Japan
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/japan, with every section open. As of June 2026.
The five pillars behind the tier
Constrained island-grid access (OCCTO).
Improving availability as nuclear restarts (15 reactors back, ~33 GW).
Very high cost.
High momentum (Tokyo).
Carbon moderate-high (~450 g), LNG/coal.
Reliability overlay
Historical bulk-system performance: No reliability flags found
Historical utility-territory delivery performance: No reliability flags found
Forward resource adequacy (assessed): Adequacy flagged
National roll-up of the east-west split: the 50Hz east issued Japan's first power shortage warnings in 2022 and stays structurally tight with only ~1.2 GW of frequency-converter links (rising toward 3 GW by 2027) to the western surplus; the 60Hz west is comfortable. Tokyo-bound load carries the eastern risk; see JP-E / JP-W.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based · Tokyo first-ever power shortage warning 2022 (Nippon.com) · Japan east-west converter capacity (Wikipedia)
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Outlook drivers
↑ Upgrade triggers
- Nuclear restarts displace LNG and lower cost/carbon.
- Continued Tokyo build.
↓ Downgrade triggers
- High power cost persists.
- Island-grid constraints.
Rating history
Data provenance and freshness
Source strength
Limited
None of the 1 data layers is directly measured; they are triangulated or modelled
Coverage
Partial
1 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
Source strength is limited: none of the 1 data layers is directly measured; they are triangulated or modelled. Confidence in the rating (Med) is a separate judgement about the opinion as a whole, set in review; source strength grades only how directly the numbers underneath were measured.
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | assessed | 2025 | Fresh | Tokyo first-ever power shortage warning 2022 (Nippon.com) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.