⚡ POWERGRIDIQ · EVIDENCE PACK

Netherlands

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/netherlands, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$108 to $150 per MWh

Midpoint about $125 per MWh

How this band was built

triangulated

From 2 public fragments

What builds the $125 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$75
$40
Wholesale energy$75
Network charges$40
Taxes & levies$10
All-in delivered$125 /MWh
How the $125/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. Dutch cost is driven less by energy than by network charges and severe grid congestion; in much of the country a new large connection is not available at any price today. Anchored to published figures (EU electricity price components (Eurostat)). How this is built →
What the classes mean →

Where the cost lands

$125
Low $108Midpoint $125High $150
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Wholesale energy plus rising network charges on a grid where connection capacity is largely full.

Dutch large loads pay a mid-to-high band, driven less by energy than by network costs and severe grid congestion. In much of the country a new large connection is not available at any price today, which keeps effective costs high for those that do connect.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Non-household electricity prices (Eurostat).

Interconnection queue

This is a large-load (demand) queue: it counts loads waiting to draw power, not generation waiting to connect. It is the closest thing to a real measure of how long a new large load waits here, but a place in it is a request, not an approval, and the withdrawal rate below is this queue's own, not a generation figure.

Active queue depth

38 GW

Typical wait

96 months

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%25

Acute access crisis: 14,000-plus waiting, quoted waits up to 10 years, whole regions full for the decade.

Availability25%40

Tight availability on a congested grid.

Cost25%49

High cost.

Momentum15%70

High momentum (Amsterdam FLAP-D), but gated.

Carbon5%52

Moderate carbon (~330 g).

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 43 is reduced to 40, a deduction of 3 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: No reliability flags found

Delivery reliability on the existing grid is good; the binding problem is connection access, not outages.

measured

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 23.9 minutes per year in 2024, excluding major event days as filed.

measured · Netbeheer Nederland reliability 2024

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. national average across Dutch DSOs. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

Forward resource adequacy (assessed): Adequacy flagged

Severe grid congestion: TenneT's offtake waiting list runs to roughly 38 GW across 212 requests, new large loads cannot connect in much of the country, and operators warn of local overloading from 2026. The connection-access dimension is already in the Access pillar; this flags the delivery-expansion and overload risk.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

assessed · Netherlands grid congestion (RAP)

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 23.9 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across several territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: Netbeheer Nederland reliability 2024

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Fast load growth competing for the same capacity.
Competing demand in the queue
About 30.4 GW of the large-load queue is likely to proceed after historical withdrawal. This is demand competing for capacity, not new supply.
Can new supply arrive
New generation sits in the same queue; the state's eight-measure push to free 5 to 10 GW by 2030 is the opening to watch.
Future firm supply
Future firm supply: adequacy flagged.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Adverse→ stable

Why: Courts continue to uphold the TenneT connection waiting list, over 14,000 businesses are queued, and grid-only connection is unavailable in much of the country.

What would change the read: The government's eight-measure campaign actually freeing 5 to 10 GW of capacity by 2030.

For new supply: New generation sits in the same queue; the state's eight-measure push to free 5 to 10 GW by 2030 is the opening to watch.

Beyond the grid: Non-grid permitting is also binding: the country paused new hyperscale builds partly over land use and water, a farmers' group has appealed a Microsoft data-centre permit, and Amsterdam now makes heat reuse a mandatory condition of new data-centre permits. IDC DCD

Outlook drivers

↑ Upgrade triggers

  • The 100-plus congestion measures and grid build clear capacity.
  • Flexibility/curtailable connections open a path.

↓ Downgrade triggers

  • Congestion worsens and waits lengthen.
  • Local data-center restrictions.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
By 2030
Dutch government targets freeing 5 to 10 GW of grid capacity via its eight-measure campaign
Whether congestion eases enough for new large connections in the currently-full core.

Evidence behind this rating

The real-world events that test our Tier 4 call for Netherlands: 2 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Dutch court upholds TenneT waiting list for a data centre connection ✓ Supports the rating
Apr 2026AccessMateriality: med

A court ruled (29 Apr 2026) that TenneT may keep Goodman's Haarlemmermeer data centre on the congestion waiting list, finding grid public interest outweighs the developer's claim; grid-only connection near Amsterdam stays effectively closed.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: NL Times ↗
14,000-plus businesses now on the Dutch grid-connection waiting list ✓ Supports the rating
Oct 2025AccessMateriality: high

Quoted waits reach up to 10 years and whole regions are full for the decade; connection, not generation, is the binding constraint.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: NL Times ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Oct 2026
AffirmedCost-pillar score 40 to 49: now set by one published rule from the band midpoint ($125/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 38 to 40. Tier 4 Constrained unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
Jul 2026
AffirmedCourt ruling hardens the connection constraint the tier already prices in; tier holds.
Trigger: Haarlemmermeer waiting-list ruling (29 Apr 2026)
June 2026
New ratingNew rating: Tier 4 Constrained assigned.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionMarket-level (M2)Good for comparing markets, not for a site
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityLocal (M4)Site-level evidence; still needs utility confirmation
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are connection and reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

2 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshNetbeheer Nederland reliability 2024
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshParliamentary letter on grid congestion, Stibbe (Feb 2026)
Realized costtriangulated2026FreshNon-household electricity prices (Eurostat)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $108 to $150 per MWh, midpoint $125, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 23.9 minutes per year (2024)
  • Historical bulk-system performance (measured)
  • Forward resource adequacy (assessed)
  • Typical interconnection wait about 96 months (generation and storage queue, not a load wait)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $108 to $150 per MWh, midpoint $125 (triangulated)
  • Schedule: interconnection queues here run about 96 months for generation and storage; a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Connection-queue crisis.
  • Local restrictions.