Portugal
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/portugal, with every section open. As of June 2026.
The five pillars behind the tier
Open and welcoming; a major Sines campus anchors the market.
Good availability with strong renewables.
Competitive cost.
Building momentum.
Clean-ish (~130-150 g).
Reliability overlay
Historical bulk-system performance: Reliability flags found
Swept up in the April 28, 2025 Iberian blackout, which cut power across mainland Portugal for about ten hours when the Spanish grid collapsed, since Portugal is tightly coupled to the Spanish system.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
event-based · 2025 Iberian blackout, ENTSO-E expert panel
Historical utility-territory delivery performance: No reliability flags found
Forward resource adequacy (assessed): Adequacy flagged
Reliability is tied to the Spanish system and to the shared reforms following the 2025 event.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
modelled
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Outlook drivers
↑ Upgrade triggers
- Sines and follow-on projects scale.
- Atlantic cable connectivity attracts tenants.
↓ Downgrade triggers
- Small-market scale.
- Connection constraints.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Not assessed | We hold no evidence for this yet |
| Connection | Not assessed | We hold no evidence for this yet |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Not assessed | We hold no evidence for this yet |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
None of the 1 data layers is directly measured; they are triangulated or modelled
Coverage
Partial
1 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | historical | 2025 | Fresh | 2025 Iberian blackout, ENTSO-E expert panel |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Historical bulk-system performance (event-based)
- Forward resource adequacy (assessed)
What is open
- Historical utility-territory delivery performance (would change the answer)
- Contractual service terms (would change the answer)
- Designed site resilience
- Cost evidence (would change the answer)
- Connection evidence (would change the answer)
- Regulatory evidence
- Substation-level capacity evidence
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- No cost or schedule range is compiled for this market.
What could disqualify this market
- Scale.
- Connection capacity.
Questions to put to the utility
- What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project caseWhy it is open: no compiled cost band for this market yet.
- How long is it from a complete application being accepted to full firm energization of the MW we need, and which milestones (initial, phased, temporary or conditional energization) would come first? Needed for a project caseWhy it is open: no countable queue or operator-published process for this market.
- What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project caseWhy it is open: no regulator outage series compiled for this market yet.
- Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?Why it is open: no dated regulatory read compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/portugal/gaps