ERCOT Central (Houston & DFW)
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/ercot-central, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$55 to $95 per MWh
Midpoint about $72 per MWh
What builds the $72 midpoint
Where the cost lands
The Central sub-region costs more than the west, but the power actually reaches the site; deliverability is what the premium buys.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: ERCOT 2024 load-zone prices (Modo Energy).
Connection friction
Friction level
Low
This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.
ERCOT's energy-only, connect-and-manage framework is the fastest large-load path in the US, and the Central load pockets (Houston, DFW) pair it with robust transmission so a firm load can actually draw its power. A 75 MW readiness threshold and posted security now apply, but there is no capacity-market queue to clear.
What builds the 24-month wait
Data-center share of demand pressure: Rising. Sources: ERCOT interconnection process · ERCOT large loads. The full cross-market connection dataset is available through the Connection Friction Feed.
The five pillars behind the tier
Strong access: Houston and North (DFW) have low congestion, generation sited near demand, and more robust transmission than the west, plus ERCOT's fast connect-and-manage energization.
Availability is workable with cheap self-supply gas; the load pockets are gas-served and dense.
Higher cost than the west, but still low by national standards; deliverability is the reason to pay it.
Highest momentum in ERCOT: the DFW and Houston corridors anchor the Texas data-center build.
Carbon is the weak pillar (gas-heavy load pockets), immaterial in the default lens.
Reliability overlay
Historical bulk-system performance: Minor flags found
ERCOT-wide assessment applied to the Central sub-region: Winter Storm Uri (Feb 2021) forced about 20,000 MW of rolling blackouts, the largest manual load shed in US history; post-Uri winterization has improved winter performance but the tail risk remains. The Houston and DFW load pockets have robust local transmission, a deliverability strength captured in the access pillar.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based · FERC/NERC Feb 2021 cold weather final report
Historical utility-territory delivery performance: No reliability flags found
Average customer interruption (SAIDI) of 98.33 minutes per year in 2024, excluding major event days as filed.
The territories inside this market
The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.
| Territory operator | SAIDI min/yr | Customers | Major-event method |
|---|---|---|---|
| Oncor Electric Delivery Company LLC (TX) | 67.28 | 4,013,062 | own method |
| CenterPoint Energy (TX) | 150.09 | 2,847,806 | IEEE 1366 |
| Denton County Elec Coop, Inc (TX) | 26.9 | 319,523 | IEEE 1366 |
Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.
Forward resource adequacy (assessed): Tight
NERC's 2024 Long-Term Reliability Assessment rates ERCOT elevated-risk grid-wide: about 20 GW of new large loads plus a more variable resource mix raise the risk of long-term shortfalls across the interconnection.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
assessed · NERC 2024 Long-Term Reliability Assessment
Contractual service terms: interruptible available
ERCOT-wide: fast access is conditioned on accepting curtailment at system peaks; the 4CP transmission mechanism further rewards curtailing at the four coincident annual peaks.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 98.33 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across 3 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Supply relief outlook
What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.
Regulatory momentum
Why: The same open, energy-only connect-and-manage framework as ERCOT statewide, applied where the transmission is robust and the load pockets are well served.
What would change the read: Restrictive new large-load interconnection rules following a major reliability event.
For new supply: The same fast energy-only build path, applied where transmission is robust and the load pockets are well served.
Beyond the grid: Water and community consent bind in Central Texas: the San Antonio to Austin corridor quadrupled data-centre development from 2023 to 2025 as Edwards Aquifer levels hit historic lows, Hays County advocates are protesting five proposed sites, and San Marcos City Council voted a data centre down outright. KUT TPR
Outlook drivers
↑ Upgrade triggers
- Continued DFW and Houston build converts the queue into operating capacity.
- Battery and solar additions ease the summer peak.
↓ Downgrade triggers
- Load-pocket congestion rises as demand concentrates.
- A Winter-Storm-Uri-scale event triggers restrictive large-load rules.
Rating history
What this would mean for a project
100 MW contracted demand, 95% load factor, HV servicecalculated
A load of this shape consumes 832,200 MWh a year. At the delivered band of $55 to $95/MWh that is $45,771,000 to $79,059,000 a year in recurring power.
Wholesale energy is 72% of the delivered cost here. The other $20/MWh is transmission and delivery (4CP), and ancillary services. See the full build-up.
Typical connection wait is 1 to 2 years, at Med confidence.
Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Broad (M1) | Directional: good for screening and monitoring |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 3 of 3 territories, 100% of customers, regional context only) |
| Connection friction | proxy | 2025/26 | Fresh | ERCOT interconnection process |
| Realized cost | triangulated | 2026 | Fresh | ERCOT 2024 load-zone prices (Modo Energy) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $55 to $95 per MWh, midpoint $72, basis triangulated, against the 100 MW archetype
- Historical utility-territory delivery performance 98.33 minutes per year (2024)
- Historical bulk-system performance (event-based)
- Forward resource adequacy (assessed)
- Contractual service terms (reported)
What is open
- Designed site resilience
- Substation-level capacity evidence
How service and connection are organized
Territories in this market, each with its own filed record: Oncor Electric Delivery Company LLC, CenterPoint Energy, Denton County Elec Coop, Inc. Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Cost $55 to $95 per MWh, midpoint $72 (triangulated)
What could disqualify this market
- Summer scarcity pricing and peak reliability.
- Rising large-load concentration in the corridors.
Questions to put to the utility
- What is the average carbon intensity of the grid supply we would draw, for which year, and is it measured or derived from the fuel mix?Why it is open: no grid snapshot compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/ercot-central/gaps