The headline hydro surplus is misleading: Churchill Falls output is largely contracted and exported, the island grid is separate and remote, and Muskrat Falls has been troubled. Deliverable power for a new island load is limited despite the paper surplus.
See live grid data →Limited access: remote, separate island grid; Labrador hydro is contracted/exported.
Constrained deliverable availability despite a large paper surplus.
Cheap power.
Little momentum.
Near-zero operational carbon (~10 g), hydro.
Modelled read: hydro-heavy but small and isolated, with a Muskrat Falls commissioning history.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
modelled
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.
The real-world events that test our Tier 3 call for Newfoundland & Labrador: 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
On 17 Sep 2026, after four days of debate, the House of Assembly voted in favour of a resolution on the Definitive Cooperation and Implementation Agreement for Churchill Falls and Gull Island, the Premier said in a statement that evening. The vote is political approval, not a contract. The agreement signed on 17 Aug 2026 by Newfoundland and Labrador Hydro, Hydro-Québec and Churchill Falls (Labrador) Corporation says it is not legally binding apart from a few procedural sections; the parties aim to sign definitive agreements by 31 Dec 2026, and the agreement ends on 31 Mar 2027 unless extended. Hydro-Québec's Gull Island project page (undated) gives 2034 as the planned commissioning year, so no Gull Island power is planned before then.
Announced 17 Aug 2026 in St. John's by the Prime Minister with the premiers of Newfoundland and Labrador and Quebec. The agreements terminate the 1969 Churchill Falls power contract and replace the December 2024 MOU. Federal financing supports Churchill Falls upgrades, developing Gull Island, co-investment with the Innu of Labrador in a Labrador onshore wind project, and associated transmission. Newfoundland and Labrador retains more of the output than under the 2024 MOU, plus a share of the wind project's output and a transmission portfolio into New York, New England and Ontario markets, which holds only if the non-binding agreement becomes definitive. TWO QUALIFIERS: the agreement is non-binding, with definitive agreements targeted by end-2026, and the Churchill Falls expansion itself (CFX) was removed from it, leaving a feasibility study with no commercial arrangements in place. The near-term physical change for a load siting in this province is the Labrador West transmission line.
The federal government referred the Labrador Trough Clean Power, Critical Minerals and Infrastructure Corridor to the Major Projects Office, which coordinates federal financing and accelerates permitting. Pre-development funding under the First and Last Mile Fund covers a Labrador West transmission expansion to connect western Labrador mining operations to the grid, and planning work for the Kami iron ore project near Wabush. The province separately reports a federal funding commitment to the Labrador West line. Lack of power has been the stated constraint on developing the region, so transmission is the binding item for any large industrial load there.
VOCM reports that CFX, the expansion of the Churchill Falls generating station itself, has been taken out of the new agreement. A feasibility study will be completed but commercial arrangements are not in place. The headline capacity therefore rests on Gull Island, the wind project and existing Churchill Falls capacity rather than on an expansion of the plant. Recorded separately from the announcement because the distinction between a committed project and a study is the whole question for anyone pricing future supply.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Not assessed | We hold no evidence for this yet |
| Connection | Not assessed | We hold no evidence for this yet |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Not assessed | We hold no evidence for this yet |
| Local capacity | Not assessed | We hold no substation-level evidence |
Low
None of the 1 data layers is directly measured; they are triangulated or modelled
Partial
1 of 3 dimensions: reliability, connection, cost
23 Oct 2026
per-layer vintages below
Source strength is low: none of the 1 data layers is directly measured; they are triangulated or modelled. Confidence in the rating (Med) is a separate judgement about the opinion as a whole, set in review; source strength grades only how directly the numbers underneath were measured.
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | modelled | 2025 | Fresh | on the market page |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
The same list as JSON: /api/v1/markets/newfoundland/gaps
How Newfoundland & Labrador's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.
Done with Newfoundland & Labrador? Browse every market or see conditions across every region.
This page is our full read on Newfoundland & Labrador alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.
With your Analyst Desk, compare Newfoundland & Labrador against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.
Since 28 Sep 2026 we serve Canada's national inventory figure for Newfoundland and Labrador: 16 gCO2e/kWh (2024, generation basis, preliminary). Where a live feed is available, the carbon figure in the live conditions on this page can differ: we derive that one hourly from the current fuel mix, so it moves through the day. Carbon intensity does not feed the PGIQ Rating.
Boundary: operational combustion, CO2-equivalent, per kWh delivered to the grid. Main activity producers only. ECCC National Inventory Report, Annex 7 →