⚡ POWERGRIDIQ · EVIDENCE PACK

Sweden North (Lulea, SE1/SE2)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/sweden-north, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$35 to $65 per MWh

Midpoint about $48 per MWh

How this band was built

modelled

From 2 public fragments

What builds the $48 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$40
$6
Wholesale energy$40
Network charges$6
Taxes & levies$2
All-in delivered$48 /MWh
How the $48/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (modelled). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. Surplus hydro in the northern bidding zones keeps energy low and stable, with modest network charges, one of the cheapest large-load bands in the world. Anchored to published figures (EU electricity price components (Eurostat)). How this is built →
What the classes mean →

Where the cost lands

$48
Low $35Midpoint $48High $65
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Abundant northern hydro in bidding zones SE1 and SE2, plus modest network charges.

Northern Sweden has one of the cheapest large-load bands in the world: surplus hydro in the northern bidding zones keeps wholesale prices low and stable. This is a large reason the north of Sweden is a magnet for new heavy load.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Modelled (estimated from a model and structural indicators where direct published figures are limited). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Non-household electricity prices, Nordics low (Eurostat).

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

Low

Typical connection wait

1 to 3 years

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

Cheap, stable northern power and comparatively fast connections; where Meta built.

The northern zones (SE1/SE2) offer the cheapest power in Europe, a stable surplus, and comparatively fast grid connections, which is why hyperscalers including Meta built there. The regional surplus is tightening as demand grows (the Nordic surplus falls from about 53 TWh in 2026 toward about 29 TWh by 2030), but the north remains among the most connectable markets in Europe.

What builds the 24-month wait

4
8
6
6
Application & site4 mo
Grid study & connection offer8 mo
Agreement & works planning6 mo
Construction & energization6 mo
Typical time to energization24 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Argus: Nordic data centres and power demand).

Data-center share of demand pressure: High. Sources: Argus: Nordic data centres and power demand · EQT: the Nordics and AI energy. The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%70

Open access with room where the power is generated; the north is a net exporter to the south.

Availability25%80

High availability: a persistent hydro-and-wind surplus in SE1/SE2.

Cost25%91

Cheapest power in Europe: SE1 (Lulea) runs a fraction of the southern-zone price.

Momentum15%60

Proven momentum: Meta's hyperscale Lulea campus anchors the cluster.

Carbon5%99

Near-zero operational carbon: hydro and wind.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability reviewed: no material concerns were found, so the rating is unchanged. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: No reliability flags found

Northern Sweden runs a large, stable hydro surplus; delivery reliability is strong and there is no local forward adequacy concern.

measured · Meta chose Lulea for stable renewable power (Seoul Economic)

Historical utility-territory delivery performance: No reliability flags found

Forward resource adequacy (assessed): No adequacy flags

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Moderate load growth competing for the same capacity.
Can new supply arrive
Regulatory momentum mixed, improving.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed↑ improving

Why: Svenska kraftnat issued preliminary connection assessments above 5,000 MW across 2025 and early 2026, a record, and has cut the queue through maturity-based requirements so the most ready projects connect faster; its 2026-2035 plan commits about SEK 225 billion, prioritising the industrial north of Norrbotten and Vasterbotten.

What would change the read: The maturity-based queue and the northern grid build delivering firm dates as flows from SE2 into SE1 tighten.

Outlook drivers

↑ Upgrade triggers

  • More hyperscale build on cheap northern surplus.
  • New transmission monetizes the surplus without eroding local cost.

↓ Downgrade triggers

  • Export constraints keep the surplus stranded.
  • Cold-snap peaks and permitting friction.

Evidence behind this rating

The real-world events that test our Tier 1 call for Sweden North (Lulea, SE1/SE2): 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Meta's Lulea hyperscale campus runs on northern-Sweden hydropower ✓ Supports the rating
2025MomentumMateriality: high

Meta's three-building Lulea campus, its first hyperscale data center outside the US, runs almost entirely on Lule River hydropower with some of the lowest, cleanest power in Europe, confirming the cheap, clean, firm profile that makes this the lowest all-in market we compile.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Meta Data Centers ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Oct 2026
AffirmedCost-pillar score 94 to 91: now set by one published rule from the band midpoint ($48/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 78 to 77. Tier 1 Prime unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
June 2026
New ratingNew rating: Tier 1 Prime assigned (northern zones SE1/SE2).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostBroad (M1)Directional: good for screening and monitoring
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are cost and connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Limited

1 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

Source strength is limited: 1 of 3 data layers directly measured; the rest are triangulated or modelled. Confidence in the rating (High) is a separate judgement about the opinion as a whole, set in review; source strength grades only how directly the numbers underneath were measured.

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmeasured2025FreshMeta chose Lulea for stable renewable power (Seoul Economic)
Connection frictionproxy2025/26FreshArgus: Nordic data centres and power demand
Realized costmodelled2026FreshNon-household electricity prices, Nordics low (Eurostat)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $35 to $65 per MWh, midpoint $48, basis modelled, against the 100 MW archetype
  • Historical bulk-system performance (measured)

What is open

  • Forward resource adequacy (assessed)
  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $35 to $65 per MWh, midpoint $48 (modelled)

What could disqualify this market

  • Northern transmission limits.
  • Winter demand peaks.

Questions to put to the utility

These come from the gaps in our record for Sweden North (Lulea, SE1/SE2): the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  2. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/sweden-north/gaps

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.