⚡ POWERGRIDIQ · EVIDENCE PACK

South Africa

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/south-africa, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$92 to $128 per MWh

Midpoint about $110 per MWh

How this band was built

administered

From 1 public fragment

What sets this band

There is no wholesale spot market here, so the band is not an energy-plus-network stack. It is set by the regulated tariff levels below.
$110
$92$128
Eskom Megaflex large-industrial tariff$110 /MWh
Roughly 11 to 12 US cents per kWh, regulated by NERSA, strongly time-of-use and climbing steeply year on year. It is the delivered cost, not a market price.
These are the regulated tariff levels that define the band, not an additive cost stack. The band is wider than a single number because Megaflex is strongly time-of-use, and it rose 8.76% from 1 April 2026. Anchored to published figures (Eskom 2026/27 tariff increase).

Where the cost lands

$110
Low $92Midpoint $110High $128
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Eskom's regulated Megaflex large-industrial tariff, roughly 11 to 12 US cents per kWh, with meaningful time-of-use spread.

South Africa's realized cost is Eskom's regulated Megaflex tariff. The band is wider than a single number because Megaflex is strongly time-of-use, but it is administered, not a market price, and it is climbing steeply year on year.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Administered (a single regulated or state-set tariff, so the figure is the delivered cost and moves only on a regulator decision). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Eskom 2026/27 tariff increase.

Large-user tariff

This market has no competitive wholesale power market, so the honest cost is the administered tariff a large load actually pays, all charges included, not a modelled spot price. A tariff market needs no live feed: it changes only when the regulator changes it.

Industrial tariff

Eskom Megaflex (about $0.110 per kWh)

administered, Eskom Megaflex large-industrial tariff, 2026/27

Trend

Rising: up 8.76% from 1 April 2026, continuing a steep multi-year climb, with the fixed capacity charge growing as a share.

South Africa's large loads buy on Eskom's regulated Megaflex tariff, not a market. It rose 8.76% from 1 April 2026 (roughly 11 to 12 US cents per kWh) as part of a steep multi-year climb. The tariff, not a spot price, is what a data center pays.

Basis: measured. Source: Eskom 2026/27 tariff increase.

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

High

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

Load-shedding has eased, but Eskom's GCCA shows no spare grid capacity across the western half of the country.

Eskom reached 300-plus days without load-shedding by early 2026, but its Generation Connection Capacity Assessment shows no capacity for new connection across the western half of the country, and hyperscalers (Microsoft, AWS, Google) are competing for Johannesburg and Cape Town capacity. Developers increasingly pair grid connection with on-site solar and gas to secure power.

What builds the 48-month wait

12
12
12
12
Application & Eskom cost estimate / budget quote12 mo
Grid connection agreement12 mo
Network build12 mo
Construction & energization12 mo
Typical time to energization48 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Eskom Generation Connection Capacity Assessment (GCCA 2025)).

Data-center share of demand pressure: Rising. Sources: Eskom Generation Connection Capacity Assessment (GCCA 2025) · Teraco solar for South Africa data centres (DCD). The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%58

Workable access; Africa's deepest data-center market.

Availability25%50

Recovering availability: 231 consecutive days without load-shedding in 2025, EAF rising.

Cost25%57

Cheap-ish power.

Momentum15%50

Real momentum (Teraco, hyperscaler regions).

Carbon5%16

High carbon (~585 g), coal-led but adding renewables.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 53 is reduced to 49, a deduction of 4 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

Modelled read: multi-year load-shedding eased sharply (long clear stretches in 2025); recovery durability is the watch.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled

Historical utility-territory delivery performance: No reliability flags found

Forward resource adequacy (assessed): No adequacy flags

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Low. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Moderate load growth competing for the same capacity.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Outlook drivers

↑ Upgrade triggers

  • Continued Eskom recovery and renewables build.
  • Hyperscaler regions scale.

↓ Downgrade triggers

  • Load-shedding returns.
  • Coal-carbon for RE-mandated tenants.

Evidence behind this rating

The real-world events that test our Tier 3 call for South Africa: 4 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Eskom completes the 2026 winter with no load shedding and its best availability since 2020 IN SERVICE ✓ Supports the rating
Sep 2026AvailabilityMateriality: med

Reported 7 Sep 2026. Eskom's year to date energy availability factor reached its highest since 2020, with unplanned outages sharply down on three years ago and a reduced call on diesel open cycle gas turbines. The load reduction eradication programme has returned most targeted customers to normal supply, with seven provinces clear.

Power to a buyer: Power that is already flowing, and more of it than three years ago. No new plant: this is the existing fleet running better, which Eskom describes as capacity effectively restored. A buyer gets a materially lower probability of scheduled interruption than the rating's history implies.
Source: SAnews, Government of South Africa ↗
Eskom extends its run without load-shedding and posts its best daily availability since 2017 ✓ Supports the rating
Aug 2026AvailabilityMateriality: low

Eskom reported (4 Aug 2026) a continuing run without load-shedding, with demand met in full from 1 Apr to 30 Jul 2026, and on 26 Jul 2026 its highest daily energy availability factor since 2017. The winter outlook to 31 Aug 2026 continues to project no load-shedding. Updates the prior one year entry.

Power to a buyer: No change to large-load cost or timing: no new plant or connection terms. It is the existing fleet meeting demand in full.
Source: SAnews / Eskom ↗
Eskom passes one year with zero load-shedding ✓ Supports the rating
Jun 2026AvailabilityMateriality: med

A full year without load-shedding reached 16 May 2026; unplanned outages are well down year-on-year and the winter outlook projects continued stability. Updates the prior entry.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: SAnews / Eskom ↗
South Africa runs 231 consecutive days without load-shedding ✓ Supports the rating
2025AvailabilityMateriality: med

Eskom's energy-availability factor is recovering, a major reliability turnaround from the 2023 crisis.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Eskom ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Oct 2026
AffirmedCost-pillar score 70 to 57: now set by one published rule from the band midpoint ($110/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 52 to 49. Tier 3 Workable unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
Sep 2026
AffirmedTier holds, and the upgrade trigger set previously stays live. A second consecutive winter without load shedding, with availability at a six year high and diesel reliance down, is the sustained performance the trigger asked for on the demand-peak side. We said we would want a full summer peak before treating recovery as grounds for an upgrade, and that has not happened yet. Revisit after the 2026-27 summer.
Trigger: Eskom reports a load shedding free 2026 winter, EAF 67.79 percent, 7 Sep 2026
Aug 2026
AffirmedTier holds. A 441 day run and a daily EAF of 82.04%, the best since 2017, extend a recovery the rating already reflects and keep the previously set upgrade trigger live. We would want sustained performance through a full summer peak before treating this as grounds for an upgrade.
Trigger: Eskom performance update, 4 Aug 2026
Jun 2026
AffirmedReliability recovery reviewed; a sustained run without load-shedding supports the availability read. Tier affirmed, with an upgrade trigger if the recovery holds.
Trigger: 231 consecutive days without load-shedding (2025)
Jun 2026
AffirmedThe availability-recovery upgrade trigger set previously is now met: a full year without load-shedding. Tier affirmed; the formal upgrade review is due in the Jan 2027 release.
Trigger: One year with zero load-shedding (16 May 2026)
June 2026
New ratingNew rating: Tier 3 Workable assigned.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostMarket-level (M2)Good for comparing markets, not for a site
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryNot assessedWe hold no evidence for this yet
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest field is connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

2 of 4 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmodelled2025Freshon the market page
Connection frictionproxy2025/26FreshEskom Generation Connection Capacity Assessment (GCCA 2025)
Large-user tariffadministered2026/27FreshEskom 2026/27 tariff increase
Realized costmeasured2026FreshEskom 2026/27 tariff increase

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $92 to $128 per MWh, midpoint $110, basis administered, against the 100 MW archetype
  • Historical bulk-system performance (modelled)

What is open

  • Forward resource adequacy (assessed)
  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Regulatory evidence
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $92 to $128 per MWh, midpoint $110 (administered)

What could disqualify this market

  • Reliability recovery durability.
  • Carbon.

Questions to put to the utility

These come from the gaps in our record for South Africa: the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  2. Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?
    Why it is open: no dated regulatory read compiled for this market yet.
  3. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/south-africa/gaps

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.