⚡ POWERGRIDIQ · EVIDENCE PACK

Germany North (Hamburg)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/germany-north, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$100 to $145 per MWh

Midpoint about $116 per MWh

How this band was built

triangulated

From 3 public fragments

What builds the $116 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$88
$20
Wholesale energy$88
Network & grid fees$20
Taxes & levies (after industrial relief)$8
All-in delivered$116 /MWh
How the $116/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. The northern zone is the cheaper German band because it is closer to wind generation; grid fees and levies stack on the wholesale price, partly offset by the industrial-price relief scheme. Anchored to published figures (EU electricity price components (Eurostat)). How this is built →
What the classes mean →

Where the cost lands

$116
Low $100Midpoint $116High $145
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Wholesale energy near 85 euros per MWh, plus grid fees and levies, partly offset by the industrial-price relief scheme.

A large German load pays the wholesale price plus substantial grid fees and levies. The northern zone is the cheaper of the two German bands because it is closer to wind generation and less network-constrained.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: EU industrial electricity prices (IEA Electricity 2026) · Non-household electricity prices (Eurostat).

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

High

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

Wind-rich north has the power, but a congested grid and long link lead times.

The northern zones carry Germany's wind surplus and are the favored siting region, but the transmission grid that moves that power is congested and new high-voltage links carry lead times of about 8 to 12 years. Access is easier than the south in principle, still multi-year in practice.

What builds the 78-month wait

12
42
18
Application & queue position6 mo
Grid study & connection offer12 mo
Network reinforcement / transmission build42 mo
Construction & energization18 mo
Typical time to energization78 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Global Data Center Hub: grid delays repricing Europe).

Data-center share of demand pressure: High. Sources: IEA: energy constraints on Europe's data centres · Global Data Center Hub: grid delays repricing Europe. The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%58

Better access: the north hosts surplus generation and spare network capacity, though export south is constrained until SuedLink; connection is workable.

Availability25%72

Strong availability: onshore and offshore wind run a surplus, with frequent curtailment when the south cannot absorb it.

Cost25%54

Cost is the national wholesale price: Germany is a single bidding zone, so the north shares the same price as the south (its advantage is physical, not price).

Momentum15%50

Lower momentum than Frankfurt: less revealed data-center build so far, though growing near the coastal cable landings.

Carbon5%55

Cleaner power locally: wind-heavy generation gives the north a lower carbon profile than the gas-and-import-leaning south.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability reviewed: no material concerns were found, so the rating is unchanged. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: No reliability flags found

Germany's delivery reliability is world-class (about 12.8 minutes average interruption in 2023), and the north runs a generation surplus.

measured · German supply reliability (Clean Energy Wire)

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 11.7 minutes per year in 2024, excluding major event days as filed.

measured · Bundesnetzagentur SAIDI 2024

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. BNetzA national SAIDI across roughly 880 German DSOs. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

Forward resource adequacy (assessed): No adequacy flags

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 11.7 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across several territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: Bundesnetzagentur SAIDI 2024

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Easing
Demand pressure
Moderate load growth competing for the same capacity.
Can new supply arrive
Regulatory momentum mixed, improving.

What this means: The supply crunch looks likely to ease for a new load energizing here in the coming years.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed↑ improving

Why: Northern Germany has surplus wind but the binding constraint is grid access, which the national data-centre strategy (18 March 2026) names as the decisive factor for 2026 to 2030; the Energy Efficiency Act requires 100 percent renewable balance-sheet coverage from 1 January 2027 and waste-heat reuse. Hamburg and the north sit closer to generation than the fully allocated southern hubs.

What would change the read: SuedLink and northern grid reinforcement converting surplus wind into firm, connectable capacity for large loads.

Outlook drivers

↑ Upgrade triggers

  • SuedLink and companion corridors complete, monetizing the northern surplus.
  • Coastal data-center build accelerates near cheap wind.

↓ Downgrade triggers

  • Curtailment persists if transmission lags.
  • National cost and policy headwinds apply here too.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
Around 2028
SuedLink HVDC link scheduled to complete
Eases the north-south transmission congestion that limits how much of the wind-rich north's power reaches load.

Rating history

Oct 2026
UpgradeCost-pillar score 45 to 54: now set by one published rule from the band midpoint ($116/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 57 to 59. Tier 3 Workable to Tier 2 Strong.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
June 2026
New ratingNew rating: Tier 3 Workable assigned (northern zone of Germany).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityLocal (M4)Site-level evidence; still needs utility confirmation
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest field is connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

1 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshBundesnetzagentur SAIDI 2024
Connection frictionproxy2025/26FreshIEA: energy constraints on Europe's data centres
Realized costtriangulated2026FreshEU industrial electricity prices (IEA Electricity 2026)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $100 to $145 per MWh, midpoint $116, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 11.7 minutes per year (2024)
  • Historical bulk-system performance (measured)

What is open

  • Forward resource adequacy (assessed)
  • Contractual service terms (would change the answer)
  • Designed site resilience

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $100 to $145 per MWh, midpoint $116 (triangulated)

What could disqualify this market

  • Export constraint until about 2028 HVDC completion.
  • Shares national price and policy risk.
Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.