Canadian Large-Load Power Cost Monitor · Delivered cost · bands dated to the year (2026) where recorded

What power actually costs a large load in Canada

Every band is the recurring delivered cost for one declared customer: 100 MW at a 95% load factor, high-voltage service. It covers energy, network, capacity, taxes and levies. Connection capital is excluded and reported separately. This is not the wholesale price. 32 of the 84 rated market and regional views carry a band we compare here. Where no public rate exists for a new large load, we don't publish one and say why.

2 Canadian markets currently carry a delivered-cost band that can be compared like for like. 7 do not, and each says why.

The declared case in full
  • Load size: 100 MW maximum contracted demand.
  • Load factor: 95%, about 832.2 GWh in a normal 8760-hour year, at a 0.95 lagging power factor.
  • Voltage: high-voltage service at a disclosed point of delivery, with N-1 at the supplying substation, transfer within 30 minutes.
  • Included: recurring energy, capacity, demand, transmission, distribution, loss, ancillary, reactive-power, tax, levy, carbon and commercial-supply charges, per MWh.
  • Excluded: customer-funded connection, substation and network-upgrade capital. It is a separate one-off cost and is never netted in.

Markets with a comparable band

Bands are comparable with each other, not a quote for your project. Change the load, load factor or voltage and the number changes. US dollars per megawatt hour, recurring.
Market Band, low to high ($/MWh)
one scale, $35 to $210
Where it sits
of 32
How built Lines evidencedConnection wait (free level) TierReport
🇨🇦 Ontario$55 to $100 Midpoint $78Cheapest thirdTriangulated0%High 3–5 yr estimate2 Strong (Tier 2)Report →
🇨🇦 Alberta$60 to $110 Midpoint $80Middle thirdTriangulated0%Severe 5–8 yr (queue capped) measured2 Strong (Tier 2)Report →

No national Canadian figure is published, for the same reason. Figures are in USD so every market compares on one scale. We don't publish a CAD conversion because we don't hold a dated exchange-rate source.

What this means for a siting shortlist

Cheapest bands in this region: Ontario and Alberta. Widest uncertainty: Alberta ($60 to $110). 7 markets in this region have no published band: see why below.

Each market's own band, midpoint included, is free on its report. The full ranking with precise midpoints, every dated change and exports is the Analyst Desk.

Analyst Desk, $600/mo

Find any market's report from the ratings page. Enterprises can license the full feed via the design-partner brief.

Your Analyst Desk access shows each market's precise midpoint in the table above.

Selling or building power instead of buying it? See the same markets ranked by hunger for new supply on the Offtake grade →

Where we don't publish a band, and why

A market is out because its evidence does not yet support a like-for-like comparison, not because it is expensive or cheap.

Evidence still being gathered.

  • 🇨🇦 Quebec Temporary: Quebec's cost review closed Affirmed, no change, on 31 Oct 2026; its band is held out of the comparison until the Régie decides R-4333-2026.
    Details

    What is missing:

    • Awaiting the Regie decision on R-4333-2026: the data-centre rate is not decided, so the band is not comparable today

    Next action: Revisit when the decision is issued.

  • Canada (6): Temporary British Columbia, Manitoba, Newfoundland & Labrador, Saskatchewan, New Brunswick, Nova Scotia. No delivered-cost band has been compiled for these markets yet.
    Details

    What each is missing:

    • no delivered-cost basis is stated
    • no published band
    • no connection-voltage or serving-utility assumption is declared
    • no figure stated in US dollars per MWh

    Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.

Structural means no amount of work here changes it. Temporary means evidence we have not finished gathering.

Of 9 Canadian markets assessed, 2 have a comparable band; 0 are excluded for structural reasons and 7 temporarily.

A market without a band stays in the product with its connection pathway, reliability and pending proceedings. Our API returns insufficient_evidence rather than a substitute figure.

What changed in cost

Dated changes to the delivered-cost record: cost-history events, rating actions on the cost pillar, corrections, withdrawn bands and decisions with a due date.

Recorded changes, newest first

  • Rating action Quebec: Under review. Details in the market report. Record →

Cost history not yet recorded for 2 markets with a band. This is a gap in our coverage, not a sign that costs were stable.

What changed, when, and which market moved are free. The figures before and after each change are on the Analyst Desk. Each market's full history: GET /api/v1/cost-history/{id}

This is a monitor, not an index. Nothing is aggregated across markets. Each row is one market's own band on its own evidence. Calling it an index would imply a composite value and a versioned aggregation method, neither of which exists. The name changes when they do. There is no national Canadian figure here, and there will not be one until a defensible aggregation method exists. Provincial delivered costs are set by different utilities under different regulators; averaging them would produce a number that describes nowhere.

How a market gets in

Membership is derived from the evidence every time this page is built. There is no list of preferred markets: a market whose band is withdrawn leaves the comparison on the next build, without anyone deciding.

All eight must hold

The delivered-cost boundary is complete and stated; the standard archetype applies at this scope; the band is current and not under correction; connection-voltage or serving utility assumptions are declared; nothing is withdrawn; the price is not specific to one customer's negotiated terms; no regulatory decision is pending that would invalidate the comparison; and units, currency and method are comparable.

What is not done

It does not compute a composite. It does not rank markets by anything other than their own published bands. It does not fill a missing bound, infer a mid-point, or convert a currency.

Publication rule

Publish with the eligible set that exists. Do not wait for a target count and do not admit an unsupported market to reach one. An empty eligible set is a publishable result: it says the evidence is not there yet, which is true and useful.

Reading the table

Lines evidenced. A midpoint and a breakdown that adds up to it are not the same as evidence. Where the share is 0%, the band is the compiled result and the component lines apportion its midpoint; they sum exactly because they were built to, which proves nothing about the split. Where it is 100%, every line stands on its own cited, dated source. A verified layer tag means part of that market's delivered cost has also been checked line by line against filed rate documents; it is published beside the band, never inside it. The column sits on this page because that is where someone decides how much to trust a comparison. How a line earns its provenance →

  • Administered: the market has no wholesale market, so the published, regulated tariff is the delivered cost and the band is tight.
  • Triangulated: built from several public sources cross-checked against each other: wholesale energy prices, capacity-auction clearing prices, published network charges and regulator filings.
  • Modelled: estimated from a model and structural indicators where direct published figures are limited.

Basis: shown per row (Administered, Triangulated or Modelled; definitions below). Where it sits places each band in the cheapest, middle or most expensive third of all 32 compared markets, by its midpoint. Connection wait is the free level shown on Connection friction, ranked.

Take the data

The same evidence behind every band, per market.

Cost evidence

Compiled recurring-cost bands and their per-line provenance, per market (realized_cost), and for the whole cohort. The CSV below carries the same bands.

GET /api/v1/ratings/{id}

GET /api/v1/screen?group=canada

Every region's delivered cost →

Screening

Filter the cohort by cost, tier, connection time and group.

GET /api/v1/screen?group=canada

JSON (API) · API & MCP →

This table as JSON

The same rows as the table above, with the figure contract on every band.

GET /api/v1/cost?region=canada

Delivered cost as JSON

Spreadsheet

Every market in the cohort, eligible or not, with its bands, failing conditions and next action.

Eligibility method v1.0 · Full methodology · Delivered cost, ranked

European day-ahead energy prices are published weekly on the price signal page. Energy is one part of a delivered bill, and it moves differently. European wholesale price signal →