Finland
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/finland, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$42 to $78 per MWh
Midpoint about $58 per MWh
What builds the $58 midpoint
Where the cost lands
Finland has the lowest non-household electricity prices in the European Union, helped by nuclear and Nordic hydro. That gives a large load a low, stable band, with the main variability coming from cold-snap winter peaks.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Non-household electricity prices, Finland lowest (Eurostat).
Connection friction
Friction level
Low
This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.
Finland pairs low-carbon power with available grid capacity and is drawing large builds such as XTX's Kajaani campus (22 MW connecting in 2026, up to 250 MW at full capacity). The Nordic surplus is falling as regional demand grows, but Finland remains among the more connectable European markets.
What builds the 24-month wait
Data-center share of demand pressure: Rising. Sources: Argus: Nordic data centres and power demand. The full cross-market connection dataset is available through the Connection Friction Feed.
The five pillars behind the tier
Open and welcoming to data centers.
Good availability (nuclear plus wind plus imports).
Competitive cost.
Real momentum (Microsoft-anchored).
Very clean (~20-70 g).
Reliability overlay
Historical bulk-system performance: No reliability flags found
Since Olkiluoto 3 (about 1.6 GW) reached regular output in 2023, national resource-adequacy assessments show no concern against the reliability standard (LOLE 2.1 hours/year), and OL3's early-years reliability was high in international comparison.
Historical utility-territory delivery performance: No reliability flags found
Forward resource adequacy (assessed): No adequacy flags
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Regulatory momentum
Why: From 1 July 2026 Finland moves data-centre electricity from the lower tax category II to the general category I, raising the power tax by about 2.19 cents per kWh, and Fingrid is restricting new connections in some areas until 2027 while it consults on the KJV2026 demand-connection code (draft 12 June 2026). A replacement incentive for value-added data centres is due in autumn 2026.
What would change the read: The autumn 2026 incentive scheme and Fingrid's capacity build offsetting the tax rise for large, heat-integrated loads.
Beyond the grid: Finland leads on turning data-centre waste heat into district heating: Fortum captures heat from large Espoo-area sites to supply about 40 percent of its regional demand, a real offset to siting friction. AFRY
Outlook drivers
↑ Upgrade triggers
- Hyperscaler build scales.
- Heat-reuse incentives add value.
↓ Downgrade triggers
- Cold-snap peaks and import dependence.
- Small-market scale limits.
Evidence behind this rating
The real-world events that test our Tier 1 call for Finland: 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
Microsoft is developing a southern-Finland data-center region across Espoo, Kirkkonummi and Vihti, with a Fortum partnership to reuse server heat as district heating for tens of thousands of homes, one of the world's largest such schemes, and has secured land near Vaasa for a second site. Sustained hyperscale investment confirms the clean, low-cost, reliable profile behind the rating.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
What this would mean for a project
100 MW contracted demand, 95% load factor, HV servicecalculated
A load of this shape consumes 832,200 MWh a year. At the delivered band of $42 to $78/MWh that is $34,952,400 to $64,911,600 a year in recurring power.
Wholesale energy is 66% of the delivered cost here. The other $20/MWh is network charges, and taxes and levies. See the full build-up.
Typical connection wait is 1 to 3 years, at Med confidence.
Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Broad (M1) | Directional: good for screening and monitoring |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | measured | 2025 | Fresh | Finnish EPR starts supplying electricity (WNN) |
| Connection friction | proxy | 2025/26 | Fresh | Argus: Nordic data centres and power demand |
| Realized cost | triangulated | 2026 | Fresh | Non-household electricity prices, Finland lowest (Eurostat) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $42 to $78 per MWh, midpoint $58, basis triangulated, against the 100 MW archetype
- Historical bulk-system performance (measured)
What is open
- Forward resource adequacy (assessed)
- Historical utility-territory delivery performance (would change the answer)
- Contractual service terms (would change the answer)
- Designed site resilience
- Substation-level capacity evidence
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Cost $42 to $78 per MWh, midpoint $58 (triangulated)
What could disqualify this market
- Winter peak and import reliance.
- Scale.
Questions to put to the utility
- What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project caseWhy it is open: no regulator outage series compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/finland/gaps