Desert Southwest (Phoenix)
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/desert-southwest, with every section open. As of June 2026.
Realized cost band
Withdrawn. The published band blended an effective regulated rate with APS's PROPOSED extra-large-load class of roughly +45%, which the Arizona Corporation Commission has not decided: the rate-case hearing closed 7 July 2026 and the Commission's vote is due by 31 December 2026. A pending proceeding may not set a current delivered cost. The band's primary source was also an ACC large-load workshop rather than a tariff.
No delivered-cost band is published for this market, and no substitute figure has been put in its place. Screening on recurring cost returns insufficient evidence for this market rather than a value we cannot defend.
Restored when: A cited EFFECTIVE rate applicable to the standard archetype -- APS's Extra High Load Factor schedule as it currently stands, or SRP's E-67 large-load terms -- with a stated cost boundary, effective date, method and confidence. The proposed class may then be carried as a dated forward risk outside the band, never inside it. Withdrawn 2026-08-20.
Interconnection queue
Active queue depth
95 GW
Typical wait
39 monthsnon-ISO West median, projects online 2018 to 2025; not specific to this market
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Moderate, improving access: Arizona utilities are accommodating large load and building fast.
Moderate availability: solar plus gas, with batteries increasingly covering the evening peak.
Low-to-mid cost.
Very high momentum: a top inventory-growth market with a deep pipeline.
Carbon moderate (~200 g), solar-heavy by day.
Reliability overlay
Historical bulk-system performance: No reliability flags found
Historical utility-territory delivery performance: No reliability flags found
Average customer interruption (SAIDI) of 67.88 minutes per year in 2024, excluding major event days as filed.
The territories inside this market
The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.
| Territory operator | SAIDI min/yr | Customers | Major-event method |
|---|---|---|---|
| Arizona Public Service Co (AZ) | 80.86 | 1,395,614 | IEEE 1366 |
| Salt River Project (AZ) | 52.81 | 1,161,925 | IEEE 1366 |
| Tucson Electric Power Co (AZ) | 68.36 | 455,579 | IEEE 1366 |
| UNS Electric, Inc (AZ) | 60.13 | 106,739 | IEEE 1366 |
Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.
Forward resource adequacy (assessed): Adequacy flagged
Phoenix and the desert Southwest face extreme summer cooling peaks that strain supply; utilities have managed them so far, but heat-driven peak stress is the standing forward risk.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
modelled
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 67.88 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across 4 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Outlook drivers
↑ Upgrade triggers
- Continued solar-plus-storage build lowers carbon and firms the peak.
- Sustained absorption converts the pipeline.
↓ Downgrade triggers
- Water and extreme-heat constraints.
- Transmission limits slow new connections.
Evidence behind this rating
The real-world events that test our Tier 2 call for Desert Southwest (Phoenix): 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
The Desert Southwest is now one of the fastest-growing US data-center markets on land, solar and a pro-build posture.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Not assessed | We hold no evidence for this yet |
| Connection | Broad (M1) | Directional: good for screening and monitoring |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Not assessed | We hold no evidence for this yet |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 2 data layers directly measured; the rest are triangulated or modelled
Coverage
Substantial
2 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 4 of 4 territories, 100% of customers, regional context only) |
| Interconnection queue | modelled | end-2025 (LBNL 2026) | Fresh | LBNL Queued Up 2026 |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Historical utility-territory delivery performance 67.88 minutes per year (2024)
- Forward resource adequacy (assessed)
- Typical interconnection wait about 39 months (generation and storage queue, not a load wait; non-ISO West median, projects online 2018 to 2025; not specific to this market)
What is open
- Contractual service terms (would change the answer)
- Designed site resilience
- Cost evidence (would change the answer)
- Regulatory evidence
- Substation-level capacity evidence
How service and connection are organized
Territories in this market, each with its own filed record: Arizona Public Service Co, Salt River Project, Tucson Electric Power Co, UNS Electric, Inc. Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Schedule: interconnection queues here run about 39 months for generation and storage (non-ISO West median, projects online 2018 to 2025; not specific to this market); a large load follows a different process and we do not hold its measured distribution
What could disqualify this market
- Summer extreme heat and cooling-peak reliability.
- Water availability for cooling.
Questions to put to the utility
- What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project caseWhy it is open: no compiled cost band for this market yet.
- Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?Why it is open: no dated regulatory read compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/desert-southwest/gaps