Quebec
The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/quebec, with every section open. As of June 2026.
Realized cost band
Recurring cost, delivered
$55 to $115 per MWh
Midpoint about $85 per MWh
What sets this band
Where the cost lands
The headline-cheap Quebec hydro rate is misleading for the load we rate: it is the general industrial tariff, not what a new data center will pay. A new data center over 5 MW faces the proposed dedicated data-centre rate of about 13 cents CAD per kWh, roughly double the industrial rate, phasing in over five years for existing sites. The band reflects legacy or partial sites near the industrial rate and new data centers at the proposed data-centre rate; it is a proposal pending the regulator, so it is labelled triangulated rather than measured.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Hydro-Quebec Rate L (large-power industrial) · Hydro-Quebec proposed data-centre rate (CBC).
Connection friction
Friction level
Severe
Typical connection wait
4 to 6 years (authorization-gated)
This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.
Quebec restricted new power procurement for large data centres in 2024, and under Bill 69 (June 2025) the Minister must authorize any new load of 5 MW or more on technical, economic and social criteria. Hydro-Quebec's proposed dedicated data-centre tariff runs about 13 cents per kWh, roughly double the large-power rate. Cheap, clean hydro is the draw; the gate is ministerial authorization and available capacity pending the Action Plan 2035 build.
What builds the 60-month wait
Data-center share of demand pressure: High. Sources: Osler: Canada grid connection policies · Data centres in Canada (BLG). The full cross-market connection dataset is available through the Connection Friction Feed.
The five pillars behind the tier
Managed access: Bill 69 (2025) requires ministerial sign-off for new loads over 5 MW, and Hydro-Quebec has proposed a ~13 cents/kWh data-center rate (pending the Regie, R-4333-2026; hearings resume in December 2026). Approved projects proceed; this is a high bar, not a shut door.
Exceptional availability: Hydro-Quebec reservoir hydro is a large, firm, dispatchable surplus.
Cheap industrial power (Rate L, about 3.8 cents CAD/kWh), but that rate is for general industry; the proposed data-centre rate of about 13 cents CAD/kWh (roughly $95 US/MWh) would put a new data centre mid-pack, not lowest, and the Regie has not yet ruled (R-4333-2026).
Momentum stalled: historically attracted AWS/Google/Microsoft, but new large-load growth is paused under the governance regime.
Among the cleanest grids on earth (~5 g), almost entirely hydro.
Reliability overlay
Historical bulk-system performance: Minor flags found
Major-event damage is largely distribution and sub-transmission; a transmission-connected firm-service load faces materially less exposure, though restoration during large storms is slow.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based · Hydro-Quebec 2023 distribution activities
Historical utility-territory delivery performance: Reliability flags found
Storm-fragile delivery: the Apr 5, 2023 ice storm alone was about 59% of that year's unadjusted SAIDI, and 2024 unadjusted SAIDI was 436 minutes per customer (roughly half of 2023). Major-event-adjusted reliability is stable, so the risk is major-event frequency and slow restoration, not blue-sky performance.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
measured · Hydro-Quebec 2024 accountability report
Forward resource adequacy (assessed): No adequacy flags
Contractual service terms: not assessed
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Designed site resilience: not applicable at market level
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
Supply relief outlook
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Regulatory momentum
Why: Hydro-Quebec's proposed dedicated data-centre tariff roughly doubles the industrial rate and is pending the Regie de l'energie; managed pricing inside an otherwise open, low-cost system.
What would change the read: The Regie approving a workable dedicated rate with a clear, predictable allocation process.
For new supply: Hydro-Quebec's Action Plan 2035 (about 185 billion CAD) is the new-supply pipeline, developed as partnership with First Nations and Inuit communities.
Beyond the grid: New supply depends on Indigenous consent: a Quebec First Nation voted to reject a landmark Hydro-Quebec deal, and the utility now frames its large hydro expansion as ongoing partnership with First Nations and Inuit communities rather than one-off settlements. Globe and Mail BLG
Outlook drivers
↑ Upgrade triggers
- Policy leans into AI growth: streamlined approvals or a dedicated large-load carve-out.
- New supply from the Action Plan 2035 frees allocation.
↓ Downgrade triggers
- The gate tightens further or the tariff rises sharply.
- Strict prioritization keeps new greenfield hyperscale out.
Scheduled to change
Evidence behind this rating
The real-world events that test our Tier 2 call for Quebec: 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
The 17 Aug 2026 agreements end the 1969 power contract, and replace the December 2024 MOU. Hydro-Quebec continues to take Churchill Falls and Gull Island power under new commercial terms and participates in the Churchill Falls expansion, Gull Island and the associated transmission build. Premier Fréchette framed the agreement as securing Quebec's energy independence and enabling growth through renewable energy. For a large load weighing Quebec, this is long-run supply certainty on a system whose access is authorization-gated and whose dedicated data-centre tariff is still before the Regie. The new pricing terms are not stated in the government releases and are not recorded here.
The Regie de l'energie hearing on Hydro-Quebec's proposed data-centre rate is now set for fall 2026, with a decision expected late 2026 or early 2027, later than the H2 2026 in-force date originally proposed.
A new large-load rate for large data-centre sites, well above the current large-power rate, pending Regie de l'energie approval for H2 2026.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
Rating history
Data provenance and freshness
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Market-level (M2) | Good for comparing markets, not for a site |
| Connection | Broad (M1) | Directional: good for screening and monitoring |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Source strength
Moderate
1 of 3 data layers directly measured; the rest are triangulated or modelled
Coverage
Full
3 of 3 dimensions: reliability, connection, cost
Last reviewed
31 Oct 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | measured | 2025 | Fresh | Hydro-Quebec 2024 accountability report |
| Connection friction | proxy | 2025/26 | Fresh | Osler: Canada grid connection policies |
| Realized cost | triangulated | 2026 | Fresh | Hydro-Quebec Rate L (large-power industrial) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
What this market can and cannot answer yet
What is established
- Recurring cost band $55 to $115 per MWh, midpoint $85, basis triangulated, against the 100 MW archetype
- Historical bulk-system performance (event-based)
What is open
- Forward resource adequacy (assessed)
- Historical utility-territory delivery performance (would change the answer)
- Contractual service terms (would change the answer)
- Designed site resilience
- Substation-level capacity evidence
How service and connection are organized
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
Credible ranges today
- Cost $55 to $115 per MWh, midpoint $85 (triangulated)
What could disqualify this market
- Policy and tariff uncertainty for unapproved new builds.
- Allocation competition with electrification and exports.
Questions to put to the utility
- What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project caseWhy it is open: no regulator outage series compiled for this market yet.
- What firm capacity is available at the substation we would connect to, and when? Needed for a project caseWhy it is open: no operator publication of area or substation capacity found for this market.
The same list as JSON: /api/v1/markets/quebec/gaps