Germany South (Frankfurt/Munich)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/germany-south, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$108 to $158 per MWh

Midpoint about $126 per MWh

How this band was built

triangulated

From 3 public fragments

What builds the $126 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$88
$28
Wholesale energy$88
Network & grid fees$28
Taxes & levies (after industrial relief)$10
All-in delivered$126 /MWh
How the $126/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. The southern band sits above the north because it is further from wind generation and carries heavier network-constraint and redispatch costs. Anchored to published figures (EU electricity price components (Eurostat)). How this is built →
What the classes mean →

Where the cost lands

$126
Low $108Midpoint $126High $158
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Wholesale energy near 85 euros per MWh, plus higher grid fees, redispatch, and network constraint costs than the north.

The southern German band sits above the north because the south is further from wind generation and carries heavier network-constraint and redispatch costs, which flow through to a large load's delivered price.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: EU industrial electricity prices (IEA Electricity 2026) · Non-household electricity prices (Eurostat).

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled measured; confidence Med-High.

Friction level

Severe

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

Frankfurt's grid is fully allocated for years; new load is pushed to ex-coal corridors.

Frankfurt, Europe's largest data-center hub, has its transmission interconnection fully allocated for years ahead, and the industrial south leans on northern power over a bottlenecked grid until SuedLink completes around 2028. Developers are moving to the Aachen-Cologne-Dusseldorf corridor and brownfield coal sites where capacity exists. Core Western European connection timelines run about 7 to 10 years.

What builds the 102-month wait

18
60
18
Application & queue position6 mo
Grid study & connection offer18 mo
Network reinforcement / transmission build60 mo
Construction & energization18 mo
Typical time to energization102 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Global Data Center Hub: grid delays repricing Europe).

Data-center share of demand pressure: Very high. Sources: IEA: energy constraints on Europe's data centres · Global Data Center Hub: grid delays repricing Europe. The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%40

Constrained access: a demand centre that depends on northern and imported power over congested corridors; connection is planning-heavy until SuedLink (about 2028).

Availability25%46

Tighter availability: the 2023 nuclear exit removed large southern baseload, leaving heavier reliance on gas, imports and redispatch.

Cost25%48

Cost is the national wholesale price (single bidding zone), though the south bears more of the redispatch burden.

Momentum15%85

Highest momentum: Frankfurt anchors the FLAP-D cluster (about 750 MW), the continent's number-one hub.

Carbon5%42

Higher carbon: gas backup and imports lift the effective carbon of southern supply relative to the wind-rich north.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 51 is reduced to 44, a deduction of 7 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: No reliability flags found

Delivery reliability is high nationwide (about 12.8 minutes average interruption in 2023); the concern here is forward firm capacity, not outages.

measured

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 11.7 minutes per year in 2024, excluding major event days as filed.

measured · Bundesnetzagentur SAIDI 2024

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. BNetzA national SAIDI across roughly 880 German DSOs. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

Forward resource adequacy (assessed): Tight

The south lost most of its nuclear baseload in 2023 and depends on northern and imported power over a bottlenecked grid; the SuedLink HVDC fix is delayed to about 2028, leaving heavy redispatch. Firm-capacity risk for a new large load is concentrated here.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

assessed · Germany SuedLink north-south line (Clean Energy Wire)

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 11.7 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across several territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: Bundesnetzagentur SAIDI 2024

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Tightening
Demand pressure
Fast load growth competing for the same capacity.
Can new supply arrive
New supply is pulled toward ex-coal corridors and the north; SuedLink (around 2028) is the structural unlock for moving that power south.
Future firm supply
Future firm supply: tight.

What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Adverse↑ improving

Why: Frankfurt's transmission is fully allocated for years and new load is pushed to ex-coal corridors, but the SuedLink link (around 2028) and grid reform are underway.

What would change the read: SuedLink completing and the southern grid de-bottlenecking so core-hub access reopens.

For new supply: New supply is pulled toward ex-coal corridors and the north; SuedLink (around 2028) is the structural unlock for moving that power south.

Beyond the grid: Efficiency permitting adds a hard design constraint: under the Energy Efficiency Act, data centres commissioned from July 2026 must reuse a rising share of waste heat (toward 20 percent by 2028) or feed district heating, with fines up to 100,000 euros for non-compliance. White & Case Columbia Climate Law

Outlook drivers

↑ Upgrade triggers

  • SuedLink completion relieves the import dependence.
  • New firm capacity or storage lands in the south.

↓ Downgrade triggers

  • Corridor delays or a faster coal exit tighten the south further.
  • Redispatch cost and congestion worsen for new large load.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
Around 2028
SuedLink HVDC link scheduled to complete
Relieves the north-south bottleneck feeding the industrial south, easing the severe Frankfurt-area access constraint.

Rating history

Oct 2026
AffirmedCost-pillar score 45 to 48: now set by one published rule from the band midpoint ($126/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 43 to 44. Tier 4 Constrained unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
June 2026
New ratingNew rating: Tier 4 Constrained assigned (southern zone of Germany).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionMarket-level (M2)Good for comparing markets, not for a site
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityLocal (M4)Site-level evidence; still needs utility confirmation
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are connection and reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

2 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshBundesnetzagentur SAIDI 2024
Connection frictionmeasured2025/26FreshIEA: energy constraints on Europe's data centres
Realized costtriangulated2026FreshEU industrial electricity prices (IEA Electricity 2026)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $108 to $158 per MWh, midpoint $126, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 11.7 minutes per year (2024)
  • Historical bulk-system performance (measured)
  • Forward resource adequacy (assessed)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $108 to $158 per MWh, midpoint $126 (triangulated)

What could disqualify this market

  • Import dependence over a bottlenecked grid until about 2028.
  • Post-nuclear firm-capacity gap concentrated in the south.