Canada's most open market: an energy-only, connect-friendly grid drawing a wave of AI data-centre announcements, with cheap gas for self-supply. What holds it back is higher power cost, a gas-heavy grid, and an interim AESO cap on large-load connections.
See live grid data →$60 to $110 per MWh
Midpoint about $80 per MWh
Alberta runs an energy-only market, so the pool price is only part of the story: transmission and distribution charges add materially on top, and the province is reworking cost allocation for large loads. The delivered cost is above the headline wholesale figure, though still moderate by global standards.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: AESO market and pool price · Alberta electricity rates (Utilities Consumer Advocate).
Severe
This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.
The AESO's interim large-load cap of 1,200 MW is fully allocated (about 970 MW to GLDC and 230 MW to Keephills), leaving roughly 37 data-centre proposals in the queue that must self-generate or wait for grid expansion, where new transmission alone can take about ten years. A durable Phase 2 framework for loads over 75 MW is still being written, so a new grid-only load faces a multi-year wait.
Data-centre share of demand pressure: High. Sources: AESO large-load connection process · Alberta AI data-centre power limits (CBC). The full cross-market connection dataset is available through the Connection Friction Feed.
Open, energy-only market; an interim AESO large-load connection cap is in place while it studies the surge.
Adequate availability (gas plus growing wind), with cheap self-supply gas.
Mid-range cost.
Rising momentum: a wave of AI announcements.
Carbon moderate (~260 g), gas-led but decarbonising.
Tight supply repeatedly pushed the system to the edge in 2024: AESO declared an EEA3 grid emergency on Jan 13, 2024 with a public alert warning of imminent rotating outages, and issued a second grid alert in April 2024 that led to brief rotating outages in the Edmonton area.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
event-based · Alberta Jan/Apr 2024 event report (MSA) · AESO April 2024 grid alert (Global News)
Recent grid alerts reflect thin reserve margins during extreme cold and low imports; market and build response is underway.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
event-based
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.
Why: The interim AESO large-load connection cap is fully subscribed, but a durable Phase 2 framework is expected as the province writes its data-centre rules.
What would change the read: AESO finalising an open, durable Phase 2 large-load connection framework.
For new supply: Abundant gas and a pro-build posture favor new generation; the binding constraint is the interim AESO large-load cap, not supply build.
Beyond the grid: Indigenous consultation and water are live legal risks: Sturgeon Lake Cree Nation is seeking judicial review of Alberta's Water Act licence for the proposed roughly 70 billion dollar Wonder Valley AI campus on drought-stricken Treaty 8 land, saying it received no notice or consultation. CBC Global News
Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.
The real-world events that test our Tier 2 call for Alberta: 2 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
The Data Centre Regulation AR 117/2026 (9 Jun 2026) codifies BYOG, prioritizing large data centres that bring their own generation. AESO's proposed BYOG process closed feedback 13 Jul 2026, with rollout expected Aug 2026 and periodic intakes.
Meta began construction (Jul 2026) of a large AI-optimized data centre in Sturgeon County, northeast of Edmonton, its first in Canada, with the company reporting that it will match the site's electricity to clean and renewable supply. That is a procurement commitment, not a description of the physical grid mix. A build of this scale is concrete large-load momentum on the Alberta grid, and a live test of the interim connection framework.
Phase 1 closed on 12 Jun 2026 with the whole interim data-centre connection limit allocated and contracted; a durable Phase 2 framework awaits Alberta's data-centre regulation.
A temporary cap on new large-load connections while AESO designs a durable framework for a wave of data-centre interest.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
100 MW contracted demand, 95% load factor, HV servicecalculated
A load of this shape consumes 832,200 MWh a year. At the delivered band of $60 to $110/MWh that is $49,932,000 to $91,542,000 a year in recurring power.
Wholesale energy is 69% of the delivered cost here. The other $25/MWh is transmission and distribution, and riders and other charges. See the full build-up.
Typical connection wait is 5 to 8 years (queue capped), at Med-High confidence.
Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Market-level (M2) | Good for comparing markets, not for a site |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Moderate
1 of 3 data layers directly measured; the rest are triangulated or modelled
Full
3 of 3 dimensions: reliability, connection, cost
June 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | historical | 2025 | Fresh | Alberta Jan/Apr 2024 event report (MSA) |
| Connection friction | measured | 2025/26 | Fresh | AESO large-load connection process |
| Realized cost | triangulated | 2026 | Fresh | AESO market and pool price |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
The same list as JSON: /api/v1/markets/alberta/gaps
How Alberta's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.
Done with Alberta? Browse every market or see conditions across every region.
This page is our full read on Alberta alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.
With your Analyst Desk, compare Alberta against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.
Since 28 Sep 2026 we serve Canada's national inventory figure for Alberta: 335 gCO2e/kWh (2024, generation basis, preliminary). Where a live feed is available, the carbon figure in the live conditions on this page can differ: we derive that one hourly from the current fuel mix, so it moves through the day. Carbon intensity does not feed the PGIQ Rating.
Boundary: operational combustion, CO2-equivalent, per kWh delivered to the grid. Main activity producers only. ECCC National Inventory Report, Annex 7 →