⚡ POWERGRIDIQ · EVIDENCE PACK

SPP (Southwest Power Pool)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/spp, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$42 to $68 per MWh

Midpoint about $54 per MWh

How this band was built

triangulated

From 2 public fragments

What builds the $54 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$30
$20
Wholesale energy$30
Transmission & delivery$20
Ancillary & other$4
All-in delivered$54 /MWh
Transmission & delivery is a bundled category. It currently combines transmission, distribution and applicable demand-related network charges in one line. Those elements have not been independently sourced or separately reconciled.
How the $54/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. SPP has no capacity-auction market, so there is no separate capacity charge. The main non-energy cost is transmission, which is high per MWh because of the region's heavy wind-driven grid build-out. Anchored to published figures (SPP 2024 State of the Market). How this is built →
What the classes mean →

Where the cost lands

$54
Low $42Midpoint $54High $68
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Wholesale energy near $26 to $28 per MWh in 2024, among the lowest in the US, plus transmission and ancillary services. SPP runs no capacity-auction market.

The Southwest Power Pool has some of the cheapest wholesale energy in the country, wind-driven and low. The main non-energy cost is transmission, high per MWh because of the region's heavy grid build-out for wind.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: SPP 2024 State of the Market · Wholesale electricity prices (EIA).

Interconnection queue

These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.

Active queue depth

171 GW

Typical wait

50 months

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%65

Open, connect-and-manage-leaning access with an ERAS fast-track.

Availability25%65

Good availability on a strong wind base with room to grow.

Cost25%88

Among the cheapest US power.

Momentum15%50

Moderate momentum: emerging (Oklahoma, Kansas).

Carbon5%58

Carbon moderate (~290 g), wind-heavy but still some fossil.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 69 is reduced to 63, a deduction of 6 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Reliability flags found

Ordered rolling blackouts during Winter Storm Uri (Feb 2021), its first-ever region-wide firm load shed, when extreme cold knocked out generation.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

event-based · FERC/NERC Feb 2021 cold weather final report

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 104.32 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 20 of 20 territories, 100% of customers, regional context only)

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. mixed methods: IEEE 82%; respondent-defined 18% of customers. Major event days are excluded throughout; the methods differ only in how those days are identified, a smaller difference than the spread between the utilities themselves. Constituents below carry their own standard. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

The territories inside this market

The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.

Territory operatorSAIDI min/yrCustomersMajor-event method
Oklahoma Gas & Electric Co (OK)98.42833,706own method
Public Service Co of Oklahoma (OK)116.7579,031IEEE 1366
Omaha Public Power District (NE)85.7403,157IEEE 1366
Evergy Kansas Central, Inc (KS)101.58392,397IEEE 1366
Evergy Missouri West (MO)118.82346,863IEEE 1366
Evergy Kansas South, Inc (KS)87.12344,853IEEE 1366
Evergy Metro (MO)103.93311,001IEEE 1366
Evergy Metro (KS)61.15285,403IEEE 1366
Southwestern Public Service Co (TX)116.21268,277IEEE 1366
Southwestern Electric Power Co (TX)234.8192,067IEEE 1366
Empire District Electric Co (MO)141.48166,833IEEE 1366
Lincoln Electric System (NE)19.3151,839IEEE 1366
City Utilities of Springfield - (MO) (MO)65.33121,822IEEE 1366
Southwestern Public Service Co (NM)135.46118,975IEEE 1366
Nebraska Public Power District (NE)74.3593,975IEEE 1366
Mountrail-Williams Elec Coop (ND)146.8119,103IEEE 1366
McKenzie Electric Coop Inc (ND)209.7413,546IEEE 1366
Empire District Electric Co (KS)89.5110,232IEEE 1366
Empire District Electric Co (OK)88.355,928IEEE 1366
Grand River Dam Authority (OK)29.92213own method

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Adequacy flagged

NERC's 2024 assessment rates SPP elevated-risk as demand grows against a changing resource mix.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

assessed · NERC 2024 Long-Term Reliability Assessment

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 104.32 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across 20 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 20 of 20 territories, 100% of customers, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Easing
Demand pressure
Moderate load growth competing for the same capacity.
New supply in motion
About 42.8 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Can new supply arrive
Regulatory momentum mixed, improving.
Future firm supply
Future firm supply: adequacy flagged.

What this means: The supply crunch looks likely to ease for a new load energizing here in the coming years.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed↑ improving

Why: FERC's 18 June 2026 Section 206 show-cause order directs SPP to justify or reform its large-load rules; SPP's relatively uncongested, low-cost footprint and active courting of new load make it one of the more open US responses.

What would change the read: SPP's Section 206 filing locking in a fast, transparent large-load connection pathway before demand outpaces the grid.

Outlook drivers

↑ Upgrade triggers

  • Big AI/data-center announcements convert to operating load.
  • Transmission build unlocks more wind.

↓ Downgrade triggers

  • Thin ecosystem keeps tenants on the coasts.
  • Wind variability without enough firming.

Evidence behind this rating

The real-world events that test our Tier 2 call for SPP (Southwest Power Pool): 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

DOE cancels the last three proposed national transmission corridors, returning siting to the states ANNOUNCED ▲ Challenges the rating
Aug 2026AccessMateriality: low

Energy Secretary Chris Wright announced on 12 Aug 2026 that DOE will not designate the Lake Erie-Canada, Southwestern Grid Connector or Tribal Energy Access corridors, the three National Interest Electric Transmission Corridors carried forward from Dec 2024. The areas cover parts of Pennsylvania, Colorado, New Mexico, Oklahoma, North Dakota, South Dakota and Nebraska. None had been designated, so no existing federal backstop siting authority is withdrawn, but the route to one closes. The Federal Power Act still lets a future secretary restart the process.

Power to a buyer: No megawatts either way. All three corridors were proposals that were never designated, so no project loses a federal siting route it already had. What narrows is future optionality for long-haul transmission; the Federal Power Act still lets a later secretary restart the process.
Source: US Department of Energy ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Jun 2026
AffirmedNamed in the FERC show-cause suite; preliminary stage, tier holds, monitoring.
Trigger: FERC Section 206 show-cause order (18 Jun 2026)
Aug 2026
AffirmedTier holds. The cancelled corridors were proposals, never designated, and SPP large-load access does not depend on federal backstop siting. Marginal negative for long-haul transmission optionality across the footprint, not a pillar move.
Trigger: DOE cancellation of three proposed National Interest Electric Transmission Corridors, 12 Aug 2026
June 2026
New ratingNew rating: Tier 2 Strong assigned.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

What this would mean for a project

100 MW contracted demand, 95% load factor, HV servicecalculated

A load of this shape consumes 832,200 MWh a year. At the delivered band of $42 to $68/MWh that is $34,952,400 to $56,589,600 a year in recurring power.

Wholesale energy is 56% of the delivered cost here. The other $24/MWh is transmission and delivery, and ancillary and other charges. See the full build-up.

Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionMarket-level (M2)Good for comparing markets, not for a site
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are connection and reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

2 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 20 of 20 territories, 100% of customers, regional context only)
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshLBNL Queued Up 2026
Realized costtriangulated2026FreshSPP 2024 State of the Market

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $42 to $68 per MWh, midpoint $54, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 104.32 minutes per year (2024)
  • Historical bulk-system performance (event-based)
  • Forward resource adequacy (assessed)
  • Typical interconnection wait about 50 months (generation and storage queue, not a load wait)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Substation-level capacity evidence

How service and connection are organized

Territories in this market, each with its own filed record: Oklahoma Gas & Electric Co, Public Service Co of Oklahoma, Omaha Public Power District, Evergy Kansas Central, Inc, Evergy Missouri West, Evergy Kansas South, Inc, Evergy Metro, Evergy Metro. Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $42 to $68 per MWh, midpoint $54 (triangulated)
  • Schedule: interconnection queues here run about 50 months for generation and storage; a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Revealed-demand maturity.
  • Wind-balancing and firming.

Questions to put to the utility

These come from the gaps in our record for SPP (Southwest Power Pool): the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/spp/gaps

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.