Alberta
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/alberta, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$60 to $110 per MWh
Midpoint about $80 per MWh
What builds the $80 midpoint
Where the cost lands
Alberta runs an energy-only market, so the pool price is only part of the story: transmission and distribution charges add materially on top, and the province is reworking cost allocation for large loads. The delivered cost is above the headline wholesale figure, though still moderate by global standards.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: AESO market and pool price · Alberta electricity rates (Utilities Consumer Advocate).
Connection friction
Friction level
Severe
This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.
The AESO's interim large-load cap of 1,200 MW is fully allocated (about 970 MW to GLDC and 230 MW to Keephills), leaving roughly 37 data-centre proposals in the queue that must self-generate or wait for grid expansion, where new transmission alone can take about ten years. A durable Phase 2 framework for loads over 75 MW is still being written, so a new grid-only load faces a multi-year wait.
What builds the 72-month wait
Data-center share of demand pressure: High. Sources: AESO large-load connection process · Alberta AI data-centre power limits (CBC). The full cross-market connection dataset is available through the Connection Friction Feed.
The five pillars behind the tier
Open, energy-only market; an interim AESO large-load connection cap is in place while it studies the surge.
Adequate availability (gas plus growing wind), with cheap self-supply gas.
Mid-range cost.
Rising momentum: a wave of AI announcements.
Carbon moderate (~260 g), gas-led but decarbonising.
Reliability overlay
Historical bulk-system performance: Reliability flags found
Tight supply repeatedly pushed the system to the edge in 2024: AESO declared an EEA3 grid emergency on Jan 13, 2024 with a public alert warning of imminent rotating outages, and issued a second grid alert in April 2024 that led to brief rotating outages in the Edmonton area.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
event-based · Alberta Jan/Apr 2024 event report (MSA) · AESO April 2024 grid alert (Global News)
Historical utility-territory delivery performance: No reliability flags found
Forward resource adequacy (assessed): Adequacy flagged
Recent grid alerts reflect thin reserve margins during extreme cold and low imports; market and build response is underway.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Regulatory momentum
Why: The interim AESO large-load connection cap is fully subscribed, but a durable Phase 2 framework is expected as the province writes its data-centre rules.
What would change the read: AESO finalising an open, durable Phase 2 large-load connection framework.
For new supply: Abundant gas and a pro-build posture favor new generation; the binding constraint is the interim AESO large-load cap, not supply build.
Beyond the grid: Indigenous consultation and water are live legal risks: Sturgeon Lake Cree Nation is seeking judicial review of Alberta's Water Act licence for the proposed roughly 70 billion dollar Wonder Valley AI campus on drought-stricken Treaty 8 land, saying it received no notice or consultation. CBC Global News
Outlook drivers
↑ Upgrade triggers
- AI announcements convert from announced to operational.
- AESO resolves the interim large-load cap with a durable framework.
↓ Downgrade triggers
- The interim connection cap tightens.
- Carbon profile deters RE-mandated tenants.
Scheduled to change
Evidence behind this rating
The real-world events that test our Tier 2 call for Alberta: 2 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
The Data Centre Regulation AR 117/2026 (9 Jun 2026) codifies BYOG, prioritizing large data centers that bring their own generation. AESO's proposed BYOG process closed feedback 13 Jul 2026, with rollout expected Aug 2026 and periodic intakes.
Meta began construction (Jul 2026) of a large AI-optimized data center in Sturgeon County, northeast of Edmonton, its first in Canada, with the company reporting that it will match the site's electricity to clean and renewable supply. That is a procurement commitment, not a description of the physical grid mix. A build of this scale is concrete large-load momentum on the Alberta grid, and a live test of the interim connection framework.
Phase 1 closed on 12 Jun 2026 with the whole interim data-centre connection limit allocated and contracted; a durable Phase 2 framework awaits Alberta's data-centre regulation.
A temporary cap on new large-load connections while AESO designs a durable framework for a wave of data-center interest.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
What this would mean for a project
100 MW contracted demand, 95% load factor, HV servicecalculated
A load of this shape consumes 832,200 MWh a year. At the delivered band of $60 to $110/MWh that is $49,932,000 to $91,542,000 a year in recurring power.
Wholesale energy is 69% of the delivered cost here. The other $25/MWh is transmission and distribution, and riders and other charges. See the full build-up.
Typical connection wait is 5 to 8 years (queue capped), at Med-High confidence.
Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Market-level (M2) | Good for comparing markets, not for a site |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | historical | 2025 | Fresh | Alberta Jan/Apr 2024 event report (MSA) |
| Connection friction | measured | 2025/26 | Fresh | AESO large-load connection process |
| Realized cost | triangulated | 2026 | Fresh | AESO market and pool price |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $60 to $110 per MWh, midpoint $80, basis triangulated, against the 100 MW archetype
- Historical bulk-system performance (event-based)
- Forward resource adequacy (assessed)
What is open
- Historical utility-territory delivery performance (would change the answer)
- Contractual service terms (would change the answer)
- Designed site resilience
- Substation-level capacity evidence
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Cost $60 to $110 per MWh, midpoint $80 (triangulated)
What could disqualify this market
- Interim large-load connection limit.
- Power cost and carbon.
Questions to put to the utility
- What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project caseWhy it is open: no regulator outage series compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/alberta/gaps