Qatar
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/qatar, with every section open. As of June 2026.
Large-user tariff
Industrial tariff
about 0.10 QR per kWh (about $0.030 per kWh)
administered, subsidized industrial rate (Kahramaa), 2025
Trend
Stable and heavily subsidized; moves only on a Kahramaa decision.
Qatar has no competitive wholesale market. A large load pays Kahramaa's administered, subsidized industrial tariff, roughly 0.10 Qatari riyal per kWh (about 3 US cents). The tariff, not a spot price, is what a data center pays, and it is genuinely among the cheapest anywhere.
Basis: measured. Source: Kahramaa electricity tariff.
The five pillars behind the tier
State-backed, workable access.
Adequate availability.
Cheap gas power.
Moderate momentum (Microsoft cloud region).
High carbon (~480 g), gas.
Reliability overlay
Historical bulk-system performance: No reliability flags found
Historical utility-territory delivery performance: No reliability flags found
Forward resource adequacy (assessed): Adequacy flagged
Modelled read: gas-rich and reliable, with extreme summer cooling peaks.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
modelled
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Outlook drivers
↑ Upgrade triggers
- Cloud-region anchored build scales.
- Solar additions lower carbon.
↓ Downgrade triggers
- Carbon-constrained buyers reweight.
- Small-market scale.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Not assessed | We hold no evidence for this yet |
| Connection | Not assessed | We hold no evidence for this yet |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Not assessed | We hold no evidence for this yet |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 2 data layers directly measured; the rest are triangulated or modelled
Coverage
Partial
1 of 3 dimensions: reliability, connection, cost
Last reviewed
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | modelled | 2025 | Fresh | on the market page |
| Large-user tariff | administered | 2025 | Fresh | Kahramaa electricity tariff |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Forward resource adequacy (assessed)
What is open
- Historical utility-territory delivery performance (would change the answer)
- Contractual service terms (would change the answer)
- Designed site resilience
- Cost evidence (would change the answer)
- Connection evidence (would change the answer)
- Regulatory evidence
- Substation-level capacity evidence
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- No cost or schedule range is compiled for this market.
What could disqualify this market
- Carbon.
- Scale.
Questions to put to the utility
- What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project caseWhy it is open: no compiled cost band for this market yet.
- How long is it from a complete application being accepted to full firm energization of the MW we need, and which milestones (initial, phased, temporary or conditional energization) would come first? Needed for a project caseWhy it is open: no countable queue or operator-published process for this market.
- What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project caseWhy it is open: no regulator outage series compiled for this market yet.
- Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?Why it is open: no dated regulatory read compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/qatar/gaps