⚡ POWERGRIDIQ · EVIDENCE PACK

Desert Southwest (Phoenix)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/desert-southwest, with every section open. As of June 2026.

Back to the report

Realized cost band

Withdrawn. The published band blended an effective regulated rate with APS's PROPOSED extra-large-load class of roughly +45%, which the Arizona Corporation Commission has not decided: the rate-case hearing closed 7 July 2026 and the Commission's vote is due by 31 December 2026. A pending proceeding may not set a current delivered cost. The band's primary source was also an ACC large-load workshop rather than a tariff.

No delivered-cost band is published for this market, and no substitute figure has been put in its place. Screening on recurring cost returns insufficient evidence for this market rather than a value we cannot defend.

Restored when: A cited EFFECTIVE rate applicable to the standard archetype -- APS's Extra High Load Factor schedule as it currently stands, or SRP's E-67 large-load terms -- with a stated cost boundary, effective date, method and confidence. The proposed class may then be carried as a dated forward risk outside the band, never inside it. Withdrawn 2026-08-20.

Interconnection queue

These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.

Active queue depth

95 GW

Typical wait

39 monthsnon-ISO West median, projects online 2018 to 2025; not specific to this market

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%68

Moderate, improving access: Arizona utilities are accommodating large load and building fast.

Availability25%62

Moderate availability: solar plus gas, with batteries increasingly covering the evening peak.

Cost25%80

Low-to-mid cost.

Momentum15%85

Very high momentum: a top inventory-growth market with a deep pipeline.

Carbon5%70

Carbon moderate (~200 g), solar-heavy by day.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 72 is reduced to 69, a deduction of 3 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: No reliability flags found

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 67.88 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 4 of 4 territories, 100% of customers, regional context only)

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. major event days identified by IEEE 1366 (2.5-beta method). It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment (being told to cut output or consumption) rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

The territories inside this market

The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.

Territory operatorSAIDI min/yrCustomersMajor-event method
Arizona Public Service Co (AZ)80.861,395,614IEEE 1366
Salt River Project (AZ)52.811,161,925IEEE 1366
Tucson Electric Power Co (AZ)68.36455,579IEEE 1366
UNS Electric, Inc (AZ)60.13106,739IEEE 1366

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Adequacy flagged

Phoenix and the desert Southwest face extreme summer cooling peaks that strain supply; utilities have managed them so far, but heat-driven peak stress is the standing forward risk.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 67.88 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across 4 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 4 of 4 territories, 100% of customers, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Fast load growth competing for the same capacity.
New supply in motion
About 23.8 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Future firm supply
Future firm supply: adequacy flagged.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Outlook drivers

↑ Upgrade triggers

  • Continued solar-plus-storage build lowers carbon and firms the peak.
  • Sustained absorption converts the pipeline.

↓ Downgrade triggers

  • Water and extreme-heat constraints.
  • Transmission limits slow new connections.

Evidence behind this rating

The real-world events that test our Tier 2 call for Desert Southwest (Phoenix): 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Phoenix overtakes Dallas and Silicon Valley on inventory ✓ Supports the rating
2025MomentumMateriality: low

The Desert Southwest is now one of the fastest-growing US data-center markets on land, solar and a pro-build posture.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: CBRE ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

June 2026
New ratingNew rating: Tier 2 Strong assigned.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostNot assessedWe hold no evidence for this yet
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryNot assessedWe hold no evidence for this yet
Local capacityNot assessedWe hold no substation-level evidence
Not yet good enough for any decision use. The weakest field is cost.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

1 of 2 data layers directly measured; the rest are triangulated or modelled

Coverage

Substantial

2 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 4 of 4 territories, 100% of customers, regional context only)
Interconnection queuemodelledend-2025 (LBNL 2026)FreshLBNL Queued Up 2026

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Historical utility-territory delivery performance 67.88 minutes per year (2024)
  • Forward resource adequacy (assessed)
  • Typical interconnection wait about 39 months (generation and storage queue, not a load wait; non-ISO West median, projects online 2018 to 2025; not specific to this market)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Cost evidence (would change the answer)
  • Regulatory evidence
  • Substation-level capacity evidence

How service and connection are organized

Territories in this market, each with its own filed record: Arizona Public Service Co, Salt River Project, Tucson Electric Power Co, UNS Electric, Inc. Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Schedule: interconnection queues here run about 39 months for generation and storage (non-ISO West median, projects online 2018 to 2025; not specific to this market); a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Summer extreme heat and cooling-peak reliability.
  • Water availability for cooling.

Questions to put to the utility

These come from the gaps in our record for Desert Southwest (Phoenix): the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project case
    Why it is open: no compiled cost band for this market yet.
  2. Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?
    Why it is open: no dated regulatory read compiled for this market yet.
  3. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/desert-southwest/gaps

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.