Great Britain
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/great-britain, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$118 to $168 per MWh
Midpoint about $138 per MWh
What builds the $138 midpoint
Where the cost lands
Britain carries one of the highest large-load bands in the coverage: gas-set wholesale prices, a capacity-market charge, and heavy network and policy costs all stack on top of each other. Delivered cost for a large load routinely runs well above the continental average.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: EU and UK industrial electricity prices (IEA Electricity 2026) · Non-household electricity prices (Eurostat).
Forward cost anchor
Forward cost pressure
Low
Latest capacity clearing price
£27.10 per kW-year
2029/30 (T-4)
Great Britain's four-year-ahead capacity auction cleared at £27.10 per kW-year for 2029/30, less than half the £60 to £65 of the prior two years. The forward cost of firm capacity is falling here, the opposite of PJM.
Source: GB T-4 Capacity Market 2029/30 (Timera Energy). A derived indicator: we publish the public clearing price and our read, never paywalled exchange data.
Interconnection queue
Active queue depth
283 GW
Typical wait
48 months
What builds the 48-month wait
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Severe access: historic waits up to 15 years; the TMO4+ 'first ready, first connected' reform (live 2025) is reordering a ~96 GW queue.
Tight availability on a constrained system.
Very high power cost (~$100+).
World-tier momentum (London FLAP-D), but entry is gated.
Cleaner grid (~155 g), wind-heavy (~30% of generation).
Reliability overlay
Historical bulk-system performance: Minor flags found
Transmission-level Energy Not Supplied was 359 MWh in 2024/25 against a regulated incentive neutral point of 147 MWh, so the operator missed its reliability target by roughly 2.4 times on the measure Ofgem actually holds it to. Average network availability was 99.9998%. For a large load the target miss is the signal: bulk supply is highly available but the trend on the regulated measure moved the wrong way.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
measured · National Grid Electricity Transmission RIIO-T2 reliability performance
Historical utility-territory delivery performance: No reliability flags found
Average customer interruption (SAIDI) of 39.71 minutes per year in 2024/25, excluding major event days as filed.
measured · Ofgem RIIO-ED2 2024/25 summary
Forward resource adequacy (assessed): Adequacy flagged
Winter margins are wind-dependent and have been tight in the past, though the 2025/26 base-case margin of 6.1 GW (about 10%) is the strongest since 2019/20, helped by storage, gas availability and the Greenlink interconnector.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
assessed · NESO winter 2025/26 margins
Contractual service terms: firm terms under retroactive reform
Connection terms for large demand are mid-reform and the reform is explicitly retroactive: a second round of queue reordering will change existing connection offers, and distribution-level demand connections are in scope this time. Government is separately consulting on whether very large users such as data centres should be required to provide a mandatory minimum level of demand flexibility, letting the operator curtail them at times of system stress. Treat a GB connection offer as firm today but revisable, and price the possibility of a curtailment obligation you did not choose.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 39.71 minutes of power per year (2024/25) (reported as Customer Minutes Lost, a SAIDI-equivalent measure). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across several territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Source: Ofgem RIIO-ED2 2024/25 summary
Supply relief outlook
What this means: The supply crunch looks likely to ease for a new load energizing here in the coming years.
Regulatory momentum
Why: NESO's TMO4+ reform is issuing Gate 2 offers and reordering a roughly 96 GW queue toward first-ready-first-connected, targeting historic waits of up to 15 years.
What would change the read: Firm pre-2030 connection offers materialising at scale for new large loads.
For new supply: NESO's first-ready-first-connected reform is issuing Gate 2 offers against a roughly 96 GW queue, so a ready generation project can now advance.
Beyond the grid: Land and water permitting is contested even as access improves: ministers have approved hyperscale sites on green belt land, but a 90 MW Buckinghamshire approval was quashed in 2026 after the government admitted a serious error over power and water concerns, and data centres have now been folded into the centralised NSIP planning regime. Leigh Day The Register
Outlook drivers
↑ Upgrade triggers
- TMO4+ reform materially shortens new-connection timelines.
- Offshore wind and grid build relieve constraints.
↓ Downgrade triggers
- Reform underdelivers and waits persist.
- Cost stays prohibitive.
Scheduled to change
Evidence behind this rating
The real-world events that test our Tier 4 call for Great Britain: 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
Ofgem opened a consultation on 29 Jul 2026 proposing a Data Centre Commitment Fee for large data centre projects, set per unit of capacity as security. The fee is returned if the project proceeds to energisation and may be forfeited on termination or non-compliance, alongside data centre specific queue management milestones on credible end-user, long-lead equipment procurement, and financial and technical capability. It cuts both ways: it could improve access for viable projects by clearing a demand queue that has grown sharply since late 2024, much of it data centres, but it imposes a substantial financing and forfeiture burden on credible developers. Consultation closes 16 Sep 2026.
Under the TMO4+ reform, Gate 2 offers for applications up to 2030 are being issued by end-Jun 2026; NESO expects only part of the firm demand seeking connection can connect before 2030, with much more in 2030 to 2035.
A first-ready, first-connected overhaul targets historic waits of many years; projects aiming for 2030 should have offers by early 2026.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Project-ready (M3) | Enough to price a project case |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Local (M4) | Site-level evidence; still needs utility confirmation |
Source strength
High
3 of 4 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024/25 | Fresh | Ofgem RIIO-ED2 2024/25 summary |
| Forward cost | measured | 2029/30 (T-4) | Fresh | GB T-4 Capacity Market 2029/30 (Timera Energy) |
| Interconnection queue | measured | end-2025 (LBNL 2026) | Fresh | NESO connections reform press release (Dec 2025) |
| Realized cost | triangulated | 2026 | Fresh | EU and UK industrial electricity prices (IEA Electricity 2026) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $118 to $168 per MWh, midpoint $138, basis triangulated, against the 100 MW archetype
- Historical utility-territory delivery performance 39.71 minutes per year (2024/25)
- Historical bulk-system performance (measured)
- Forward resource adequacy (assessed)
- Contractual service terms (reported)
- Typical interconnection wait about 48 months (generation and storage queue, not a load wait)
What is open
- Designed site resilience
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
Who runs the connection process: National Energy System Operator (system operator), via Connections reform, Gate 2 application. Demand connection terms are mid-reform and the reform reaches existing offers; distribution-level demand is in scope. Where the process starts.
Credible ranges today
- Cost $118 to $168 per MWh, midpoint $138 (triangulated)
- Schedule: interconnection queues here run about 48 months for generation and storage; a large load follows a different process and we do not hold its measured distribution
What could disqualify this market
- Connection-queue reform execution.
- Very high power cost.