⚡ POWERGRIDIQ · EVIDENCE PACK

ERCOT (Texas)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/ercot, with every section open. As of June 2026.

Back to the report

Recurring cost across modelled locations

$42–95 /MWh
Low from ERCOT West (West Texas & Panhandle), high from ERCOT Central (Houston & DFW). No regional midpoint is published.
ERCOT West (West Texas & Panhandle)$42–80 /MWh
ERCOT Central (Houston & DFW)$55–95 /MWh

Not market-wide coverage. This is NOT market-wide coverage of every location in this region. It is the range across the locations named in `derived_from`, and a site elsewhere in the region may fall outside it. Use the constituent market records for a location-specific figure.

A parent midpoint would assert a typical site for the whole region. PowerGridIQ models specific locations, not a regional average, so no midpoint is published. How this is built →

Forward cost anchor

Siting a load is a decade-long cost bet, so the forward cost of firm capacity matters more than today's spot price. This is the public capacity-auction clearing price, the market's own forward read, not a paywalled forward curve.

Forward cost pressure

Elevated

Latest capacity clearing price

no capacity market (energy-only)

ongoing

Trend: No capacity auction; the forward signal comes from scarcity pricing and forward energy, not a clearing price.

ERCOT is an energy-only market with no capacity auction, so the forward cost of firm capacity is signaled through scarcity pricing (the operating-reserve demand curve) and forward energy rather than a clearing price. NERC rates ERCOT high-risk for forward adequacy from about 2029.

Source: NERC 2025 Long-Term Reliability Assessment (Jan 2026). A derived indicator: we publish the public clearing price and our read, never paywalled exchange data.

Interconnection queue (the line to connect to the grid)

These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.

Active queue depth

408 GW

Typical wait

30 months

What builds the 30-month wait

3
9
18
Application & screening3 mo
Interconnection study & agreement9 mo
Construction & energization18 mo
Typical time to energization30 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (ERCOT interconnection process).

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

The five pillars behind the tier

Access30%88

Open and fast. The Texas grid operator (ERCOT) lets a large new load connect quickly and then manages any constraints, on the condition that it can be dialled back when the grid is tight, rather than making it wait years for firm supply. This is one of the quickest paths to power anywhere.

Availability25%62

Tight at peak but workable: summer scarcity is real, but cheap on-site gas (behind-the-meter) floors the practical availability for a developer who can self-supply.

Cost25%83

Cheap power and the cheapest self-supply: low wholesale plus abundant gas make Texas one of the lowest recurring-cost markets for a large load.

Momentum15%80

Proven momentum: more than 1 GW of data-center capacity and widely called 'the next Virginia'; ~233 GW of large-load interconnection requests, over 70% data centers.

Carbon5%55

Carbon is the weak pillar (~310 g/kWh, gas-heavy). It barely moves the default rating, but a carbon-weighted preset would lower ERCOT's score.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

National reliability adjustment: the five-pillar score of 78 is reduced to 70, a deduction of 8 points. A national overview carries the average of its rated regions’ reliability adjustments (ERCOT West (West Texas & Panhandle) 8, ERCOT Central (Houston & DFW) 8), because a national view has to represent all of them, not only the strongest. The region pages carry the actionable ratings and their own adjustments. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

Extreme-cold fragility was demonstrated in Winter Storm Uri (Feb 2021), when ERCOT ordered about 20,000 MW of rolling blackouts, the largest manual load shed in US history, with outages lasting days; freezing and fuel issues drove roughly 76% of unit failures. Post-Uri winterization rules have improved subsequent winter performance but the tail risk remains.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

event-based · FERC/NERC Feb 2021 cold weather final report

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 97.52 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 10 territories, 100% of customers, regional context only)

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. mixed methods: IEEE 60%; respondent-defined 40% of customers. Major event days are excluded throughout; the methods differ only in how those days are identified, a smaller difference than the spread between the utilities themselves. Constituents below carry their own standard. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment (being told to cut output or consumption) rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

The territories inside this market

The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.

Territory operatorSAIDI min/yrCustomersMajor-event method
Oncor Electric Delivery Company LLC (TX)67.284,013,062own method
CenterPoint Energy (TX)150.092,847,806IEEE 1366
City of San Antonio - (TX) (TX)61.8938,905IEEE 1366
AEP Texas Central Company (TX)149.6913,164IEEE 1366
Austin Energy (TX)76.03557,039IEEE 1366
Pedernales Electric Coop, Inc (TX)57.44425,109IEEE 1366
Denton County Elec Coop, Inc (TX)26.9319,523IEEE 1366
Texas-New Mexico Power Co (TX)118.37268,934own method
AEP Texas North Company (TX)102.6199,119IEEE 1366
Bluebonnet Electric Coop, Inc (TX)117.15132,597IEEE 1366

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Tight

NERC's 2024 Long-Term Reliability Assessment rates ERCOT elevated-risk: about 20 GW of new large loads plus a more variable, less dispatchable resource mix raise the risk of long-term shortfalls.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

assessed · NERC 2024 Long-Term Reliability Assessment

Contractual service terms: interruptible available

ERCOT's open-and-fast access is explicitly conditioned on a large load accepting curtailment when the grid is tight, so the fast route to power is a non-firm route. Firm service is a different, slower product.

What the service contract promises, as distinct from how the system has performed · ERCOT large flexible load standards

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 97.52 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across 10 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 10 territories, 100% of customers, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Favourableunder review (PUCT large-load rule)

Why: Energy-only connect-and-manage (connect first, ease congestion later) keeps ERCOT the fastest large-load path in the US; the regulatory watch is readiness-tested queue management (a 75 MW threshold and posted security), not closure.

What would change the read: Restrictive new large-load interconnection rules following a major reliability event.

For new supply: Energy-only connect-and-manage is the fastest generation build path in the US, which is why supply and demand are racing each other here.

Beyond the grid: Water and local consent are the main non-grid frictions: a University of Texas poll found 56 percent of Texas voters, and 62 percent in rural areas, oppose a data centre in their community, and the state still does not require most centres to report water use even as it faces scarcity. Texas Tribune UT Austin

Outlook drivers

↑ Upgrade triggers

  • Sustained build converts the large-load queue into operating capacity without reliability backlash.
  • Continued battery and solar additions lower carbon and ease the peak.

↓ Downgrade triggers

  • A repeat of a Winter-Storm-Uri-scale reliability event triggers restrictive large-load rules.
  • Political limits on new large-load interconnection.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
From about 2029
NERC flags an elevated energy-shortfall risk as large-load growth outpaces firm supply
The adequacy inflection a multi-year siting decision should price in, even with today's fast energization.

Evidence behind this rating

The real-world events that test our Tier 2 call for ERCOT (Texas): 6 support it and 2 challenge it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

ERCOT issues Batch Zero conditional classifications, restarting the process it paused on 3 Aug ANNOUNCED ✓ Supports the rating
Sep 2026AccessMateriality: high

Market notice M-A080326-04, 3 Sep 2026. ERCOT told each interconnecting DSP and TSP which of its large loads are conditionally included in Batch Zero, subject to conditions such as the load passing verification, curing deficiencies in dynamic model data, or the PUCT granting a good cause exception. Disputes over a provisional classification run under Planning Guide 9.3.1(2)(a). ERCOT stated it will not seek a good cause exception for every large load that requested one, and that failure to satisfy any applicable condition may disqualify the load from Batch Zero.

Power to a buyer: No supply added. This is a queue step: it tells named loads whether they are provisionally inside Batch Zero, and every inclusion is conditional. Energization still waits on a verification exercise ERCOT expects to take several months, so nothing here moves an electron.
Source: ERCOT market notice M-A080326-04 ↗
PUCT approves the routes for the first extra-high-voltage lines in Texas CONTRACTED ✓ Supports the rating
Aug 2026AvailabilityMateriality: med

On 28 Aug 2026 the commission voted unanimously to approve two Oncor certificate amendments and final routes for ultrahigh voltage lines running southwest from Bosque County, west of Dallas Fort Worth, allowing construction to begin. These are the first projects under the 2023 Permian Basin Reliability Plan to clear regulatory approval, over recorded opposition from landowners and some state legislators.

Power to a buyer: No power now. Routes are fixed and construction is authorised, so this is a committed transmission build rather than a proposal, but lines of this voltage are a late-decade delivery. It widens the pipe into West Texas eventually; it adds no generation at all.
Source: Texas Tribune ↗
PUCT hearing bounds the scope of the data center audit; ERCOT still targets April 2027 for Batch Zero ANNOUNCED ✓ Supports the rating
Aug 2026AccessMateriality: high

At a special PUCT open meeting on 14 Aug 2026, ERCOT officials said the verification audit ordered by Gov. Abbott covers the data center projects in the Batch Zero study, will take several months, and is confined to that study. ERCOT general counsel Chad Seely said the work was already planned as spot checks and has been moved to the front of the interconnection study process. ERCOT still aims to complete the first batch study by its original April 2027 deadline.

Power to a buyer: No new supply. This bounds a delay rather than adding capacity: a verification step over the Batch Zero projects, running several months, with ERCOT still targeting April 2027 for the Batch Zero study. The binding constraint is queue processing time.
Source: Texas Tribune ↗
BNEF puts a large share of the US data center pipeline at risk of delay from the Texas pause ANNOUNCED ▲ Challenges the rating
Aug 2026MomentumMateriality: med

BloombergNEF estimated on 5 Aug 2026 that the Texas interconnection pause exposes a large share of the US data center pipeline, with leasing revenue at risk. BNEF also forecasts substantial ERCOT data center additions through 2030. All figures are BNEF estimates, not measured outcomes.

Power to a buyer: Nothing is delivered or lost by an estimate. The capacity at risk and the revenue exposure are BloombergNEF model outputs, not measured outcomes, and no capacity changes because of them.
Source: Utility Dive / BloombergNEF ↗
Texas orders a verification step before any data center large load advances; ERCOT misses the Batch Zero classification date ▲ Challenges the rating
Aug 2026AccessMateriality: high

ERCOT received a letter from Gov. Greg Abbott on 3 Aug 2026 directing it to conduct a verification process before advancing any data center Large Loads through interconnection. ERCOT confirmed it did not notify interconnecting TSPs and DSPs of Batch Zero classifications by the scheduled 7 Aug 2026 date, and will file a good cause exception request ahead of the PUCT open meeting on 20 Aug 2026. Duration and scope of the verification step are not yet defined.

Power to a buyer: A delay of unknown length: no data center large load advances through ERCOT interconnection until the verification step is done, and its duration and scope are not yet defined. No supply changes.
Source: ERCOT market notice M-A080326-01 ↗
PUCT approves ERCOT's Batch Zero process for connecting large loads ✓ Supports the rating
Jun 2026AccessMateriality: med

The PUCT approved (18 Jun 2026) ERCOT's Batch Zero framework, which studies readiness-screened large loads in batches with a Jul 2026 cutoff for the 2028-2032 study. Formal regulatory sign-off on the readiness-tested queue.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: ERCOT / PUCT ↗
GW Ranch in Pecos County wins its state air permit as a private-grid gas campus that will not connect to ERCOT ANNOUNCED
Jan 2026MomentumMateriality: low

Pacifico Energy announced on 26 Jan 2026 that the Texas Commission on Environmental Quality had issued the air permit for GW Ranch, a gas-fired power campus with battery storage and solar in Pecos County, built to supply co-located hyperscale data centres. Pacifico says the campus will operate independently of the electricity grid, will not draw from or add load to the ERCOT grid, and needs no new utility transmission lines. It targets first power in the first half of 2027. Logged as announced: the permit is in hand, but we have found no owner confirmation that major construction has started. This is a self-supply path for one campus, not new supply for the market.

Power to a buyer: Nothing for an ERCOT grid buyer. The plant is private-grid by design, so it counts as no supply to the ERCOT grid however large its permit. What it shows is a large load sidestepping the connection queue by building its own generation.
Source: Pacifico Energy ↗
ERCOT moves to readiness-tested large-load queue management as requests climb further ✓ Supports the rating
Jun 2026AccessMateriality: med

The large-load queue kept climbing through the first half of 2026, and ERCOT introduced evidence-based readiness screens (site control, permits, financing, equipment orders) to separate committed builds from speculative ones. A market disciplining a queue this large is one where large loads genuinely want to build, supporting the rating.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Utility Dive ↗
ERCOT large-load requests surge year-on-year ✓ Supports the rating
Dec 2025Momentum / AvailabilityMateriality: med

Most requests come from data centers, and ERCOT's large-load outlook for 2030 has the demand side racing as fast as supply. Demand at this scale choosing Texas confirms the cheap, fast-to-connect profile behind the strong rating.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: ERCOT ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Sep 2026
Under reviewReview stays open, and is narrower than it was in August. The pathway is moving again: ERCOT has issued provisional Batch Zero classifications, which is more than the August entry could assume. But inclusion is conditional, energization still waits on a verification exercise ERCOT expects to take several months with no stated end date, and ERCOT has said it will not pursue every good cause exception requested, so some loads submitted in good faith will not make this batch. Tier 2 holds. Resolve when verification outcomes are published rather than on a calendar date.
Trigger: ERCOT Batch Zero conditional classifications, market notice M-A080326-04, 3 Sep 2026
Aug 2026
Under reviewTier not moved, but the connection pathway that underpins the Access score is paused with no stated end date. A verification gate applied to every data center large load, layered on Batch Zero, is a material change in how fast a large load can reach energization in the market we score as the fastest in the US. Direction is genuinely uncertain: a short verification exercise leaves the tier intact, a durable screening regime does not. Resolve after the PUCT open meeting on 20 Aug 2026. Update, Sep 2026: that date no longer applies; the September 2026 entry resolves the review when ERCOT publishes verification outcomes.
Trigger: Gov. Abbott directive and ERCOT market notice M-A080326-01, 3 Aug 2026; missed Batch Zero classification date, 7 Aug 2026
Jun 2026
AffirmedLarge-load demand surge reviewed; fast connect-and-manage energization and cheap self-supply gas keep the fundamentals strong.
Trigger: ERCOT large-load requests reach ~233 GW (Dec 2025)
Jul 2026
DowngradeUnder the v2 reliability overlay, ERCOT is held at Tier 2. Fundamentals remain strong (78) and connect-and-manage energization is still the fastest large-load path in the US, but a NERC elevated-risk forward outlook plus the Winter Storm Uri record cap it below Prime.
Trigger: Methodology v2 reliability overlay; NERC 2024 Long-Term Reliability Assessment elevated-risk finding
Jul 2026
AffirmedTier holds. Formal PUCT approval of Batch Zero adds regulatory certainty to large-load access; queue discipline supports, not weakens, the rating.
Trigger: PUCT approval of Batch Zero, 18 Jun 2026
Oct 2026
AffirmedAffirmed, no change, 23 Oct 2026. ERCOT began issuing Batch Zero verification requests on 9 Sep 2026 and has not yet published verification outcomes. Inclusion stays conditional, but the pathway is moving, so tier and outlook are held. A durable screening regime that excludes good-faith loads would be grounds to revisit Access.
Trigger: Gov. Abbott directive and ERCOT market notice M-A080326-01, 3 Aug 2026; Batch Zero conditional classifications, 3 Sep 2026; Batch Zero verification requests, market notice M-A090926-01, 9 Sep 2026
June 2026
New ratingNew rating: assigned, split into West and Central sub-regions.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

All 3 data layers are directly measured

Coverage

Substantial

2 of 3 dimensions: reliability, connection, cost

Last reviewed

23 Oct 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 10 territories, 100% of customers, regional context only)
Forward costmeasuredongoingFreshNERC 2025 Long-Term Reliability Assessment (Jan 2026)
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshLBNL Queued Up 2026

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.