Ireland (Dublin)
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/ireland, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$130 to $180 per MWh
Midpoint about $150 per MWh
What builds the $150 midpoint
Where the cost lands
Ireland has the most expensive large-load band in the coverage. Non-household prices are the highest in the European Union, the system is small and constrained, and data centers already draw about a fifth of national demand, so a new large load pays a steep, constraint-driven premium.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Modelled (estimated from a model and structural indicators where direct published figures are limited). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Non-household electricity prices, Ireland highest (Eurostat) · Data centres 22% of demand (CSO Ireland).
Interconnection queue
Active queue depth
5 GW
Typical wait
48 months
What builds the 48-month wait
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Hard access gate: a 2021-2025 freeze on new Dublin data-center grid connections was lifted in late 2025 only for projects that self-generate or store their full demand. Grid-only connection stays effectively closed in the east.
Tight availability: a small, constrained system with data centers already ~22% of national demand.
Expensive power.
Historically high momentum (a FLAP-D hub), now gated.
Moderate carbon (~340 g), gas-led.
Reliability overlay
Historical bulk-system performance: No reliability flags found
Historical utility-territory delivery performance: No reliability flags found
Forward resource adequacy (assessed): Tight
Tight adequacy: EirGrid warns of possible Amber system alerts at low-wind, low-import evening peaks, and the system leans on temporary emergency generation plus protocols under which large users (mostly data centres) cut demand by up to 75% in an emergency. Data-center demand is the core driver, which is why grid-only connection around Dublin is gated.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
event-based · EirGrid winter adequacy outlook
Contractual service terms: interruptible expected
The system leans on protocols under which large users, mostly data centres, cut demand by up to 75% in an emergency. A large new load here should expect an interruptibility obligation as a condition of service rather than as an option.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Regulatory momentum
Why: The Dublin data-centre connection moratorium was lifted in December 2025, but only for projects that self-generate or store their full demand; grid-only connection stays effectively closed in the east.
What would change the read: EirGrid confirming that conditional connections genuinely reopen grid access for large loads, not just self-supply.
For new supply: New grid-connected supply faces the same congestion; the near-term route is on-site or stored generation that lets a load self-supply, the condition under which Dublin connections reopened.
Beyond the grid: Community and resource pressure underlies the grid limit: data centres' large and rising share of national electricity has made them a sustained political flashpoint, which is the backdrop to the connection restrictions. DCD
Outlook drivers
↑ Upgrade triggers
- The self-supply pathway and green energy parks unlock new regional capacity.
- Offshore wind and grid build relieve the eastern constraint.
↓ Downgrade triggers
- The gate tightens or self-supply economics fail to pencil.
- Continued moratorium pressure.
Scheduled to change
Evidence behind this rating
The real-world events that test our Tier 5 call for Ireland (Dublin): 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
New grid links are allowed only for projects that can self-generate or store their full demand; grid-only connection stays effectively closed in the east.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Broad (M1) | Directional: good for screening and monitoring |
| Connection | Project-ready (M3) | Enough to price a project case |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Local (M4) | Site-level evidence; still needs utility confirmation |
Source strength
Moderate
1 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
23 Oct 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | assessed | 2025 | Fresh | EirGrid winter adequacy outlook |
| Interconnection queue | measured | end-2025 (LBNL 2026) | Fresh | EirGrid ECP-2.5 assumptions |
| Realized cost | modelled | 2026 | Fresh | Non-household electricity prices, Ireland highest (Eurostat) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $130 to $180 per MWh, midpoint $150, basis modelled, against the 100 MW archetype
- Forward resource adequacy (assessed)
- Contractual service terms (reported)
- Typical interconnection wait about 48 months (generation and storage queue, not a load wait)
What is open
- Historical utility-territory delivery performance (would change the answer)
- Designed site resilience
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
Who runs the connection process: EirGrid and ESB Networks (system operator and distribution operator), via Large Energy User connection assessment. Dublin-area constraints are explicit policy, not queue congestion. Where the process starts.
Credible ranges today
- Cost $130 to $180 per MWh, midpoint $150 (modelled)
- Schedule: interconnection queues here run about 48 months for generation and storage; a large load follows a different process and we do not hold its measured distribution
What could disqualify this market
- Policy gate and self-supply requirement.
- System tightness with data centers at ~22% of demand.
Questions to put to the utility
- What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project caseWhy it is open: no regulator outage series compiled for this market yet.
The same list as JSON: /api/v1/markets/ireland/gaps