Netherlands
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/netherlands, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$108 to $150 per MWh
Midpoint about $125 per MWh
What builds the $125 midpoint
Where the cost lands
Dutch large loads pay a mid-to-high band, driven less by energy than by network costs and severe grid congestion. In much of the country a new large connection is not available at any price today, which keeps effective costs high for those that do connect.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Non-household electricity prices (Eurostat).
Interconnection queue
Active queue depth
38 GW
Typical wait
96 months
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Acute access crisis: 14,000-plus waiting, quoted waits up to 10 years, whole regions full for the decade.
Tight availability on a congested grid.
High cost.
High momentum (Amsterdam FLAP-D), but gated.
Moderate carbon (~330 g).
Reliability overlay
Historical bulk-system performance: No reliability flags found
Delivery reliability on the existing grid is good; the binding problem is connection access, not outages.
measured
Historical utility-territory delivery performance: No reliability flags found
Average customer interruption (SAIDI) of 23.9 minutes per year in 2024, excluding major event days as filed.
measured · Netbeheer Nederland reliability 2024
Forward resource adequacy (assessed): Adequacy flagged
Severe grid congestion: TenneT's offtake waiting list runs to roughly 38 GW across 212 requests, new large loads cannot connect in much of the country, and operators warn of local overloading from 2026. The connection-access dimension is already in the Access pillar; this flags the delivery-expansion and overload risk.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
assessed · Netherlands grid congestion (RAP)
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 23.9 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across several territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Regulatory momentum
Why: Courts continue to uphold the TenneT connection waiting list, over 14,000 businesses are queued, and grid-only connection is unavailable in much of the country.
What would change the read: The government's eight-measure campaign actually freeing 5 to 10 GW of capacity by 2030.
For new supply: New generation sits in the same queue; the state's eight-measure push to free 5 to 10 GW by 2030 is the opening to watch.
Beyond the grid: Non-grid permitting is also binding: the country paused new hyperscale builds partly over land use and water, a farmers' group has appealed a Microsoft data-centre permit, and Amsterdam now makes heat reuse a mandatory condition of new data-centre permits. IDC DCD
Outlook drivers
↑ Upgrade triggers
- The 100-plus congestion measures and grid build clear capacity.
- Flexibility/curtailable connections open a path.
↓ Downgrade triggers
- Congestion worsens and waits lengthen.
- Local data-center restrictions.
Scheduled to change
Evidence behind this rating
The real-world events that test our Tier 4 call for Netherlands: 2 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
A court ruled (29 Apr 2026) that TenneT may keep Goodman's Haarlemmermeer data centre on the congestion waiting list, finding grid public interest outweighs the developer's claim; grid-only connection near Amsterdam stays effectively closed.
Quoted waits reach up to 10 years and whole regions are full for the decade; connection, not generation, is the binding constraint.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Market-level (M2) | Good for comparing markets, not for a site |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Local (M4) | Site-level evidence; still needs utility confirmation |
Source strength
High
2 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | Netbeheer Nederland reliability 2024 |
| Interconnection queue | measured | end-2025 (LBNL 2026) | Fresh | Parliamentary letter on grid congestion, Stibbe (Feb 2026) |
| Realized cost | triangulated | 2026 | Fresh | Non-household electricity prices (Eurostat) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $108 to $150 per MWh, midpoint $125, basis triangulated, against the 100 MW archetype
- Historical utility-territory delivery performance 23.9 minutes per year (2024)
- Historical bulk-system performance (measured)
- Forward resource adequacy (assessed)
- Typical interconnection wait about 96 months (generation and storage queue, not a load wait)
What is open
- Contractual service terms (would change the answer)
- Designed site resilience
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Cost $108 to $150 per MWh, midpoint $125 (triangulated)
- Schedule: interconnection queues here run about 96 months for generation and storage; a large load follows a different process and we do not hold its measured distribution
What could disqualify this market
- Connection-queue crisis.
- Local restrictions.