_state":"estimated_allocation","provenance_state_label":"Estimated allocation","provenance_state_means":"Apportioned from a compiled total or midpoint by analyst judgement. Not independently calculated, and not corroborated by anything outside the band it came from.","derivation":"allocation_of_compiled_midpoint","derivation_note":"This line apportions the compiled midpoint. Its value was not separately observed.","source_of_band_not_line":"EU electricity price components (Eurostat)","source_url_of_band_not_line":"https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics","band_as_of":"2026","customer_applicability":"100 MW contracted demand, 95% load factor, HV service","band_confidence":"triangulated","as_of":"2026","method":"analyst apportionment of the compiled midpoint across categories","confidence":"allocation","confidence_note":"Apportioned from the compiled delivered-cost midpoint by analyst judgement. Not separately observed.","covers_categories":["taxes"],"corroborated_by":null,"state_vocabulary_version":"provenance-state-1.0","what_would_upgrade_it":"A separately sourced figure for this category with its own date, method and confidence. Until then the band's provenance establishes the total only, not this line.","version":"line-provenance-1.1"},"evidence":"estimated_allocation"}],"component_status":{"arithmetic_integrity":true,"evidence_reconciliation":"not_independently_reconciled","independently_sourced_lines":0,"total_lines":3,"bundled":[],"text":"The delivered-cost band is the compiled result. The component lines are an estimated allocation of its midpoint, not separately observed figures.","provenance_summary":{"by_state":{"estimated_allocation":3},"usd_by_state":{"estimated_allocation":98},"evidenced_share_pct":0,"lines_awaiting_evidence":["Wholesale energy","Network charges","Taxes & levies"],"what_would_close_them":"A separately sourced or tariff-derived figure for each category, with its own date, method and confidence. Until then the band's provenance establishes the total only, not these lines.","version":"provenance-state-1.0"},"category_coverage":{"energy":{"status":"estimated","line":"Wholesale energy","missing_evidence":"An independently sourced wholesale or tariff energy figure with its own date, method and confidence."},"capacity":{"status":"unavailable","missing_evidence":"No capacity or resource adequacy figure is held for this market."},"transmission":{"status":"bundled","line":"Network charges","combined_with":["distribution"],"line_is_sourced":false,"line_provenance_state":"estimated_allocation","source":null,"source_url":null,"effective":null,"formula":null,"missing_evidence":"A separate transmission figure, or a sourced apportionment of the Network charges line."},"distribution":{"status":"bundled","line":"Network charges","combined_with":["transmission"],"line_is_sourced":false,"line_provenance_state":"estimated_allocation","source":null,"source_url":null,"effective":null,"formula":null,"missing_evidence":"A separate distribution figure, or a sourced apportionment of the Network charges line."},"demand_charges":{"status":"unavailable","missing_evidence":"No demand charges figure is held for this market."},"ancillary":{"status":"unavailable","missing_evidence":"No ancillary services and uplift figure is held for this market."},"riders":{"status":"unavailable","missing_evidence":"No riders and unavoidable regulatory charges figure is held for this market."},"carbon":{"status":"unavailable","missing_evidence":"No carbon-related charges figure is held for this market."},"taxes":{"status":"estimated","line":"Taxes & levies","missing_evidence":"An independently sourced recurring taxes figure with its own date, method and confidence."},"connection_capital":{"status":"not_applicable","reason":"Outside the recurring $/MWh boundary by definition."}},"category_vocabulary_version":"cost-categories-1.0","capacity_cross_check":null,"method_version":"cost-components-1.0"},"component_source":["EU electricity price components (Eurostat)","https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics"],"figures":{"low_usd_per_mwh":{"value":82,"unit":"USD/MWh (delivered, 100 MW at 95% load factor, HV)","as_of":"2026-06","source":{"name":"PowerGridIQ cost engine","url":"https://powergridiq.com/cost-methodology"},"method":"estimated","confidence":"triangulated","stable_id":"pgiq:spain:low_usd_per_mwh:2026-06","report_url":"https://powergridiq.com/rating/spain"},"mid_usd_per_mwh":{"value":98,"unit":"USD/MWh (delivered, 100 MW at 95% load factor, HV)","as_of":"2026-06","source":{"name":"PowerGridIQ cost engine","url":"https://powergridiq.com/cost-methodology"},"method":"estimated","confidence":"triangulated","stable_id":"pgiq:spain:mid_usd_per_mwh:2026-06","report_url":"https://powergridiq.com/rating/spain"},"high_usd_per_mwh":{"value":118,"unit":"USD/MWh (delivered, 100 MW at 95% load factor, HV)","as_of":"2026-06","source":{"name":"PowerGridIQ cost engine","url":"https://powergridiq.com/cost-methodology"},"method":"estimated","confidence":"triangulated","stable_id":"pgiq:spain:high_usd_per_mwh:2026-06","report_url":"https://powergridiq.com/rating/spain"}}},"cost_availability":{"label":"Standardized cost observable","means":"A comparable recurring-cost band can be built from observable, applicable inputs for the standard archetype.","user_action":"Use the band, with its stated confidence and boundary.","class":"standardized_observable","band_published":true},"cost_evidence_state":{"state":"applicable_evidence_incomplete","answerable":"conditionally","label":"Applicable, evidence incomplete","means":"The archetype can buy the service and the band is sound, but some published figures do not yet carry their own source, date, method and confidence.","remedy":"Finish the per-line provenance. No new access or negotiation is required.","also_holds":[],"vocabulary_version":"evidence-state-1.0"},"jurisdiction_evidence":null,"cost_structure":null,"cost_withdrawn":null,"cost_correction":null,"carbon_correction":null,"carbon_official_reference":null,"partial_cost_verified":null,"cost_pillar_calculation":{"method":"cost-rescore-1.1","rubric_version":"cost-rescore-1.1","rule":"Cost pillar = 90 at $50/MWh, 35 at $150/MWh, straight line, kept within 35-95, scored on the band midpoint.","input_usd_per_mwh":98,"input_mid_usd_per_mwh":98,"level_score":63.6,"direction":"stable","direction_adjustment":0,"observability":"estimated_allocation","observability_adjustment":0,"cost_pillar":64,"arithmetic":"63.6 +0 +0 = 64","band_low_usd_per_mwh":82,"band_high_usd_per_mwh":118,"score_at_band_low":72,"score_at_band_high":53,"previous_cost_pillar":62},"evidence":{"source_reliability":"Moderate","coverage":"Full","coverage_dimensions":3,"last_reviewed":"June 2026","measured_layers":1,"data_layers":3,"layers":[{"layer":"PGIQ Rating opinion","method":"opinion","vintage":"June 2026","freshness":"Current","source_url":"https://powergridiq.com/methodology"},{"layer":"Reliability review","method":"historical","vintage":"2025","freshness":"Fresh","source_url":"https://www.entsoe.eu/news/2025/10/03/28-april-blackout-in-spain-and-portugal-expert-panel-releases-comprehensive-factual-report/"},{"layer":"Connection friction","method":"measured","vintage":"2025/26","freshness":"Fresh","source_url":"https://www.ree.es/en/press-office/news/press-release/2026/02/red-elctrica-publishes-demand-access-capacities-for-the-transmission-grid"},{"layer":"Realized cost","method":"triangulated","vintage":"2026","freshness":"Fresh","source_url":"https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics"}]},"outlook":"Positive","confidence":"Med","under_review":false,"thesis":"Cheap Iberian solar and a genuinely opening market (Madrid, Aragon). Strong renewables and a competitive cost base make Spain a real European riser.","pillars":{"access":65,"availability":72,"cost":64,"momentum":58,"carbon":82},"pillar_rationale":{"access":"Opening access; growing hub activity in Madrid and Aragon.","availability":"Good availability with strong solar and wind.","cost":"Scored from what a 100 MW load actually pays here once grid fees, taxes and other charges are added, not from the wholesale price: about $98 per MWh (band $82 to $118). On the PGIQ cost scale ($50 per MWh scores 90, $150 per MWh scores 35) that gives 64. At the cheap end of the band it would score 72; at the dear end, 53.","momentum":"Improving momentum.","carbon":"Clean-ish (~80-130 g)."},"reads":{"build":"Build score 30/100","sell":"Offtake grade C (index 47/100)","plan":"Load pressure: Rising","monitor":"Grid strength: Watch (52/100)"},"offtake_opportunity_index":47,"demand_hunger":44,"build_feasibility":30,"supplier_signals":{"bess_arbitrage_usd_mwh":41,"bess_arbitrage_pct":68,"solar_capture_pct":82,"wind_capture_pct":103},"outlook_drivers":{"upgrade":["Madrid/Aragon build accelerates.","Solar-plus-storage firms supply and lowers cost."],"downgrade":["Grid-connection bottlenecks.","Heat and water constraints."]},"risks":["Connection-queue growth.","Summer heat/water."],"peers":{"like":"Portugal (cheap Iberian solar)","ahead":"on scale vs Portugal","behind":"Nordics on carbon"},"sources":[{"label":"Europe data-center market","url":"https://www.cushmanwakefield.com/en/insights/emea-data-centre-update"}],"latest_action":{"date":"Oct 2026","type":"Affirmed","note":"Cost-pillar score now set by one published rule from the delivered-cost band, not by analyst judgement. The band itself is unchanged. PGIQ Rating 59 to 60. Tier 2 Strong unchanged.","trigger":"Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release","release":"ratings-release-2026-cost"},"grid":{"price_usd_mwh":60,"carbon_intensity_g":130,"renewable_pct":64,"renewable_generation_share_pct":64,"low_carbon_generation_share_pct":86,"fuel_mix":{"wind":28,"nuclear":22,"solar":18,"hydro":14,"gas":12,"coal":2,"biofuel":4},"demand_mw":25000,"capacity_mw":58000,"imports_mw":1500,"exports_mw":2000,"firm_capacity_mw":null,"firm_capacity_availability":"insufficient_evidence","firm_capacity_basis":null,"est_peak_mw":38750,"firm_headroom_mw":null,"firm_headroom_availability":"dependency_unavailable","peak_stress_pct":null,"peak_stress_availability":"dependency_unavailable","adequacy_required_input":"capacity_mix_mw with a declared basis, or an official dependable or accredited capacity from the operator","price_cycle":"solar","price_basis":"not_reviewed","price_absent_reason":null,"price_source":"modelled-baseline","price_as_of":null,"price_vintage":"undated_modelled_baseline","price_is_live":false,"carbon_intensity_unit":"gCO2eq/kWh","carbon_measurement_boundary":"operational_combustion","carbon_calculation_method":"structural_estimate","carbon_emission_factor_source":null,"carbon_basis_withdrawn":true,"carbon_imports_treatment":"not_accounted","carbon_provenance_state":"structural","carbon_decision_eligibility":"insufficient_evidence","carbon_confidence":"low","source":"modelled-baseline","figures":{"price_usd_mwh":{"value":60,"unit":"USD/MWh","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"modelled","confidence":"Med","stable_id":"pgiq:spain:price_usd_mwh:2026-06","report_url":"https://powergridiq.com/rating/spain"},"carbon_intensity_g":{"value":130,"unit":"gCO2/kWh","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"modelled","confidence":"Med","stable_id":"pgiq:spain:carbon_intensity_g:2026-06","report_url":"https://powergridiq.com/rating/spain"},"renewable_pct":{"value":64,"unit":"percent","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:renewable_pct:2026-06","report_url":"https://powergridiq.com/rating/spain"},"renewable_generation_share_pct":{"value":64,"unit":"percent","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:renewable_generation_share_pct:2026-06","report_url":"https://powergridiq.com/rating/spain"},"low_carbon_generation_share_pct":{"value":86,"unit":"percent","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:low_carbon_generation_share_pct:2026-06","report_url":"https://powergridiq.com/rating/spain"},"demand_mw":{"value":25000,"unit":"MW","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"modelled","confidence":"Med","stable_id":"pgiq:spain:demand_mw:2026-06","report_url":"https://powergridiq.com/rating/spain"},"capacity_mw":{"value":58000,"unit":"MW","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"modelled","confidence":"Med","stable_id":"pgiq:spain:capacity_mw:2026-06","report_url":"https://powergridiq.com/rating/spain"},"imports_mw":{"value":1500,"unit":"MW","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"modelled","confidence":"Med","stable_id":"pgiq:spain:imports_mw:2026-06","report_url":"https://powergridiq.com/rating/spain"},"exports_mw":{"value":2000,"unit":"MW","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"modelled","confidence":"Med","stable_id":"pgiq:spain:exports_mw:2026-06","report_url":"https://powergridiq.com/rating/spain"},"est_peak_mw":{"value":38750,"unit":"MW","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:est_peak_mw:2026-06","report_url":"https://powergridiq.com/rating/spain"},"firm_headroom_mw":{"value":null,"unit":"MW","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:firm_headroom_mw:2026-06","report_url":"https://powergridiq.com/rating/spain","absence":"insufficient_evidence","reason_text":"Not enough evidence to publish a value."},"peak_stress_pct":{"value":null,"unit":"percent","as_of":"2026-06","source":{"name":"PowerGridIQ grid baseline and operator feeds","url":"https://powergridiq.com/data-quality"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:peak_stress_pct:2026-06","report_url":"https://powergridiq.com/rating/spain","absence":"insufficient_evidence","reason_text":"Not enough evidence to publish a value."}}},"evidence_depth":{"use_case":"project_case","use_case_label":"Standardized Project Case","overall":"M2 Compiled","overall_permits":"Compiled from cited sources: supports investor and institutional analysis.","insufficient_evidence":false,"unassessed_required_fields":[],"project_ready":false,"blocking_fields":["connection","reliability"],"fields":{"cost":"M3 Project-ready","connection":"M2 Compiled","reliability":"M2 Compiled","carbon":"M2 Compiled","regulatory":"M2 Compiled","local_capacity":"not_assessed"},"by_use_case":{"discovery":{"label":"Discovery and monitoring","matrix_version":"1.0","tier":"M2 Compiled","ready":false,"blocking_fields":["connection"],"insufficient_evidence":false,"why":""},"market_comparison":{"label":"Market comparison","matrix_version":"1.0","tier":"M2 Compiled","ready":false,"blocking_fields":["connection","reliability"],"insufficient_evidence":false,"why":""},"project_case":{"label":"Standardized Project Case","matrix_version":"1.0","tier":"M2 Compiled","ready":false,"blocking_fields":["connection","reliability"],"insufficient_evidence":false,"why":""},"project_case_carbon":{"label":"Project Case with a carbon requirement","matrix_version":"1.0","tier":"M2 Compiled","ready":false,"blocking_fields":["connection","reliability","carbon"],"insufficient_evidence":false,"why":""},"site_diligence":{"label":"Conditional site diligence","matrix_version":"1.0","tier":"not_assessed","ready":false,"blocking_fields":["connection","reliability","local_capacity"],"insufficient_evidence":true,"why":"not assessed here: local capacity"}},"reliability_layers":{"bulk_historical":{"state":"held","method":"event-based"},"forward_adequacy":{"state":"held","method":"modelled"},"local_delivery":{"state":"unknown","method":null},"contractual_service":{"state":"unknown","method":null},"designed_site_resilience":{"state":"unknown","method":null}},"definition_version":"carbon_scope@1.0;connection_process@1.0;cost_archetype@1.0;evidence_tiers@1.0;reliability_layers@1.0","scale":"M1 broad / M2 compiled / M3 project-ready / M4 local; cumulative, so each tier includes the ones below it. Assigned per field from held evidence with provenance. Not a rating strength, confidence score or feasibility conclusion."},"next_review":"2027-11-15","report_url":"https://powergridiq.com/rating/spain","as_of":"June 2026","evidence_layers":{"version":"evidence-layers-1.0","band":{"state":"independently_compiled","label":"Independently compiled","means":"The band is assembled from multiple sourced, dated and applicable published figures. It is not a single benchmark and it is not a tariff reconstruction.","reproducible":"partially"},"component":{"total_lines":3,"reproducible_lines":0,"states":["estimated_allocation"],"all_lines_are_estimated_allocations":true,"independently_reproducible":false,"illustrative":true,"notice":"Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.","notice_short":"Illustrative allocation — lines not separately sourced","vocabulary_version":"evidence-layers-1.0"},"cost_pillar":{"state":"rubric_derived","label":"Rubric derived","means":"The score is reproduced from a declared rubric, stored inputs and a published formula, and a gate asserts the published score and the rubric agree.","reproducible":true},"layers_are_independent":"Band, component and cost-pillar evidence are separate judgments. A market may have a sound, applicable band and an illustrative component breakdown at the same time. Do not read a component-evidence limitation as a statement about the band."},"in_cost_comparison":{"value":true,"reason_code":null,"reason_text":null},"figures":{"tier":{"value":2,"unit":"tier_1_best_to_5","as_of":"2026-06","source":{"name":"PowerGridIQ Rating","url":"https://powergridiq.com/methodology"},"method":"rated","confidence":"Med","stable_id":"pgiq:spain:tier:2026-06","report_url":"https://powergridiq.com/rating/spain"},"score":{"value":60,"unit":"points_0_100","as_of":"2026-06","source":{"name":"PowerGridIQ Rating","url":"https://powergridiq.com/methodology"},"method":"rated","confidence":"Med","stable_id":"pgiq:spain:score:2026-06","report_url":"https://powergridiq.com/rating/spain"},"pillar_score":{"value":67,"unit":"points_0_100","as_of":"2026-06","source":{"name":"PowerGridIQ Rating","url":"https://powergridiq.com/methodology"},"method":"rated","confidence":"Med","stable_id":"pgiq:spain:pillar_score:2026-06","report_url":"https://powergridiq.com/rating/spain"},"pillar_tier":{"value":2,"unit":"tier_1_best_to_5","as_of":"2026-06","source":{"name":"PowerGridIQ Rating","url":"https://powergridiq.com/methodology"},"method":"rated","confidence":"Med","stable_id":"pgiq:spain:pillar_tier:2026-06","report_url":"https://powergridiq.com/rating/spain"},"reliability_dock":{"value":7,"unit":"points_deducted","as_of":"2026-06","source":{"name":"PowerGridIQ Rating","url":"https://powergridiq.com/methodology"},"method":"rated","confidence":"Med","stable_id":"pgiq:spain:reliability_dock:2026-06","report_url":"https://powergridiq.com/rating/spain"},"offtake_opportunity_index":{"value":47,"unit":"index_0_100","as_of":"2026-06","source":{"name":"PowerGridIQ Rating","url":"https://powergridiq.com/methodology"},"method":"derived","confidence":"Med","stable_id":"pgiq:spain:offtake_opportunity_index:2026-06","report_url":"https://powergridiq.com/rating/spain"}},"figure_contract_version":"1.0"}