CAISO (California)
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/caiso, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$95 to $155 per MWh
Midpoint about $120 per MWh
What builds the $120 midpoint
Where the cost lands
California's wholesale price badly understates the delivered cost. A large load carries some of the highest non-bypassable and delivery charges in the United States, so an all-in figure of roughly $95 to $155 per MWh is realistic, well above the $42 wholesale reading. On this basis California is an expensive market for a new large load, not a cheap one.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: CPUC on data-center cost allocation · CAISO large loads and Rule 30.
Interconnection queue
Active queue depth
191 GW
Typical wait
60 months
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Constrained access: deep cluster-study queue, storage-heavy backlog.
Tight availability: the evening net-load ramp as solar fades.
High cost.
High momentum: the established Silicon Valley cluster.
Carbon moderate (~230 g), solar-and-gas with heavy storage.
Reliability overlay
Historical bulk-system performance: Reliability flags found
ISO-ordered rotating outages during the August 2020 heat wave (about 492,000 customers cut on Aug 14) show supply-shortfall load-shedding risk at peak.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
event-based · CAISO rotating outages fact sheet
Historical utility-territory delivery performance: Reliability flags found
Average customer interruption (SAIDI) of 177.06 minutes per year in 2024, excluding major event days as filed. Public Safety Power Shutoffs: utilities proactively de-energize lines during wildfire-risk weather, so a load can lose grid power for reasons unrelated to its own site.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
event-based · CPUC Public Safety Power Shutoffs · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 4 of 4 territories, 100% of customers, regional context only)
The territories inside this market
The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.
| Territory operator | SAIDI min/yr | Customers | Major-event method |
|---|---|---|---|
| Pacific Gas & Electric Co. (CA) | 275.6 | 5,795,693 | IEEE 1366 |
| Southern California Edison Co (CA) | 100.25 | 5,316,264 | IEEE 1366 |
| San Diego Gas & Electric Co (CA) | 71.13 | 1,527,274 | IEEE 1366 |
| City of Santa Clara - (CA) (CA) | 161.73 | 60,620 | IEEE 1366 |
Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.
Forward resource adequacy (assessed): Adequacy flagged
NERC's 2024 assessment rates California elevated-risk, with extreme heat likely to cause reserve shortfalls.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
assessed · NERC 2024 Long-Term Reliability Assessment
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 177.06 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across 4 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Regulatory momentum
Why: FERC's 18 June 2026 Section 206 show-cause order directs CAISO to justify or rewrite its large-load and co-location tariff terms, so the rules for connecting a data centre are formally in flux; California's high retail costs and its own cost-allocation review add friction on top.
What would change the read: The Section 206 process settling on clear large-load connection and cost-allocation rules, and California resolving who pays for the supporting build.
Outlook drivers
↑ Upgrade triggers
- Storage build flattens the ramp and frees capacity.
- Queue reform speeds connections.
↓ Downgrade triggers
- Wildfire-season shutoffs and ramp tightness worsen.
- Cost and policy push new build out of state.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Market-level (M2) | Good for comparing markets, not for a site |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
High
2 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
23 Oct 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 4 of 4 territories, 100% of customers, regional context only) |
| Interconnection queue | measured | end-2025 (LBNL 2026) | Fresh | LBNL Queued Up 2026 |
| Realized cost | triangulated | 2026 | Fresh | CPUC on data-center cost allocation |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $95 to $155 per MWh, midpoint $120, basis triangulated, against the 100 MW archetype
- Historical utility-territory delivery performance 177.06 minutes per year (2024)
- Historical bulk-system performance (event-based)
- Forward resource adequacy (assessed)
- Typical interconnection wait about 60 months (generation and storage queue, not a load wait)
What is open
- Contractual service terms (would change the answer)
- Designed site resilience
- Substation-level capacity evidence
How service and connection are organized
Territories in this market, each with its own filed record: Pacific Gas & Electric Co., Southern California Edison Co, San Diego Gas & Electric Co, City of Santa Clara - (CA). Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Cost $95 to $155 per MWh, midpoint $120 (triangulated)
- Schedule: interconnection queues here run about 60 months for generation and storage; a large load follows a different process and we do not hold its measured distribution
What could disqualify this market
- Evening ramp and supply adequacy.
- Wildfire/PSPS and high cost.
Questions to put to the utility
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/caiso/gaps