⚡ POWERGRIDIQ · EVIDENCE PACK

United Arab Emirates

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/uae, with every section open. As of June 2026.

Back to the report

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$50 to $85 per MWh

Midpoint about $65 per MWh

How this band was built

modelled

From 2 public fragments

What sets this band

There is no wholesale spot market here, so the band is not an energy-plus-network stack. It is set by the regulated tariff levels below.
$65
$50$85
Regulated commercial / large-load rate (ADDC, DEWA)$65 /MWh
The UAE runs regulated utility rates, not a wholesale market. Abu Dhabi's flat commercial rate is about 20 fils per kWh (roughly 54 US dollars per MWh) with no fuel surcharge; Dubai's DEWA slabs and fuel surcharge run higher. Abundant gas and record-cheap solar underpin the low band.
These are the regulated tariff levels that define the band, not an additive cost stack. The band reflects the regulated utility rate on abundant gas and among the world's cheapest solar; it is a tariff, not a spot price, and Abu Dhabi sits below Dubai. Anchored to published figures (UAE electricity price (GlobalPetrolPrices, Dec 2025)).

Where the cost lands

$65
Low $50Midpoint $65High $85
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: A regulated utility rate (Abu Dhabi's ADDC or Dubai's DEWA) on abundant natural gas and record-low solar, with Abu Dhabi the cheaper of the two.

The UAE is one of the cheaper large-load markets in the coverage: Abu Dhabi's flat commercial rate is around 54 US dollars per MWh with no fuel surcharge, and record-low solar tariffs keep the generation cost down. Dubai runs a little higher. State-backed pricing for strategic AI loads can land lower still.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Modelled (estimated from a model and structural indicators where direct published figures are limited). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: UAE electricity price (GlobalPetrolPrices) · Abu Dhabi commercial tariff (UAE utility guide).

Large-user tariff

This market has no competitive wholesale power market, so the honest cost is the administered tariff a large load actually pays, all charges included, not a modelled spot price. A tariff market needs no live feed: it changes only when the regulator changes it.

Industrial tariff

about 26 to 32 fils per kWh (about $0.080 per kWh)

administered, EtihadWE large-load and data-centre incentive rate, 2026

Trend

An incentive rate aimed at data centres and heavy industry, plus a fuel surcharge of about 5 fils; below general commercial rates but well above the cost of gas generation.

The United Arab Emirates has no competitive wholesale market, so a large load pays an administered tariff, not a spot price. EtihadWE's large-load incentive rate for data centres and heavy industry is about 26 to 32 fils per kWh (roughly 7 to 9 US cents, or 70 to 90 US dollars per MWh), plus a fuel surcharge. That is the honest delivered cost, far above the cheap-gas generation cost, and it places the UAE mid-pack globally rather than among the cheapest.

Basis: measured. Source: EtihadWE large-industrial incentive rate.

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

Low

Typical connection wait

1 to 3 years

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

State-backed and fast: DEWA and EWEC coordinate large-load connections on abundant gas and cheap solar.

The UAE is one of the more connectable large-load markets: vertically integrated, state-directed utilities (DEWA in Dubai, EWEC in Abu Dhabi) coordinate connections on abundant gas and among the world's cheapest solar, and sovereign AI projects are prioritised. The forward watch item is heat-driven summer peaks and water for cooling, not a queue clock.

What builds the 24-month wait

4
6
8
6
Application & approval4 mo
Grid study & connection offer6 mo
Network works8 mo
Construction & energization6 mo
Typical time to energization24 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (UAE electricity price (GlobalPetrolPrices)).

Data-center share of demand pressure: High. Sources: UAE electricity price (GlobalPetrolPrices) · Abu Dhabi commercial tariff (UAE utility guide). The full cross-market connection dataset is available through the Connection Friction Feed.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%82

State-backed and fast: national champions (G42, Khazna) and a coordinated build mean connection is quick by global standards.

Availability25%70

Adequate and adding: capacity is expanding fast, and Barakah nuclear (~23% of generation) adds firm, low-carbon baseload.

Cost25%82

Cheap power: among the lowest wholesale costs globally, a major draw for compute.

Momentum15%80

AI-driven momentum: 358 MW operational heading toward ~950 MW by 2028, a ~1.4 GW pipeline including Stargate-class projects.

Carbon5%42

Carbon is moderate (~380 g) thanks to nuclear and solar, but still gas-led; this is the pillar that moves the rating under a carbon lens.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 77 is reduced to 74, a deduction of 3 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: No reliability flags found

Historical utility-territory delivery performance: No reliability flags found

World-leading delivery reliability in the main load centre: DEWA (Dubai) reported customer minutes lost of 0.82 minutes per year in 2025, a global record, versus roughly 15 minutes at leading EU utilities.

measured · DEWA world-record CML (Arabian Business)

Forward resource adequacy (assessed): Adequacy flagged

Firm baseload is strong (Barakah nuclear supplies about 25% of national electricity, roughly 5.6 GW), but extreme-heat cooling demand drives high summer peaks; capacity is expanding to match.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled · Barakah at ~25% of UAE electricity (World Nuclear Assoc.)

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Tightening
Demand pressure
Fast load growth competing for the same capacity.
Future firm supply
Future firm supply: adequacy flagged.

What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.

Outlook drivers

↑ Upgrade triggers

  • AI pipeline converts from announced to operational at scale.
  • Continued nuclear and solar growth keeps lowering grid carbon.

↓ Downgrade triggers

  • A carbon-constrained buyer base (EU-tied, hyperscaler RE mandates) reweights away from the region.
  • Water and cooling constraints in extreme heat.

Scheduled to change

Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
2026
First 200 MW of the Stargate UAE campus targeted for energization
The initial tranche of the 5 GW Abu Dhabi build; confirms the pace of the Tier 1 momentum.

Evidence behind this rating

The real-world events that test our Tier 1 call for United Arab Emirates: 2 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Stargate UAE: a large Abu Dhabi AI campus, the largest outside the US, begins build-out ✓ Supports the rating
2025MomentumMateriality: high

G42, OpenAI, Oracle, Nvidia and SoftBank are building Stargate UAE, a compute cluster inside a UAE-US AI campus in Abu Dhabi, with a first phase targeted for 2026, powered by nuclear, solar and gas. A build of this scale confirms the abundant firm power and pro-build stance behind the Tier 1 rating.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: OpenAI ↗
Barakah nuclear supplies a large share of UAE generation ✓ Supports the rating
2025Carbon / AvailabilityMateriality: med

The completed plant cleans the grid and adds firm, low-carbon baseload as the sovereign-AI build accelerates.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: The National ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

Oct 2026
AffirmedCost-pillar score 90 to 82: now set by one published rule from the band midpoint ($65/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 76 to 74. Tier 1 Prime unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
Jul 2026
Under reviewThe Cost pillar (currently 90) is placed under review. The figure reflected the cheap-gas generation cost, not the delivered tariff: EtihadWE's large-load and data-centre incentive rate is about 26 to 32 fils per kWh (roughly $70 to $90 per MWh), which is mid-pack globally, not among the cheapest. Reassessing the Cost score, which may ease; because the Prime rating leans partly on cost, the Tier 1 status is being re-examined.
Trigger: Realized-cost review of the EtihadWE large-load tariff (Jul 2026)
Jun 2026
AffirmedTier 1 Prime affirmed on abundant firm gas capacity, an open pro-build stance, and a strong national AI-power agenda.
Trigger: National AI and data-centre build-out (2026)
Oct 2026
AffirmedAffirmed, no change, 23 Oct 2026. Closes the cost-pillar review of the EtihadWE large-load tariff. Since the cost-rescore release of 15 Oct 2026 the UAE Cost pillar is scored from its delivered-cost band rather than the cheap-gas generation cost, which is the question the review asked. Tier and outlook held.
Trigger: Realized-cost review of the EtihadWE large-load tariff (Jul 2026); cost-rescore release, 15 Oct 2026
June 2026
New ratingNew rating: Tier 1 Prime assigned (carbon-sensitive).
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostBroad (M1)Directional: good for screening and monitoring
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryNot assessedWe hold no evidence for this yet
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are cost and connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

2 of 4 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

23 Oct 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmeasured2025FreshDEWA world-record CML (Arabian Business)
Connection frictionproxy2025/26FreshUAE electricity price (GlobalPetrolPrices)
Large-user tariffadministered2026FreshEtihadWE large-industrial incentive rate
Realized costmodelled2026FreshUAE electricity price (GlobalPetrolPrices)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $50 to $85 per MWh, midpoint $65, basis modelled, against the 100 MW archetype
  • Forward resource adequacy (assessed)

What is open

  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Regulatory evidence
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $50 to $85 per MWh, midpoint $65 (modelled)

What could disqualify this market

  • Carbon profile for RE-mandated tenants.
  • Concentration in a few state-led developers.

Questions to put to the utility

These come from the gaps in our record for United Arab Emirates: the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  2. Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?
    Why it is open: no dated regulatory read compiled for this market yet.
  3. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/uae/gaps

Generated with the report at each build; free, like the report. For information only; not investment, engineering or procurement advice.