⚡ POWERGRIDIQ · EVIDENCE PACK

Great Britain

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/great-britain, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$118 to $168 per MWh

Midpoint about $138 per MWh

How this band was built

triangulated

From 3 public fragments

What builds the $138 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$75
$33
$18
Wholesale energy$75
Network charges$33
Policy & levies$18
Capacity market$12
All-in delivered$138 /MWh
How the $138/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. Britain stacks gas-set wholesale energy, some of Europe's heaviest network and policy costs, and a capacity-market charge, which is why its delivered cost runs well above the continental average. Anchored to published figures (UK electricity price components (IEA Electricity 2026)). How this is built →
What the classes mean →

Where the cost lands

$138
Low $118Midpoint $138High $168
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: High wholesale energy, plus a capacity-market charge and some of Europe's heaviest network and policy costs.

Britain carries one of the highest large-load bands in the coverage: gas-set wholesale prices, a capacity-market charge, and heavy network and policy costs all stack on top of each other. Delivered cost for a large load routinely runs well above the continental average.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: EU and UK industrial electricity prices (IEA Electricity 2026) · Non-household electricity prices (Eurostat).

Forward cost anchor

Siting a load is a decade-long cost bet, so the forward cost of firm capacity matters more than today's spot price. This is the public capacity-auction clearing price, the market's own forward read, not a paywalled forward curve.

Forward cost pressure

Low

Latest capacity clearing price

£27.10 per kW-year

2029/30 (T-4)

Trend: Falling sharply, from £60 to £65 in the prior two auctions, as connection reform and softer demand ease the market.

Great Britain's four-year-ahead capacity auction cleared at £27.10 per kW-year for 2029/30, less than half the £60 to £65 of the prior two years. The forward cost of firm capacity is falling here, the opposite of PJM.

Source: GB T-4 Capacity Market 2029/30 (Timera Energy). A derived indicator: we publish the public clearing price and our read, never paywalled exchange data.

Interconnection queue

This is a generation and storage interconnection queue. It shows how congested the interconnection system is for new supply. It does not measure how long a new large load waits, and its withdrawal rate is not a load withdrawal rate. The figures below are this market's own, published by its system operator; they are not part of, and not comparable with, the United States queue totals.

Active queue depth

283 GW

Typical wait

48 months

What builds the 48-month wait

12
12
12
12
Application window & Gate 2 offer12 mo
Connection design & agreement12 mo
Network reinforcement12 mo
Construction & energization12 mo
Typical time to energization48 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (NESO connections reform).

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%38

Severe access: historic waits up to 15 years; the TMO4+ 'first ready, first connected' reform (live 2025) is reordering a ~96 GW queue.

Availability25%45

Tight availability on a constrained system.

Cost25%42

Very high power cost (~$100+).

Momentum15%82

World-tier momentum (London FLAP-D), but entry is gated.

Carbon5%78

Cleaner grid (~155 g), wind-heavy (~30% of generation).

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 50 is reduced to 47, a deduction of 3 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

Transmission-level Energy Not Supplied was 359 MWh in 2024/25 against a regulated incentive neutral point of 147 MWh, so the operator missed its reliability target by roughly 2.4 times on the measure Ofgem actually holds it to. Average network availability was 99.9998%. For a large load the target miss is the signal: bulk supply is highly available but the trend on the regulated measure moved the wrong way.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

measured · National Grid Electricity Transmission RIIO-T2 reliability performance

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 39.71 minutes per year in 2024/25, excluding major event days as filed.

measured · Ofgem RIIO-ED2 2024/25 summary

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. Ofgem all-DNO average across the fourteen GB licence areas. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

Forward resource adequacy (assessed): Adequacy flagged

Winter margins are wind-dependent and have been tight in the past, though the 2025/26 base-case margin of 6.1 GW (about 10%) is the strongest since 2019/20, helped by storage, gas availability and the Greenlink interconnector.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

assessed · NESO winter 2025/26 margins

Contractual service terms: firm terms under retroactive reform

Connection terms for large demand are mid-reform and the reform is explicitly retroactive: a second round of queue reordering will change existing connection offers, and distribution-level demand connections are in scope this time. Government is separately consulting on whether very large users such as data centres should be required to provide a mandatory minimum level of demand flexibility, letting the operator curtail them at times of system stress. Treat a GB connection offer as firm today but revisable, and price the possibility of a curtailment obligation you did not choose.

What the service contract promises, as distinct from how the system has performed · Spring 2026 update on Demand Connection Reform for data centres and large energy users (CMS, Mar 2026)

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 39.71 minutes of power per year (2024/25) (reported as Customer Minutes Lost, a SAIDI-equivalent measure). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across several territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: Ofgem RIIO-ED2 2024/25 summary

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Easing
Demand pressure
Fast load growth competing for the same capacity.
New supply in motion
About 135.8 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Can new supply arrive
NESO's first-ready-first-connected reform is issuing Gate 2 offers against a roughly 96 GW queue, so a ready generation project can now advance.
Future firm supply
Future firm supply: adequacy flagged.

What this means: The supply crunch looks likely to ease for a new load energizing here in the coming years.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed↑ improving

Why: NESO's TMO4+ reform is issuing Gate 2 offers and reordering a roughly 96 GW queue toward first-ready-first-connected, targeting historic waits of up to 15 years.

What would change the read: Firm pre-2030 connection offers materialising at scale for new large loads.

For new supply: NESO's first-ready-first-connected reform is issuing Gate 2 offers against a roughly 96 GW queue, so a ready generation project can now advance.

Beyond the grid: Land and water permitting is contested even as access improves: ministers have approved hyperscale sites on green belt land, but a 90 MW Buckinghamshire approval was quashed in 2026 after the government admitted a serious error over power and water concerns, and data centres have now been folded into the centralised NSIP planning regime. Leigh Day The Register

Outlook drivers

↑ Upgrade triggers

  • TMO4+ reform materially shortens new-connection timelines.
  • Offshore wind and grid build relieve constraints.

↓ Downgrade triggers

  • Reform underdelivers and waits persist.
  • Cost stays prohibitive.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
H2 2026
Next NESO connections application window opens
The route to a Gate 2 offer under the reformed queue; its timing gates when a new large load can enter.
2030
First reform-era firm demand connections targeted
NESO estimates about 13 GW of firm demand can connect before 2030, with more between 2030 and 2035.

Evidence behind this rating

The real-world events that test our Tier 4 call for Great Britain: 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Ofgem consults on a refundable data centre commitment fee to clear speculative projects from the queue ▲ Challenges the rating
Jul 2026AccessMateriality: high

Ofgem opened a consultation on 29 Jul 2026 proposing a Data Centre Commitment Fee for large data centre projects, set per unit of capacity as security. The fee is returned if the project proceeds to energisation and may be forfeited on termination or non-compliance, alongside data centre specific queue management milestones on credible end-user, long-lead equipment procurement, and financial and technical capability. It cuts both ways: it could improve access for viable projects by clearing a demand queue that has grown sharply since late 2024, much of it data centres, but it imposes a substantial financing and forfeiture burden on credible developers. Consultation closes 16 Sep 2026.

Power to a buyer: Nothing yet: this is a consultation. If adopted, a large data centre would post security per unit of capacity, returned at energisation and forfeitable on termination or non-compliance.
Source: Ofgem ↗
NESO begins issuing Gate 2 connection offers for pre-2030 projects ✓ Supports the rating
Jun 2026AccessMateriality: med

Under the TMO4+ reform, Gate 2 offers for applications up to 2030 are being issued by end-Jun 2026; NESO expects only part of the firm demand seeking connection can connect before 2030, with much more in 2030 to 2035.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: NESO ↗
TMO4+ connection reform goes live, reordering the connection queue ✓ Supports the rating
2025AccessMateriality: med

A first-ready, first-connected overhaul targets historic waits of many years; projects aiming for 2030 should have offers by early 2026.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: NESO ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Oct 2026
AffirmedCost-pillar score 20 to 42: now set by one published rule from the band midpoint ($138/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 41 to 47. Tier 4 Constrained unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
Aug 2026
AffirmedTier holds. The proposal is a consultation, not in force, and it cuts both ways: a refundable fee of up to GBP 712,500 per MW is a real balance-sheet demand on a credible developer, but the intent is to strip the 125 GW demand-connection queue (Jun 2025; separate from the generation queue on /connection-friction) of projects that were never going to connect, which is what a serious large load needs. Revisit on the final decision after 16 Sep 2026; a fee at the top of the range with weak refund mechanics would be an Access negative.
Trigger: Ofgem consultation on data centre connection reforms, 29 Jul 2026
Jun 2026
AffirmedConnection reform is delivering on schedule (Gate 2 offers issuing), supporting the positive outlook, but firm pre-2030 capacity stays scarce. Tier affirmed, outlook unchanged.
Trigger: NESO Gate 2 offers for pre-2030 projects (Jun 2026)
June 2026
New ratingNew rating: Tier 4 Constrained assigned (momentum noted, no up-override).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionProject-ready (M3)Enough to price a project case
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityLocal (M4)Site-level evidence; still needs utility confirmation
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest field is reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

3 of 4 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024/25FreshOfgem RIIO-ED2 2024/25 summary
Forward costmeasured2029/30 (T-4)FreshGB T-4 Capacity Market 2029/30 (Timera Energy)
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshNESO connections reform press release (Dec 2025)
Realized costtriangulated2026FreshEU and UK industrial electricity prices (IEA Electricity 2026)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $118 to $168 per MWh, midpoint $138, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 39.71 minutes per year (2024/25)
  • Historical bulk-system performance (measured)
  • Forward resource adequacy (assessed)
  • Contractual service terms (reported)
  • Typical interconnection wait about 48 months (generation and storage queue, not a load wait)

What is open

  • Designed site resilience

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
Who runs the connection process: National Energy System Operator (system operator), via Connections reform, Gate 2 application. Demand connection terms are mid-reform and the reform reaches existing offers; distribution-level demand is in scope. Where the process starts.

Credible ranges today

  • Cost $118 to $168 per MWh, midpoint $138 (triangulated)
  • Schedule: interconnection queues here run about 48 months for generation and storage; a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Connection-queue reform execution.
  • Very high power cost.
Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.