ERCOT (Texas)
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/ercot, with every section open. As of June 2026.
Recurring cost across modelled locations
Not market-wide coverage. This is NOT market-wide coverage of every location in this region. It is the range across the locations named in `derived_from`, and a site elsewhere in the region may fall outside it. Use the constituent market records for a location-specific figure.
A parent midpoint would assert a typical site for the whole region. PowerGridIQ models specific locations, not a regional average, so no midpoint is published. How this is built →
Forward cost anchor
Forward cost pressure
Elevated
Latest capacity clearing price
no capacity market (energy-only)
ongoing
ERCOT is an energy-only market with no capacity auction, so the forward cost of firm capacity is signaled through scarcity pricing (the operating-reserve demand curve) and forward energy rather than a clearing price. NERC rates ERCOT high-risk for forward adequacy from about 2029.
Source: NERC 2025 Long-Term Reliability Assessment (Jan 2026). A derived indicator: we publish the public clearing price and our read, never paywalled exchange data.
Interconnection queue (the line to connect to the grid)
Active queue depth
408 GW
Typical wait
30 months
What builds the 30-month wait
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Open and fast. The Texas grid operator (ERCOT) lets a large new load connect quickly and then manages any constraints, on the condition that it can be dialled back when the grid is tight, rather than making it wait years for firm supply. This is one of the quickest paths to power anywhere.
Tight at peak but workable: summer scarcity is real, but cheap on-site gas (behind-the-meter) floors the practical availability for a developer who can self-supply.
Cheap power and the cheapest self-supply: low wholesale plus abundant gas make Texas one of the lowest recurring-cost markets for a large load.
Proven momentum: more than 1 GW of data-center capacity and widely called 'the next Virginia'; ~233 GW of large-load interconnection requests, over 70% data centers.
Carbon is the weak pillar (~310 g/kWh, gas-heavy). It barely moves the default rating, but a carbon-weighted preset would lower ERCOT's score.
Reliability overlay
Historical bulk-system performance: Minor flags found
Extreme-cold fragility was demonstrated in Winter Storm Uri (Feb 2021), when ERCOT ordered about 20,000 MW of rolling blackouts, the largest manual load shed in US history, with outages lasting days; freezing and fuel issues drove roughly 76% of unit failures. Post-Uri winterization rules have improved subsequent winter performance but the tail risk remains.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based · FERC/NERC Feb 2021 cold weather final report
Historical utility-territory delivery performance: No reliability flags found
Average customer interruption (SAIDI) of 97.52 minutes per year in 2024, excluding major event days as filed.
The territories inside this market
The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.
| Territory operator | SAIDI min/yr | Customers | Major-event method |
|---|---|---|---|
| Oncor Electric Delivery Company LLC (TX) | 67.28 | 4,013,062 | own method |
| CenterPoint Energy (TX) | 150.09 | 2,847,806 | IEEE 1366 |
| City of San Antonio - (TX) (TX) | 61.8 | 938,905 | IEEE 1366 |
| AEP Texas Central Company (TX) | 149.6 | 913,164 | IEEE 1366 |
| Austin Energy (TX) | 76.03 | 557,039 | IEEE 1366 |
| Pedernales Electric Coop, Inc (TX) | 57.44 | 425,109 | IEEE 1366 |
| Denton County Elec Coop, Inc (TX) | 26.9 | 319,523 | IEEE 1366 |
| Texas-New Mexico Power Co (TX) | 118.37 | 268,934 | own method |
| AEP Texas North Company (TX) | 102.6 | 199,119 | IEEE 1366 |
| Bluebonnet Electric Coop, Inc (TX) | 117.15 | 132,597 | IEEE 1366 |
Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.
Forward resource adequacy (assessed): Tight
NERC's 2024 Long-Term Reliability Assessment rates ERCOT elevated-risk: about 20 GW of new large loads plus a more variable, less dispatchable resource mix raise the risk of long-term shortfalls.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
assessed · NERC 2024 Long-Term Reliability Assessment
Contractual service terms: interruptible available
ERCOT's open-and-fast access is explicitly conditioned on a large load accepting curtailment when the grid is tight, so the fast route to power is a non-firm route. Firm service is a different, slower product.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 97.52 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across 10 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Regulatory momentum
Why: Energy-only connect-and-manage (connect first, ease congestion later) keeps ERCOT the fastest large-load path in the US; the regulatory watch is readiness-tested queue management (a 75 MW threshold and posted security), not closure.
What would change the read: Restrictive new large-load interconnection rules following a major reliability event.
For new supply: Energy-only connect-and-manage is the fastest generation build path in the US, which is why supply and demand are racing each other here.
Beyond the grid: Water and local consent are the main non-grid frictions: a University of Texas poll found 56 percent of Texas voters, and 62 percent in rural areas, oppose a data centre in their community, and the state still does not require most centres to report water use even as it faces scarcity. Texas Tribune UT Austin
Outlook drivers
↑ Upgrade triggers
- Sustained build converts the large-load queue into operating capacity without reliability backlash.
- Continued battery and solar additions lower carbon and ease the peak.
↓ Downgrade triggers
- A repeat of a Winter-Storm-Uri-scale reliability event triggers restrictive large-load rules.
- Political limits on new large-load interconnection.
Scheduled to change
Evidence behind this rating
The real-world events that test our Tier 2 call for ERCOT (Texas): 6 support it and 2 challenge it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
Market notice M-A080326-04, 3 Sep 2026. ERCOT told each interconnecting DSP and TSP which of its large loads are conditionally included in Batch Zero, subject to conditions such as the load passing verification, curing deficiencies in dynamic model data, or the PUCT granting a good cause exception. Disputes over a provisional classification run under Planning Guide 9.3.1(2)(a). ERCOT stated it will not seek a good cause exception for every large load that requested one, and that failure to satisfy any applicable condition may disqualify the load from Batch Zero.
On 28 Aug 2026 the commission voted unanimously to approve two Oncor certificate amendments and final routes for ultrahigh voltage lines running southwest from Bosque County, west of Dallas Fort Worth, allowing construction to begin. These are the first projects under the 2023 Permian Basin Reliability Plan to clear regulatory approval, over recorded opposition from landowners and some state legislators.
At a special PUCT open meeting on 14 Aug 2026, ERCOT officials said the verification audit ordered by Gov. Abbott covers the data center projects in the Batch Zero study, will take several months, and is confined to that study. ERCOT general counsel Chad Seely said the work was already planned as spot checks and has been moved to the front of the interconnection study process. ERCOT still aims to complete the first batch study by its original April 2027 deadline.
BloombergNEF estimated on 5 Aug 2026 that the Texas interconnection pause exposes a large share of the US data center pipeline, with leasing revenue at risk. BNEF also forecasts substantial ERCOT data center additions through 2030. All figures are BNEF estimates, not measured outcomes.
ERCOT received a letter from Gov. Greg Abbott on 3 Aug 2026 directing it to conduct a verification process before advancing any data center Large Loads through interconnection. ERCOT confirmed it did not notify interconnecting TSPs and DSPs of Batch Zero classifications by the scheduled 7 Aug 2026 date, and will file a good cause exception request ahead of the PUCT open meeting on 20 Aug 2026. Duration and scope of the verification step are not yet defined.
The PUCT approved (18 Jun 2026) ERCOT's Batch Zero framework, which studies readiness-screened large loads in batches with a Jul 2026 cutoff for the 2028-2032 study. Formal regulatory sign-off on the readiness-tested queue.
Pacifico Energy announced on 26 Jan 2026 that the Texas Commission on Environmental Quality had issued the air permit for GW Ranch, a gas-fired power campus with battery storage and solar in Pecos County, built to supply co-located hyperscale data centres. Pacifico says the campus will operate independently of the electricity grid, will not draw from or add load to the ERCOT grid, and needs no new utility transmission lines. It targets first power in the first half of 2027. Logged as announced: the permit is in hand, but we have found no owner confirmation that major construction has started. This is a self-supply path for one campus, not new supply for the market.
The large-load queue kept climbing through the first half of 2026, and ERCOT introduced evidence-based readiness screens (site control, permits, financing, equipment orders) to separate committed builds from speculative ones. A market disciplining a queue this large is one where large loads genuinely want to build, supporting the rating.
Most requests come from data centers, and ERCOT's large-load outlook for 2030 has the demand side racing as fast as supply. Demand at this scale choosing Texas confirms the cheap, fast-to-connect profile behind the strong rating.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
Source strength
High
All 3 data layers are directly measured
Coverage
Substantial
2 of 3 dimensions: reliability, connection, cost
Last reviewed
23 Oct 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 10 territories, 100% of customers, regional context only) |
| Forward cost | measured | ongoing | Fresh | NERC 2025 Long-Term Reliability Assessment (Jan 2026) |
| Interconnection queue | measured | end-2025 (LBNL 2026) | Fresh | LBNL Queued Up 2026 |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.