⚡ POWERGRIDIQ · EVIDENCE PACK

US Southeast (Atlanta)

The evidence behind the PGIQ Rating, exactly as printed on powergridiq.com/rating/us-southeast, with every section open. As of June 2026.

Back to the report

Realized cost band

Withdrawn. The band was anchored on a regulated bundled industrial tariff that a new 100 MW load cannot take: Georgia closed its standard schedules to new large loads on 1 February 2025 and requires an individually negotiated contract instead. The band's primary source was also EIA industrial monthly pricing, which may serve only as a lagged validation layer and not as the headline large-load price.

No delivered-cost band is published for this market, and no substitute figure has been put in its place. Screening on recurring cost returns insufficient evidence for this market rather than a value we cannot defend.

Restored when: Executed or filed large-load contract terms for a comparable customer, or a published contract-based rate the archetype could actually be offered, with a stated cost boundary, effective date, method and confidence. EIA industrial pricing may corroborate such a band but may not be its primary source. Withdrawn 2026-08-20.

Interconnection queue

These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.

Active queue depth

153 GW

Typical wait

50 months

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%65

Workable access: faster than PJM, with utility-led connection and active large-load accommodation.

Availability25%60

Moderate availability: Southern Company is adding gas and solar to keep pace with the build.

Cost25%72

Reasonable cost: mid-range wholesale, cheaper than the coastal hubs.

Momentum15%88

Very high momentum: ~2 GW under construction, a top-three NA market by inventory growth.

Carbon5%60

Carbon moderate (~270 g), gas-and-nuclear with rising solar.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.

Reliability overlay

Reliability adjustment: the five-pillar score of 69 is reduced to 65, a deduction of 4 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

Winter Storm Elliott (Dec 2022) forced rolling blackouts at TVA (its first ever) and Duke Energy in the Carolinas when cold knocked out coal and gas generation; imports prevented wider outages.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

event-based · FERC Dec 2022 Winter Storm Elliott review

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 114.26 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 6 of 6 territories, 100% of customers, regional context only)

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. major event days identified by IEEE 1366 (2.5-beta method). It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment (being told to cut output or consumption) rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

The territories inside this market

The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.

Territory operatorSAIDI min/yrCustomersMajor-event method
Georgia Power Co (GA)127.942,717,959IEEE 1366
Jackson Electric Member Corp - (GA) (GA)73.94268,760IEEE 1366
Cobb Electric Membership Corp (GA)35.12218,807IEEE 1366
Sawnee Electric Membership Corporation (GA)45.7200,598IEEE 1366
GreyStone Power Corporation (GA)94.99149,514IEEE 1366
Walton Electric Member Corp (GA)168.48140,132IEEE 1366

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Adequacy flagged

Winter generation adequacy under extreme cold is the main forward risk; largely vertically integrated utilities are adding capacity.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled

Contractual service terms: firm with take or pay

Since 1 February 2025 a new customer whose expected peak demand is 100 MW or more, at one site or contiguous tracts, may no longer take the standard large-power tariffs (PLL-18, or the standard price option of TOU-SC-15) at all. It must negotiate a customised contract under a rule the Georgia commission approved on 23 January 2025. Service is firm: there is no curtailment obligation attached, which distinguishes this from ERCOT or Ireland. The exposure is commercial instead. Contracts now run up to 15 years, against a previous maximum of 5, and carry minimum billing, so the customer pays a set amount each month whatever it actually consumes. Before construction begins the utility may require collateral, a security deposit or a letter of credit, to secure recovery of what it spends preparing to serve. Ending early can require repaying the distribution, transmission and generation investment made to get ready. Every contract at or above the threshold must be filed with the commission at least 30 days before signature, which creates a review window but also means the terms are individually negotiated and not public: there is no template to price against. As of late 2025 the utility had signed 29 large-load commitments, of which 6 are named and 22 remain confidential.

What the service contract promises, as distinct from how the system has performed · Georgia Power Rules and Regulations tariff, large-load provisions (2025)

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 114.26 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across 6 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 6 of 6 territories, 100% of customers, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Easing
Demand pressure
Fast load growth competing for the same capacity.
New supply in motion
About 38.2 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Can new supply arrive
Regulatory momentum mixed, improving.
Future firm supply
Future firm supply: adequacy flagged.

What this means: The supply crunch looks likely to ease for a new load energizing here in the coming years.

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed↑ improving

Why: Georgia's PSC now requires any new load of 100 MW or more to sign a customized contract with financial guarantees, terms up to 15 years and minimum payments (in force since 1 February 2025), and in December 2025 approved roughly 10 GW of new generation, about 80 percent to serve data centres, with cost protections for residential customers. Access is managed and selective but genuinely open.

What would change the read: The customized-contract regime and the April 2026 Customer Identified Resource programme delivering firm, predictable connection at scale.

Outlook drivers

↑ Upgrade triggers

  • Sustained 2 GW-plus build energizes on schedule.
  • Vogtle nuclear and solar lower carbon and firm supply.

↓ Downgrade triggers

  • Supply additions lag the build and tighten availability.
  • Local opposition to large loads.

Evidence behind this rating

The real-world events that test our Tier 2 call for US Southeast (Atlanta): 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Atlanta's data-center build under construction keeps growing ✓ Supports the rating
2025MomentumMateriality: low

The US Southeast is now a top-three North American market by build, with Southern Company adding gas and solar.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: CBRE ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Rating history

June 2026
New ratingNew rating: Tier 2 Strong assigned.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Data provenance and freshness

What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostNot assessedWe hold no evidence for this yet
ConnectionMarket-level (M2)Good for comparing markets, not for a site
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityNot assessedWe hold no substation-level evidence
Not yet good enough for any decision use. The weakest field is cost.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

All 2 data layers are directly measured

Coverage

Substantial

2 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 6 of 6 territories, 100% of customers, regional context only)
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshLBNL Queued Up 2026

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Historical utility-territory delivery performance 114.26 minutes per year (2024)
  • Historical bulk-system performance (event-based)
  • Forward resource adequacy (assessed)
  • Contractual service terms (reported)
  • Typical interconnection wait about 50 months (generation and storage queue, not a load wait)

What is open

  • Designed site resilience
  • Cost evidence (would change the answer)
  • Substation-level capacity evidence

How service and connection are organized

Territories in this market, each with its own filed record: Georgia Power Co, Jackson Electric Member Corp - (GA), Cobb Electric Membership Corp, Sawnee Electric Membership Corporation, GreyStone Power Corporation, Walton Electric Member Corp. Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Schedule: interconnection queues here run about 50 months for generation and storage; a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Availability keeping pace with rapid build.
  • Summer cooling peaks.

Questions to put to the utility

These come from the gaps in our record for US Southeast (Atlanta): the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project case
    Why it is open: no compiled cost band for this market yet.
  2. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/us-southeast/gaps