Pacific Northwest
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/pacific-northwest, with every section open. As of June 2026.
Realized cost band
Withdrawn. The published band was derived from the Bonneville Power Administration priority-firm rate, which a new large load cannot obtain: federal hydro allocations are largely committed and a new customer would pay a market premium above the federal rate. A tariff the standard archetype cannot purchase may not set a delivered-cost band.
No delivered-cost band is published for this market, and no substitute figure has been put in its place. Screening on recurring cost returns insufficient evidence for this market rather than a value we cannot defend.
Restored when: A delivered-cost band is rebuilt from a source a new 100 MW high-load-factor customer could actually contract, with a stated cost boundary, effective date, method and confidence, reconciled like every other published market. Withdrawn 2026-08-20.
Interconnection queue
Active queue depth
130 GW
Typical wait
39 monthsnon-ISO West median, projects online 2018 to 2025; not specific to this market
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
The five pillars behind the tier
Access is tightening: the BPA interconnection queue is lengthening as demand surges.
High availability: abundant, firm hydro across the Northwest.
Cheap power: among the lowest US wholesale costs.
Proven momentum: long-established hyperscale clusters (central Washington, Oregon).
Clean grid (~70 g), hydro-led.
Reliability overlay
Historical bulk-system performance: Minor flags found
A dayslong cold snap over Martin Luther King weekend in January 2024 brought the region dangerously close to rolling outages.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based
Historical utility-territory delivery performance: No reliability flags found
Average customer interruption (SAIDI) of 152.68 minutes per year in 2024, excluding major event days as filed.
The territories inside this market
The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.
| Territory operator | SAIDI min/yr | Customers | Major-event method |
|---|---|---|---|
| Puget Sound Energy Inc (WA) | 203.0 | 1,240,043 | IEEE 1366 |
| Portland General Electric Co (OR) | 133.0 | 942,296 | IEEE 1366 |
| PacifiCorp (OR) | 107.57 | 638,000 | IEEE 1366 |
| Idaho Power Co (ID) | 164.01 | 621,746 | IEEE 1366 |
| City of Seattle - (WA) (WA) | 110.8 | 537,470 | IEEE 1366 |
| PUD No 1 of Snohomish County (WA) | 181.4 | 386,741 | IEEE 1366 |
| Avista Corp (WA) | 112.0 | 270,134 | IEEE 1366 |
| PUD No 1 of Clark County - (WA) (WA) | 59.0 | 233,669 | IEEE 1366 |
| City of Tacoma - (WA) (WA) | 80.45 | 179,969 | IEEE 1366 |
| Avista Corp (ID) | 165.0 | 145,203 | IEEE 1366 |
| PacifiCorp (WA) | 101.99 | 138,254 | IEEE 1366 |
| City of Eugene - (OR) (OR) | 65.26 | 102,048 | IEEE 1366 |
| PacifiCorp (ID) | 129.44 | 89,035 | IEEE 1366 |
| PUD No 1 of Benton County (WA) | 39.5 | 56,863 | IEEE 1366 |
| PUD No 1 of Cowlitz County (WA) | 125.6 | 54,257 | IEEE 1366 |
| PUD No 1 of Chelan County (WA) | 95.23 | 51,143 | IEEE 1366 |
| Inland Power & Light Company (WA) | 278.0 | 48,046 | IEEE 1366 |
| PUD No 1 of Grays Harbor County (WA) | 202.0 | 45,710 | IEEE 1366 |
| PUD No 3 of Mason County (WA) | 269.34 | 36,547 | own method |
| PUD No 1 of Lewis County (WA) | 604.74 | 35,583 | IEEE 1366 |
| Peninsula Light Company (WA) | 136.07 | 35,518 | IEEE 1366 |
| PUD No 1 of Franklin County (WA) | 55.4 | 35,015 | own method |
| Kootenai Electric Cooperative (ID) | 125.04 | 34,499 | IEEE 1366 |
| PUD No 1 of Clallam County (WA) | 213.1 | 33,769 | own method |
| City of Springfield - (OR) (OR) | 11.61 | 33,147 | IEEE 1366 |
| City of Idaho Falls - (ID) (ID) | 72.4 | 32,782 | IEEE 1366 |
| Oregon Trail El Cons Coop, Inc (OR) | 142.15 | 31,823 | own method |
| City of Richland - (WA) (WA) | 94.0 | 27,563 | IEEE 1366 |
| Consumers Power, Inc (OR) | 354.1 | 23,819 | IEEE 1366 |
| PUD No 1 of Okanogan County (WA) | 110.1 | 22,175 | own method |
| Midstate Electric Coop, Inc (OR) | 369.0 | 21,517 | own method |
| PUD No 1 of Jefferson County (WA) | 424.0 | 21,166 | IEEE 1366 |
| Columbia River Peoples Ut Dist (OR) | 54.54 | 20,817 | IEEE 1366 |
| Salem Electric - (OR) (OR) | 19.66 | 20,556 | own method |
| Idaho Power Co (OR) | 434.79 | 20,146 | IEEE 1366 |
| Northern Lights, Inc (ID) | 1219.7 | 19,609 | own method |
| Umatilla Electric Coop Assn (OR) | 99.06 | 19,473 | IEEE 1366 |
| Coos-Curry Electric Coop, Inc (OR) | 181.3 | 18,713 | IEEE 1366 |
| Fall River Rural Elec Coop Inc (ID) | 6.78 | 18,225 | IEEE 1366 |
| Benton Rural Electric Assn (WA) | 156.01 | 16,453 | IEEE 1366 |
| Orcas Power & Light Coop (WA) | 212.5 | 15,251 | IEEE 1366 |
| PUD No 1 of Klickitat County (WA) | 384.0 | 14,254 | own method |
| Lane Electric Coop Inc (OR) | 826.4 | 13,468 | own method |
| City of Centralia - (WA) (WA) | 55.66 | 10,745 | IEEE 1366 |
| Northern Wasco County PUD (OR) | 34.84 | 10,490 | IEEE 1366 |
| Big Bend Electric Coop, Inc (WA) | 191.77 | 9,477 | IEEE 1366 |
| United Electric Co-op, Inc - (ID) (ID) | 40.33 | 7,513 | IEEE 1366 |
| Columbia Rural Elec Assn, Inc (WA) | 213.9 | 6,507 | IEEE 1366 |
| Clatskanie Peoples Util Dist (OR) | 517.86 | 4,777 | IEEE 1366 |
| Salmon River Electric Coop Inc (ID) | 198.88 | 3,056 | IEEE 1366 |
| Northern Lights, Inc (WA) | 0.89 | 14 | own method |
Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.
Forward resource adequacy (assessed): Tight
The Northwest holds most US hydro capacity, so a dry hydro year combined with an extended cold snap is the region's rolling-blackout risk; BPA has warned of a widening resource gap and took large drought-driven revenue losses.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
assessed · PNW energy-shortage risk in extreme conditions (Spokesman) · Drought cuts PNW hydropower (EIA)
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Reliability metrics
Delivery reliability (measured)
The average customer loses about 152.68 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across 51 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
Supply relief outlook
What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.
Regulatory momentum
Why: BPA is federally administered and outside FERC's Section 206 orders; it has paused its long-term queue under a Grid Access Transformation Project and is weighing readiness requirements and a 13 MW large-load threshold. Transmission is available except in data-centre pockets like central Oregon and the Portland metro, where about 18 GW of BPA's 24 GW load request is data centres.
What would change the read: The Grid Access Transformation reform reopening a clear queue with firm connection dates for large loads.
Outlook drivers
↑ Upgrade triggers
- BPA expands transmission and clears the queue.
- Continued hydro-backed clean-power advantage attracts firm tenants.
↓ Downgrade triggers
- Queue and transmission constraints harden.
- Dry-year hydro variability.
Evidence behind this rating
The real-world events that test our Tier 2 call for Pacific Northwest: 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
Seattle City Council passed a one-year moratorium on siting large data centres (Jun 2026) pending a study of grid, land-use and ratepayer impacts.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Not assessed | We hold no evidence for this yet |
| Connection | Broad (M1) | Directional: good for screening and monitoring |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 2 data layers directly measured; the rest are triangulated or modelled
Coverage
Substantial
2 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 51 of 55 territories, 98% of customers, regional context only) |
| Interconnection queue | modelled | end-2025 (LBNL 2026) | Fresh | LBNL Queued Up 2026 |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Historical utility-territory delivery performance 152.68 minutes per year (2024)
- Historical bulk-system performance (event-based)
- Forward resource adequacy (assessed)
- Typical interconnection wait about 39 months (generation and storage queue, not a load wait; non-ISO West median, projects online 2018 to 2025; not specific to this market)
What is open
- Contractual service terms (would change the answer)
- Designed site resilience
- Cost evidence (would change the answer)
- Substation-level capacity evidence
How service and connection are organized
Territories in this market, each with its own filed record: Puget Sound Energy Inc, Portland General Electric Co, PacifiCorp, Idaho Power Co, City of Seattle - (WA), PUD No 1 of Snohomish County, Avista Corp, PUD No 1 of Clark County - (WA). Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Schedule: interconnection queues here run about 39 months for generation and storage (non-ISO West median, projects online 2018 to 2025; not specific to this market); a large load follows a different process and we do not hold its measured distribution
What could disqualify this market
- BPA interconnection backlog.
- Hydrological variability.
Questions to put to the utility
- What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project caseWhy it is open: no compiled cost band for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/pacific-northwest/gaps