Quebec

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/quebec, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$55 to $115 per MWh

Midpoint about $85 per MWh

How this band was built

triangulated

From 3 public fragments

What sets this band

There is no wholesale spot market here, so the band is not an energy-plus-network stack. It is set by the regulated tariff levels below.
$28
$95
$28$115
Legacy Rate L (large industrial)$28 /MWh
The general large-power industrial tariff, about 3.8 cents CAD per kWh, among the lowest anywhere. It applies to legacy or partial sites, not to a new data center.
Proposed data-centre rate$95 /MWh
Hydro-Quebec's filed dedicated rate for data centres over 5 MW, about 13 cents CAD per kWh, roughly double Rate L, pending the Regie de l'energie. This is what a new data center would pay.
These are the regulated tariff levels that define the band, not an additive cost stack. The band runs from legacy sites near Rate L up to new data centers at the proposed dedicated rate, which is why it is wide. Anchored to published figures (Hydro-Quebec proposed data-centre rate (CBC)).

Where the cost lands

$85
Low $55Midpoint $85High $115
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Quebec has no wholesale market, so the cost is Hydro-Quebec's regulated tariff. The general large-industrial Rate L is about 3.8 cents CAD per kWh (~$28 per MWh), among the lowest anywhere, but Hydro-Quebec has filed to roughly double the rate for data centres specifically, to about 13 cents CAD per kWh (~$95 per MWh), pending the Regie de l'energie, with a still-higher rate proposed for cryptocurrency.

The headline-cheap Quebec hydro rate is misleading for the load we rate: it is the general industrial tariff, not what a new data center will pay. A new data center over 5 MW faces the proposed dedicated data-centre rate of about 13 cents CAD per kWh, roughly double the industrial rate, phasing in over five years for existing sites. The band reflects legacy or partial sites near the industrial rate and new data centers at the proposed data-centre rate; it is a proposal pending the regulator, so it is labelled triangulated rather than measured.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Hydro-Quebec Rate L (large-power industrial) · Hydro-Quebec proposed data-centre rate (CBC).

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

Severe

Typical connection wait

4 to 6 years (authorization-gated)

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

Cheap hydro, but new large loads are authorization-gated: the Minister must approve any connection of 5 MW or more.

Quebec restricted new power procurement for large data centres in 2024, and under Bill 69 (June 2025) the Minister must authorize any new load of 5 MW or more on technical, economic and social criteria. Hydro-Quebec's proposed dedicated data-centre tariff runs about 13 cents per kWh, roughly double the large-power rate. Cheap, clean hydro is the draw; the gate is ministerial authorization and available capacity pending the Action Plan 2035 build.

What builds the 60-month wait

12
12
24
12
Ministerial authorization12 mo
Grid study & connection offer12 mo
Network reinforcement24 mo
Construction & energization12 mo
Typical time to energization60 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Osler: Canada grid connection policies).

Data-center share of demand pressure: High. Sources: Osler: Canada grid connection policies · Data centres in Canada (BLG). The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%55

Managed access: Bill 69 (2025) requires ministerial sign-off for new loads over 5 MW, and Hydro-Quebec has proposed a ~13 cents/kWh data-center rate (pending the Regie, R-4333-2026; hearings resume in December 2026). Approved projects proceed; this is a high bar, not a shut door.

Availability25%90

Exceptional availability: Hydro-Quebec reservoir hydro is a large, firm, dispatchable surplus.

Cost25%100

Cheap industrial power (Rate L, about 3.8 cents CAD/kWh), but that rate is for general industry; the proposed data-centre rate of about 13 cents CAD/kWh (roughly $95 US/MWh) would put a new data centre mid-pack, not lowest, and the Regie has not yet ruled (R-4333-2026).

Momentum15%30

Momentum stalled: historically attracted AWS/Google/Microsoft, but new large-load growth is paused under the governance regime.

Carbon5%100

Among the cleanest grids on earth (~5 g), almost entirely hydro.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 74 is reduced to 67, a deduction of 7 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

Major-event damage is largely distribution and sub-transmission; a transmission-connected firm-service load faces materially less exposure, though restoration during large storms is slow.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

event-based · Hydro-Quebec 2023 distribution activities

Historical utility-territory delivery performance: Reliability flags found

Storm-fragile delivery: the Apr 5, 2023 ice storm alone was about 59% of that year's unadjusted SAIDI, and 2024 unadjusted SAIDI was 436 minutes per customer (roughly half of 2023). Major-event-adjusted reliability is stable, so the risk is major-event frequency and slow restoration, not blue-sky performance.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

measured · Hydro-Quebec 2024 accountability report

Forward resource adequacy (assessed): No adequacy flags

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Slow load growth competing for the same capacity.
Can new supply arrive
Hydro-Quebec's Action Plan 2035 (about 185 billion CAD) is the new-supply pipeline, developed as partnership with First Nations and Inuit communities.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed→ stable

Why: Hydro-Quebec's proposed dedicated data-centre tariff roughly doubles the industrial rate and is pending the Regie de l'energie; managed pricing inside an otherwise open, low-cost system.

What would change the read: The Regie approving a workable dedicated rate with a clear, predictable allocation process.

For new supply: Hydro-Quebec's Action Plan 2035 (about 185 billion CAD) is the new-supply pipeline, developed as partnership with First Nations and Inuit communities.

Beyond the grid: New supply depends on Indigenous consent: a Quebec First Nation voted to reject a landmark Hydro-Quebec deal, and the utility now frames its large hydro expansion as ongoing partnership with First Nations and Inuit communities rather than one-off settlements. Globe and Mail BLG

Outlook drivers

↑ Upgrade triggers

  • Policy leans into AI growth: streamlined approvals or a dedicated large-load carve-out.
  • New supply from the Action Plan 2035 frees allocation.

↓ Downgrade triggers

  • The gate tightens further or the tariff rises sharply.
  • Strict prioritization keeps new greenfield hyperscale out.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
After Dec 2026
Regie de l'energie ruling on Hydro-Quebec's dedicated data-centre tariff (R-4333-2026); hearings ran 1-9 Oct 2026 and resume in December 2026, no ruling yet
Would set the roughly 13 cents CAD per kWh rate a new data center pays, versus the legacy industrial rate.
By Oct 2026
Quebec general election, with the Churchill Falls agreement still non-binding
The Parti Quebecois government, sworn in on 21 Oct 2026, says it will review the Churchill Falls and Gull Island agreement and bring it to the National Assembly; it has not said it will scrap it. The first real test of whether the 17 Aug announcement becomes a commitment.
End 2026
Definitive binding agreements on Churchill Falls and Gull Island targeted
Until they are executed nothing is contractually settled, and the federal Major Projects Office referral does not take effect.

Evidence behind this rating

The real-world events that test our Tier 2 call for Quebec: 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Quebec secures long-term Churchill Falls and Gull Island supply as the 1969 contract is terminated NON-BINDING ✓ Supports the rating
Aug 2026AvailabilityMateriality: high

The 17 Aug 2026 agreements end the 1969 power contract, and replace the December 2024 MOU. Hydro-Quebec continues to take Churchill Falls and Gull Island power under new commercial terms and participates in the Churchill Falls expansion, Gull Island and the associated transmission build. Premier Fréchette framed the agreement as securing Quebec's energy independence and enabling growth through renewable energy. For a large load weighing Quebec, this is long-run supply certainty on a system whose access is authorization-gated and whose dedicated data-centre tariff is still before the Regie. The new pricing terms are not stated in the government releases and are not recorded here.

Power to a buyer: No change to what a Quebec load can connect to today. Access stays authorization-gated and the dedicated data-centre tariff is still before the Regie.
Source: Government of Newfoundland and Labrador ↗
Regie hearing on the proposed data-centre tariff slips to fall 2026 ✓ Supports the rating
Jul 2026CostMateriality: low

The Regie de l'energie hearing on Hydro-Quebec's proposed data-centre rate is now set for fall 2026, with a decision expected late 2026 or early 2027, later than the H2 2026 in-force date originally proposed.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: BLG ↗
Hydro-Quebec proposes a dedicated data-centre tariff ▲ Challenges the rating
Jun 2026Cost / AccessMateriality: med

A new large-load rate for large data-centre sites, well above the current large-power rate, pending Regie de l'energie approval for H2 2026.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Hydro-Quebec / CBC ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Jul 2026
Under reviewThe Cost pillar (currently 100) is placed under review. On closer analysis, the proposed dedicated data-centre rate of about 13 cents CAD per kWh (roughly $95 US per MWh) puts Quebec mid-pack for a new data center rather than lowest in the set; the cheap Rate L (about 3.8 cents) applies to general industry, not to the load we rate. Reassessing whether the Cost score overstates the advantage for a new data center. Tier likely holds; the Cost pillar may ease.
Trigger: Realized-cost review of the Hydro-Quebec data-centre tariff (Jul 2026)
Jun 2026
AffirmedProposed data-centre tariff reviewed; this is managed pricing inside an open, low-cost system, not a closure. Price remains the lowest in the set; Tier 2 affirmed, outlook unchanged.
Trigger: Hydro-Quebec ~13 cents/kWh tariff proposal (Jun 2026)
Jul 2026
AffirmedTier holds. The tariff is still a proposal and its in-force date has slipped; no change until the Regie rules.
Trigger: Regie hearing timing update, Jul 2026
Oct 2026
Under reviewReview extended 2026-10-23. The cost read stays under review while we await the Regie de l'energie decision in case R-4333-2026, before deciding whether Quebec joins the cost comparison set. Tier and outlook held. Next review by 22 Nov 2026.
Trigger: Review extended, approved 23 Oct 2026; Regie de l'energie case R-4333-2026
Oct 2026
AffirmedAffirmed, no change, 31 Oct 2026. Closes the cost-pillar review of the Hydro-Québec data-centre tariff. The Régie de l'énergie has not ruled on case R-4333-2026: hearings ran 1-9 Oct 2026 and continue in December. On 26 Oct 2026 the Superior Court annulled the government decrees that backed the proposed rate; Hydro-Québec maintains its request. With no rate decided, the Cost assessment, tier and outlook are held. The Churchill Falls agreement remains non-binding and Gull Island is outside the outlook window. Revisit when the Régie decides R-4333-2026.
Trigger: Realized-cost review of the Hydro-Quebec data-centre tariff (Jul 2026); Régie case R-4333-2026
June 2026
New ratingNew rating: Tier 2 Strong assigned (light policy override).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostMarket-level (M2)Good for comparing markets, not for a site
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest field is connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

1 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

31 Oct 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmeasured2025FreshHydro-Quebec 2024 accountability report
Connection frictionproxy2025/26FreshOsler: Canada grid connection policies
Realized costtriangulated2026FreshHydro-Quebec Rate L (large-power industrial)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $55 to $115 per MWh, midpoint $85, basis triangulated, against the 100 MW archetype
  • Historical bulk-system performance (event-based)

What is open

  • Forward resource adequacy (assessed)
  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $55 to $115 per MWh, midpoint $85 (triangulated)

What could disqualify this market

  • Policy and tariff uncertainty for unapproved new builds.
  • Allocation competition with electrification and exports.

Questions to put to the utility

These come from the gaps in our record for Quebec: the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  2. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/quebec/gaps