PGIQ Rating v2 (reliability-adjusted) · as of June 2026
2

🇺🇸 Pacific Northwest

Strong, with known trade-offs, and access is getting harder Reliability flags found
Tier 2 Strong · Composite 69/100, #7 of 79 markets (fundamentals 75 minus a reliability dock) · Outlook Negative · High confidence · how we score

Cheap, clean hydro and a proven hub. It sits just below the top tier because the BPA connection queue is tightening: the fundamentals are excellent, but the path to actually connect is getting harder.

See live grid data →
One market,
four reads
BuildTier 2Siting ratingSellGrade BOfftakePlanRisingLoad pressureMonitorWatchGrid strength
The same market, four decisions. Open any lens to see this market ranked against the rest.
Time to energize · file to power
~55 mo
File a large load today, powered ~2031. Typical range 38 to 72 months, modelled.
End-to-end wait for a large new load, from a complete application being accepted to full firm energization of the nominated MW. Earlier milestones (initial, phased, temporary or conditional energization) are reported separately. A typical case, not a firm quote. · Source: LBNL Queued Up 2026 · Compare markets →
The same market, read four ways

Pacific Northwest is a moderate market to sell power into

Grade B (Moderate)
Offtake score 67/100
Demand 41, build feasibility 55, combined into the score. For a seller: where buyers already pay, how tight supply is, and how feasible new build is here.
Price to beat
A 100 MW load on our standard case pays about $52/MWh delivered here. A competitive supply offer works against that level.
Queue depth (generation and storage)
About 130 GW in the interconnection queue (the line to connect to the grid), typical wait 55 months.
Regulatory momentum
Mixed, stable. BPA is federally administered and outside FERC's Section 206 orders; it has paused its long-term queue under a Grid Access Transformation Project and is weighing readiness requirements and a 13 MW large-load threshold. Transmission is available except in data-centre pockets like central Oregon and the Portland metro, where about 18 GW of BPA's 24 GW load request is data centres.
See it on the Offtake Grade →

Pacific Northwest: little room at system level, rising demand pressure

Little room 33/100
System-level room, not local capacity
Local capacity: not assessed. We have found no operator publication of area or substation capacity for this market, so whether the bus serving a candidate site can take the load is an open question. Absence of a finding here is not evidence that capacity exists.
Two reads for a grid planner: how much room the system as a whole looks to have (Little room), and how hard demand is already pushing (Rising). The first is a market-level estimate from connection ease, forward adequacy and reliability margin. It is not local deliverability. Capacity at a specific substation is not assessed for this market, and a market can look roomy while the bus you want has nothing available. Confirm local capacity with the utility before relying on it.
Generation and storage queue
130 GW requested; about 32.5 GW likely to reach operation after historical withdrawal. The gap is speculative pipeline. This counts generation and storage seeking to connect, not load.
Demand growth
Fast load growth in our read, the pull on your system.
Future firm supply
Future firm supply: tight for a large new load.
Load Pipeline Reality → Where demand is hungry → Connection friction →

Grid Risk Annex BETA

Watch
Needs structuring or mitigants · grid strength 44/100
A cited, dated grid-risk read on Pacific Northwest for a capital provider, the banks and private-credit lenders, infrastructure funds and insurers holding or underwriting a power or data-centre exposure here. Drop it into a credit memo and watch each factor over the life of the exposure.
Read it against your asset. For a load asset (Buy), weight connection access and energization timing. For a generation or offtake asset (Sell), weight offtake demand, curtailment (when a plant is told to stop feeding the grid) and cost realisation. For a grid or transmission asset (Move), weight load-pipeline reality and buildout risk.
Rating and track record
PGIQ Tier 2 Strong, outlook Negative, High confidence. Scored on a public, dated, falsifiable record you can cite in a credit memo.
Delivery reliability
Reliability flags found in the bulk and local outage record we reviewed.
Future firm supply
Future firm supply: tight.
Cost certainty
Recurring cost about $52/MWh (band $40 to $70) for the standard 100 MW case, basis modelled. Excludes connection capital.
Regulatory / stroke-of-pen
Mixed, stable. BPA is federally administered and outside FERC's Section 206 orders; it has paused its long-term queue under a Grid Access Transformation Project and is weighing readiness requirements and a 13 MW large-load threshold. Transmission is available except in data-centre pockets like central Oregon and the Portland metro, where about 18 GW of BPA's 24 GW load request is data centres.
Execution risk
130 GW in the generation and storage queue, about 75% historically withdrawn, the risk the project or load actually energizes on time.
Ongoing monitor
Track this market's rating actions and the Global Power Index as a covenant-style monitor over the life of the exposure.
Monitoring plan
Covenant-style triggers to watch over the life of the exposure: a change in the PGIQ rating or outlook; a dated regulatory move (stroke-of-pen risk); a capacity-auction or cost-band shift; a forward firm-supply adequacy warning; and a rise in queue drop-out or connection friction. Track them on this market page and the Global Power Index, or as Analyst Desk alerts.
Sources: EIA / BPA regional data
This is a directional grid-risk screen, not a credit rating, and not investment, engineering or procurement advice.
The formatted, cited Grid Risk Annex export is an Analyst Desk feature.See the Grid Exposure Monitor →

Regulatory momentum

The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed→ stable

Why: BPA is federally administered and outside FERC's Section 206 orders; it has paused its long-term queue under a Grid Access Transformation Project and is weighing readiness requirements and a 13 MW large-load threshold. Transmission is available except in data-centre pockets like central Oregon and the Portland metro, where about 18 GW of BPA's 24 GW load request is data centres.

What would change the read: The Grid Access Transformation reform reopening a clear queue with firm connection dates for large loads.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%55

Access is tightening: the BPA interconnection queue is lengthening as demand surges.

Availability25%83

High availability: abundant, firm hydro across the Northwest.

Cost25%90

Cheap power: among the lowest US wholesale costs.

Momentum15%70

Proven momentum: long-established hyperscale clusters (central Washington, Oregon).

Carbon5%88

Clean grid (~70 g), hydro-led.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-center build already underway, not just stated intentions.
Seller view: Read these the other way: momentum is your customer pipeline, cost is your revenue ceiling, and access is how hard it is to build and sell here, not only to connect.

Reliability overlay

Reliability adjustment: the five-pillar score of 75 is reduced to 69, a deduction of 6 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.

Historical bulk-system performance: Minor flags found

A dayslong cold snap over Martin Luther King weekend in January 2024 brought the region dangerously close to rolling outages.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

event-based

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 144.44 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 14 utilities, regional context only)

Role not yet declared. We have not recorded whether this is one operator’s filing or an average across several, so read it as context until we do. major event days identified by IEEE 1366 (2.5-beta method). It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

Which utility would serve you?

The market figure above is an average across these territories. Your site sits in one of them, not in the average. Each row below is that utility’s own filed record, which is the evidence a Project Case can actually rest on.

Serving utilitySAIDI min/yrCustomersMajor-event method
Puget Sound Energy Inc (WA)203.01,240,043IEEE 1366
Portland General Electric Co (OR)133.0942,296IEEE 1366
PacifiCorp (OR)107.57638,000IEEE 1366
Idaho Power Co (ID)164.01621,746IEEE 1366
City of Seattle - (WA) (WA)110.8537,470IEEE 1366
PUD No 1 of Snohomish County (WA)181.4386,741IEEE 1366
Avista Corp (WA)112.0270,134IEEE 1366
PUD No 1 of Clark County - (WA) (WA)59.0233,669IEEE 1366
City of Tacoma - (WA) (WA)80.45179,969IEEE 1366
Avista Corp (ID)165.0145,203IEEE 1366
PacifiCorp (WA)101.99138,254IEEE 1366
City of Eugene - (OR) (OR)65.26102,048IEEE 1366
PacifiCorp (ID)129.4489,035IEEE 1366
Idaho Power Co (OR)434.7920,146IEEE 1366

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Tight

The Northwest holds most US hydro capacity, so a dry hydro year combined with an extended cold snap is the region's rolling-blackout risk; BPA has warned of a widening resource gap and took large drought-driven revenue losses.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

assessed · PNW energy-shortage risk in extreme conditions (Spokesman) · Drought cuts PNW hydropower (EIA)

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.
Seller view: Tight forward capacity (firm supply promised for future years) is scarcity that firm generation and storage get paid for; an adequacy flag is a demand signal for new supply, not only a risk to a load.

Supply relief outlook

Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Tightening
Demand pressure
Fast load growth competing for the same capacity.
New supply in motion
About 32.5 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Can new supply arrive
Regulatory momentum mixed, stable.
Future firm supply
Future firm supply: tight.

What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.

Reliability metrics

Delivery reliability (measured)

The average customer loses about 144.44 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 14 utilities, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Interconnection queue

These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Figures below are refreshed quarterly; each is labelled measured or modelled.

Active queue depth

130 GW

Typical wait

55 months

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centers, and the sources, is available through /api/v1/queue/pacific-northwest with a paid key. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

Seller view: A deep queue is both your own time-to-revenue and a moat against competing supply; what matters is the effective supply likely to complete after withdrawal, not the headline queue.

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$40 to $70 per MWh

Midpoint about $52 per MWh

How this band was built

modelled

From 2 public fragments

What builds the $52 midpoint

$40
$10
Federal hydro (BPA priority-firm rate)$40
Transmission$10
Ancillary & other$2
All-in delivered$52 /MWh
How the $52/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The split is our estimate; the total is the midpoint of the compiled band (modelled). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. Anchored by low-cost federal hydro at the BPA priority-firm rate, with little capacity cost; the catch is availability, since firm hydro allocations are largely spoken for and a new load may pay a market premium above the federal rate. Anchored to published figures (Bonneville Power Administration rates).

Where the cost lands

$52
Low $40Midpoint $52High $70
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimised one. The midpoint is our best central read.
What is in the number: Federal hydro power at the Bonneville Power Administration priority-firm rate, plus transmission. Little capacity cost, but firm hydro is increasingly scarce.

The Pacific Northwest is anchored by low-cost federal hydro, giving it one of the cheapest large-load bands in the coverage. The catch is availability: firm hydro allocations are largely spoken for, so a new large load may pay a market premium above the federal rate.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: triangulated from public sources, in US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Bonneville Power Administration rates.

Seller view: This delivered price is the level a competitive supply offer must beat, and the revenue ceiling a merchant plant works against here.

Data provenance and freshness

What we hold for this market, field by field. Each tier below is assigned from the evidence actually held for that field, with provenance. A low tier means we looked and it is thin; it is not a verdict on the market.
cost: M1connection: M1reliability: M2carbon: M2regulatory: M2local capacity: not_assessed
Against a Standardized Project Case, the binding field is cost, connection, reliability. That is what a standardized case would turn on here; a readiness result for your own project depends on your own requirements, siting and utility, which this market-level read does not know.
Read against other uses: Discovery and monitoring: M1 · Market comparison: M1 · Project Case with a carbon requirement: M1 · Conditional site diligence: insufficient.
Depth is not a rating strength, a confidence score or a feasibility conclusion. An aggregate is only ever shown for a named use case, and equals the lowest tier across that use case's required fields. Definitions v1.0. See the full coverage matrix.
How solid the data behind this rating is, on two separate axes plus recency. Source reliability is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source reliability

Limited

1 of 3 data layers measured

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (IEEE 1366 major-event treatment, customer-weighted blend of 14 utilities, regional context only)
Interconnection queuemodelledend-2025 (LBNL 2026)FreshLBNL Queued Up 2026
Realized costmodelled2026FreshBonneville Power Administration rates

Freshness reflects each layer's refresh cadence: reliability annual to three-yearly, capacity-auction and queue yearly, tariffs every year or two. The full cross-market freshness dashboard is at /data-quality.

What this market can and cannot answer yet

No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $40 to $70 per MWh, midpoint $52, basis modelled, against the 100 MW archetype
  • Historical utility-territory delivery performance 144.44 minutes per year (2024)
  • Historical bulk-system performance (event-based)
  • Forward resource adequacy (assessed)
  • Typical interconnection wait about 55 months (generation and storage queue, not a load wait)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience
  • local_capacity evidence

Who would actually serve you

Territories in this market, each with its own filed record: Puget Sound Energy Inc, Portland General Electric Co, PacifiCorp, Idaho Power Co, City of Seattle - (WA), PUD No 1 of Snohomish County, Avista Corp, PUD No 1 of Clark County - (WA). Which one serves a given site depends on where that site is.
Who runs the connection process: not yet compiled for this market. This is wayfinding rather than evidence, and its absence is a gap in our compilation, not a fact about the market.

Credible ranges today

  • Cost $40 to $70 per MWh, midpoint $52 (modelled)
  • Schedule: interconnection queues here run about 55 months for generation and storage; a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • BPA interconnection backlog.
  • Hydrological variability.

Five questions for the utility or system operator

  1. What is the available capacity at the bulk supply point and substation that would serve this site, and what would a 100 MW request do to it?
  2. Is firm service available at 100 MW, and what curtailment rights would you retain over us once we are energised?
  3. What are the milestone dates from a complete application to full firm energisation, and which network upgrades would a 100 MW load trigger?
  4. What is the all-in delivered rate for 100 MW at a 95% load factor, including demand, network and rider charges, under the tariff that would actually apply?
  5. What is your own territory's SAIDI and SAIFI for the industrial class, on which major-event standard, and what redundancy serves the candidate substation?

Documents that would advance the case

  • The area or substation capacity study, and the current queue position list.
  • The applicable large-load tariff or the draft electric service agreement.
  • The interconnection or system impact study, and a specimen connection offer.
  • The current tariff sheet with all riders, and any large-load contract terms.
  • The utility's own reliability filing and the substation single-line diagram.

Outlook drivers

↑ Upgrade triggers

  • BPA expands transmission and clears the queue.
  • Continued hydro-backed clean-power advantage attracts firm tenants.

↓ Downgrade triggers

  • Queue and transmission constraints harden.
  • Dry-year hydro variability.

Key risks

Peer comparison

Trades like
Quebec / Norway (cheap clean hydro)
Ahead
on cost
Behind
ERCOT on access

Evidence behind this rating

The real-world events that test our Tier 2 call for Pacific Northwest: 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Seattle enacts a one-year data-centre siting moratorium ✓ Supports the rating
Jun 2026AccessMateriality: low

Seattle City Council passed a one-year moratorium on siting data centres above 20 MVA (Jun 2026) pending a study of grid, land-use and ratepayer impacts.

Source: Seattle City Light ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.
🔔 Get alerts for Pacific Northwest
Be notified the moment this market's PGIQ Rating, outlook, or a material development changes. Free while we validate demand.

Rating history

Jun 2026
AffirmedSeattle's siting moratorium is consistent with the existing negative outlook; localised, not system-wide. Tier affirmed.
Trigger: Seattle data-centre moratorium (Jun 2026)
June 2026
New ratingNew rating: Tier 2 Strong assigned.
🔒 The full time series behind Pacific Northwest, how its score, recurring cost, and interconnection queue have moved month by month, is part of the Analyst Desk. The rating actions above are always free.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Score history

How Pacific Northwest's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.

Loading history…

How does Pacific Northwest compare to the other 78 markets?

This page is our full read on Pacific Northwest alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.

With your Analyst Desk, compare Pacific Northwest against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.

+ Add to your shortlist Recurring cost, ranked Connection friction, ranked Get the Analyst Desk →