⚡ POWERGRIDIQ · EVIDENCE PACK

Saudi Arabia

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/saudi-arabia, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$50 to $58 per MWh

Midpoint about $53 per MWh

How this band was built

administered

From 1 public fragment

What sets this band

There is no wholesale spot market here, so the band is not an energy-plus-network stack. It is set by the regulated tariff levels below.
$53
$50$58
Administered industrial tariff$53 /MWh
About 5.3 US cents per kWh, set by the regulator. There is no wholesale market, so the tariff is the delivered cost, and it moves only on a regulator decision.
These are the regulated tariff levels that define the band, not an additive cost stack. Anchored to published figures (Saudi Electricity Regulatory Authority (SERA)).

Where the cost lands

$53
Low $50Midpoint $53High $58
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: The administered industrial tariff, about 5.3 US cents per kWh. There is no wholesale market, so the tariff is the delivered cost.

Because Saudi Arabia has no competitive wholesale market, the realized cost is simply the administered industrial tariff, and the band is tight and firm. It moves only on a regulator decision.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Administered (a single regulated or state-set tariff, so the figure is the delivered cost and moves only on a regulator decision). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Saudi Electricity Regulatory Authority (SERA).

Large-user tariff

This market has no competitive wholesale power market, so the honest cost is the administered tariff a large load actually pays, all charges included, not a modelled spot price. A tariff market needs no live feed: it changes only when the regulator changes it.

Industrial tariff

about SAR 0.20 per kWh (about $0.053 per kWh)

administered, subsidized industrial rate, 2025

Trend

Stable and heavily subsidized; moves only on a regulator decision.

Saudi Arabia has no competitive wholesale market, so a large load pays the administered industrial tariff, about SAR 0.20 per kWh (roughly 5.3 US cents), among the lowest in the world. There is no spot price to track: the tariff is the truth, and it changes only when the regulator changes it.

Basis: measured. Source: Saudi Electricity Regulatory Authority (SERA).

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

Low

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

State-backed and fast: SERA and the Ministry of Energy site strategic AI loads into system planning at competitive rates.

Connection runs through SERA and the Ministry of Energy, which are integrating large new loads into system-level planning and siting them where grid capacity allows. Strategic AI projects such as Humain are prioritised and indicative power costs are quoted in the low single-digit US cents per kWh, so a state-aligned large load connects quickly; the watch item is siting to match grid capacity rather than a queue clock.

What builds the 24-month wait

4
6
8
6
Application & SERA / SEC approval4 mo
Grid study & connection offer6 mo
Network works8 mo
Construction & energization6 mo
Typical time to energization24 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Greenberg Traurig: Saudi data-centre framework).

Data-center share of demand pressure: High. Sources: Greenberg Traurig: Saudi data-centre framework · Saudi data-centre capacity sixfold since Vision 2030 (Arab News). The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%78

State-backed and fast access.

Availability25%70

Adequate and adding availability.

Cost25%88

Among the cheapest power globally.

Momentum15%58

Surging AI momentum (Humain, DataVolt).

Carbon5%12

High carbon (~600 g), oil-and-gas; the pillar that moves the rating under a carbon lens.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 72 is reduced to 67, a deduction of 5 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

Record-heat summers have caused localized outages when air-conditioning demand forced generating units offline, and reliability is uneven across the country.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

event-based · Record heat causing Saudi power outages

Historical utility-territory delivery performance: Minor flags found

Regional disparities between distribution operators; some areas are materially less reliable than others.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled

Forward resource adequacy (assessed): Adequacy flagged

Extreme summer cooling peaks strain supply from May to September; large capacity build is underway.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Moderate load growth competing for the same capacity.
Future firm supply
Future firm supply: adequacy flagged.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Outlook drivers

↑ Upgrade triggers

  • NEOM/sovereign-AI build converts to operating capacity.
  • Massive solar build lowers carbon.

↓ Downgrade triggers

  • Carbon-constrained buyers reweight away.
  • Water/cooling in extreme heat.

Evidence behind this rating

The real-world events that test our Tier 2 call for Saudi Arabia: 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Saudi sovereign-AI programs (Humain, DataVolt) scale compute demand ✓ Supports the rating
2025MomentumMateriality: low

State-backed AI infrastructure accelerates power demand on the cheapest-tier grid in the set.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: DCD ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Oct 2026
AffirmedCost-pillar score 95 to 88: now set by one published rule from the band midpoint ($53/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 69 to 67. Tier 2 Strong unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
June 2026
New ratingNew rating: Tier 2 Strong assigned (carbon-sensitive).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostMarket-level (M2)Good for comparing markets, not for a site
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryNot assessedWe hold no evidence for this yet
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest field is connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

2 of 4 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewhistorical2025FreshRecord heat causing Saudi power outages
Connection frictionproxy2025/26FreshGreenberg Traurig: Saudi data-centre framework
Large-user tariffadministered2025FreshSaudi Electricity Regulatory Authority (SERA)
Realized costmeasured2026FreshSaudi Electricity Regulatory Authority (SERA)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $50 to $58 per MWh, midpoint $53, basis administered, against the 100 MW archetype
  • Historical bulk-system performance (event-based)
  • Forward resource adequacy (assessed)

What is open

  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Regulatory evidence
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $50 to $58 per MWh, midpoint $53 (administered)

What could disqualify this market

  • Carbon for RE-mandated tenants.
  • Concentration in state-led programs.

Questions to put to the utility

These come from the gaps in our record for Saudi Arabia: the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  2. Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?
    Why it is open: no dated regulatory read compiled for this market yet.
  3. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/saudi-arabia/gaps

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.