Connection friction · as of June 2026

Connection queues and waits: 54 markets, worst first

How hard it is to connect a large new load in each market, and how long it takes. Each market shows a friction level and, where we hold one, the typical wait for a large new load as a year band. Where the only timing evidence is a generation and storage queue, we show the queue and say the load wait is not measured. Every figure is labelled measured, modelled or proxy and cited on the market page. Year-band waits are free here, and each market's own wait in months is free on its rating page; this table with every market's wait in months, and how each queue has moved, are the Analyst Desk, part of the Connection Friction Feed.

● Severe● High● Moderate● Low
File to energized, worst first
Each bar is one market’s end-to-end wait for a large new load as a year band: solid up to the low end, faded across the band. Hover a bar for the stages the wait is made of, in order. Stages overlap in practice and vary by project; the band is a typical case anchored to each operator’s published process, not a quoted date. 25 markets carry a stage build-up and are drawn here; the other 29 on this page are graded but not timed.
1y2y3y4y5y6y7y8y9y10yGermany South (Frankfurt/Munich) · 7 to 10 years · stages: Application & queue position → Grid study & connection offer → Network reinforcement / transmission build → Construction & energizationGermany South (Frankfurt/Munich) · 7 to 10 years · stages: Application & queue position → Grid study & connection offer → Network reinforcement / transmission build → Construction & energization🇩🇪 Germany South7 to 10 yearsJapan East (Tokyo, 50Hz) · 5 to 10 years · stages: Application & capacity study → Grid connection study & offer → Substation & network reinforcement → Construction & energizationJapan East (Tokyo, 50Hz) · 5 to 10 years · stages: Application & capacity study → Grid connection study & offer → Substation & network reinforcement → Construction & energization🇯🇵 Japan East5 to 10 yearsAlberta · 5 to 8 years · stages: Application & queue entry → System study & connection offer → Transmission build → Construction & energizationAlberta · 5 to 8 years · stages: Application & queue entry → System study & connection offer → Transmission build → Construction & energization🇨🇦 Alberta5 to 8 yearsGermany North (Hamburg) · 5 to 8 years · stages: Application & queue position → Grid study & connection offer → Network reinforcement / transmission build → Construction & energizationGermany North (Hamburg) · 5 to 8 years · stages: Application & queue position → Grid study & connection offer → Network reinforcement / transmission build → Construction & energization🇩🇪 Germany North5 to 8 yearsJapan West (Osaka, 60Hz) · 4 to 8 years · stages: Application & capacity study → Grid connection study & offer → Substation & network reinforcement → Construction & energizationJapan West (Osaka, 60Hz) · 4 to 8 years · stages: Application & capacity study → Grid connection study & offer → Substation & network reinforcement → Construction & energization🇯🇵 Japan West4 to 8 yearsQuebec · 4 to 6 years · stages: Ministerial authorization → Grid study & connection offer → Network reinforcement → Construction & energizationQuebec · 4 to 6 years · stages: Ministerial authorization → Grid study & connection offer → Network reinforcement → Construction & energization🇨🇦 Quebec4 to 6 yearsOntario · 3 to 5 years · stages: Application & IESO system impact study → Transmitter connection impact assessment → Line upgrades & substation → Construction & energizationOntario · 3 to 5 years · stages: Application & IESO system impact study → Transmitter connection impact assessment → Line upgrades & substation → Construction & energization🇨🇦 Ontario3 to 5 yearsSouth Africa · 3 to 5 years · stages: Application & Eskom cost estimate / budget quote → Grid connection agreement → Network build → Construction & energizationSouth Africa · 3 to 5 years · stages: Application & Eskom cost estimate / budget quote → Grid connection agreement → Network build → Construction & energization🇿🇦 South Africa3 to 5 yearsSouth Korea · 3 to 5 years · stages: Supply confirmation (KEPCO) → 154 kV tie-in study & agreement → Substation & line build → Construction & energizationSouth Korea · 3 to 5 years · stages: Supply confirmation (KEPCO) → 154 kV tie-in study & agreement → Substation & line build → Construction & energization🇰🇷 South Korea3 to 5 yearsTaiwan · 3 to 5 years · stages: Application & Taipower review → Grid study & connection offer → Substation & network reinforcement (161 kV) → Construction & energizationTaiwan · 3 to 5 years · stages: Application & Taipower review → Grid study & connection offer → Substation & network reinforcement (161 kV) → Construction & energization🇹🇼 Taiwan3 to 5 yearsFrance · 3 to 4 years · stages: Application & site designation → Grid study & connection offer → Agreement & works planning → Construction & energizationFrance · 3 to 4 years · stages: Application & site designation → Grid study & connection offer → Agreement & works planning → Construction & energization🇫🇷 France3 to 4 yearsIndia · 2 to 4 years · stages: Application & DISCOM approval → Grid study & connection agreement → Network augmentation → Construction & energizationIndia · 2 to 4 years · stages: Application & DISCOM approval → Grid study & connection agreement → Network augmentation → Construction & energization🇮🇳 India2 to 4 yearsPhilippines · 2 to 4 years · stages: Application & NGCP / Meralco study → Substation & feeder build → Connection agreement → Construction & energizationPhilippines · 2 to 4 years · stages: Application & NGCP / Meralco study → Substation & feeder build → Connection agreement → Construction & energization🇵🇭 Philippines2 to 4 yearsSweden South (Malmo, SE4) · 2 to 4 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energizationSweden South (Malmo, SE4) · 2 to 4 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energization🇸🇪 Sweden South2 to 4 yearsThailand · 2 to 4 years · stages: Application & EGAT / PEA study → Grid connection agreement → Network reinforcement → Construction & energizationThailand · 2 to 4 years · stages: Application & EGAT / PEA study → Grid connection agreement → Network reinforcement → Construction & energization🇹🇭 Thailand2 to 4 yearsHong Kong · 2 to 3 years · stages: Application & CLP / HK Electric study → Supply agreement → Network works → Construction & energizationHong Kong · 2 to 3 years · stages: Application & CLP / HK Electric study → Supply agreement → Network works → Construction & energization🇭🇰 Hong Kong2 to 3 yearsFinland · 1 to 3 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energizationFinland · 1 to 3 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energization🇫🇮 Finland1 to 3 yearsMalaysia · 1 to 3 years · stages: Green Lane application → Grid study & connection offer → Network works → Construction & energizationMalaysia · 1 to 3 years · stages: Green Lane application → Grid study & connection offer → Network works → Construction & energization🇲🇾 Malaysia1 to 3 yearsNorway · 1 to 3 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energizationNorway · 1 to 3 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energization🇳🇴 Norway1 to 3 yearsSaudi Arabia · 1 to 3 years · stages: Application & SERA / SEC approval → Grid study & connection offer → Network works → Construction & energizationSaudi Arabia · 1 to 3 years · stages: Application & SERA / SEC approval → Grid study & connection offer → Network works → Construction & energization🇸🇦 Saudi Arabia1 to 3 yearsSweden North (Lulea, SE1/SE2) · 1 to 3 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energizationSweden North (Lulea, SE1/SE2) · 1 to 3 years · stages: Application & site → Grid study & connection offer → Agreement & works planning → Construction & energization🇸🇪 Sweden North1 to 3 yearsUnited Arab Emirates · 1 to 3 years · stages: Application & approval → Grid study & connection offer → Network works → Construction & energizationUnited Arab Emirates · 1 to 3 years · stages: Application & approval → Grid study & connection offer → Network works → Construction & energization🇦🇪 United Arab Emirates1 to 3 yearsERCOT Central (Houston & DFW) · 1 to 2 years · stages: Application & screening → Interconnection study & agreement → Construction & energizationERCOT Central (Houston & DFW) · 1 to 2 years · stages: Application & screening → Interconnection study & agreement → Construction & energization🇺🇸 ERCOT Central1 to 2 yearsERCOT West (West Texas & Panhandle) · 1 to 2 years · stages: Application & screening → Interconnection study & agreement → Construction & energizationERCOT West (West Texas & Panhandle) · 1 to 2 years · stages: Application & screening → Interconnection study & agreement → Construction & energization🇺🇸 ERCOT West1 to 2 yearsIndonesia · 1 to 2 years · stages: Application & PLN study → Connection agreement → Network works → Construction & energizationIndonesia · 1 to 2 years · stages: Application & PLN study → Connection agreement → Network works → Construction & energization🇮🇩 Indonesia1 to 2 years
MarketRegionConnection frictionDetailBasis
🇨🇦 AlbertaCanadaSevere5 to 8 years (queue capped) ↗measured
🇩🇪 Germany South (Frankfurt/Munich)EuropeSevere7 to 10 years ↗measured
🇺🇸 ISO New EnglandUnited StatesSevere3 to 7 years (modelled from the generation queue) ↗modelled
🇯🇵 Japan East (Tokyo, 50Hz)AsiaSevere5 to 10 years ↗measured
🇳🇱 NetherlandsEuropeSevere38 GW load queue; wait 6 to 10 years ↗measured
🇺🇸 Northern Virginia (PJM)United StatesSevere3 to 9 years (modelled from the generation queue) ↗modelled
🇨🇦 QuebecCanadaSevere4 to 6 years (authorization-gated) ↗estimate
🇹🇼 TaiwanAsiaSevere3 to 5 years ↗estimate
🇺🇸 CAISO (California)United StatesHigh2 to 8 years (modelled from the generation queue) ↗modelled
🇩🇪 Germany North (Hamburg)EuropeHigh5 to 8 years ↗estimate
🇬🇧 Great BritainEuropeHigh2 to 6 years (modelled from the generation queue) ↗modelled
🇮🇪 Ireland (Dublin)EuropeHigh3 to 5 years (modelled from the generation queue) ↗modelled
🇯🇵 Japan West (Osaka, 60Hz)AsiaHigh4 to 8 years ↗estimate
🇺🇸 MISO (Midwest)United StatesHigh2 to 7 years (modelled from the generation queue) ↗modelled
🇺🇸 NYISO (New York)United StatesHigh3 to 7 years (modelled from the generation queue) ↗modelled
🇨🇦 OntarioCanadaHigh3 to 5 years ↗estimate
🇺🇸 SPP (Southwest Power Pool)United StatesHigh2 to 7 years (modelled from the generation queue) ↗modelled
🇿🇦 South AfricaAfricaHigh3 to 5 years ↗estimate
🇰🇷 South KoreaAsiaHigh3 to 5 years ↗estimate
🇪🇸 SpainEuropeHighpermit-gated ↗estimate
🇺🇸 US Southeast (Atlanta)United StatesHigh2 to 6 years (modelled from the generation queue) ↗modelled
🇺🇸 Desert Southwest (Phoenix)United StatesModerate1 to 5 years (modelled from the generation queue) ↗modelled
🇫🇷 FranceEuropeModerate3 to 4 years (fast track) ↗measured
🇭🇰 Hong KongAsiaModerate2 to 3 years ↗estimate
🇮🇳 IndiaAsiaModerate2 to 4 years ↗estimate
🇮🇩 IndonesiaAsiaModerate1 to 2 years (Batam) ↗estimate
🇲🇾 MalaysiaAsiaModerate1 to 3 years (Green Lane) ↗estimate
🇺🇸 Pacific NorthwestUnited StatesModerate1 to 5 years (modelled from the generation queue) ↗modelled
🇵🇭 PhilippinesAsiaModerate2 to 4 years ↗estimate
🇸🇪 Sweden South (Malmo, SE4)EuropeModerate2 to 4 years ↗estimate
🇹🇭 ThailandAsiaModerate2 to 4 years ↗estimate
🇺🇸 ERCOT Central (Houston & DFW)United StatesLow1 to 2 years ↗estimate
🇺🇸 ERCOT West (West Texas & Panhandle)United StatesLow1 to 2 years ↗estimate
🇫🇮 FinlandEuropeLow1 to 3 years ↗estimate
🇳🇴 NorwayEuropeLow1 to 3 years ↗estimate
🇸🇦 Saudi ArabiaMiddle EastLow1 to 3 years ↗estimate
🇸🇪 Sweden North (Lulea, SE1/SE2)EuropeLow1 to 3 years ↗estimate
🇦🇪 United Arab EmiratesMiddle EastLow1 to 3 years ↗estimate
🇦🇺 Australia NSW (Sydney)OceaniaLevel not ratedabout 2 years (NEM-wide target; Sydney West constrained) ↗estimate
🇦🇺 Australia Queensland (Brisbane)OceaniaLevel not ratedabout 2 years (NEM-wide target) ↗estimate
🇦🇺 Australia Victoria (Melbourne)OceaniaLevel not ratedabout 2 years (NEM-wide target) ↗estimate
🇧🇷 Brazil (Sao Paulo)Latin AmericaLevel not rated1 to 5 years (seasonal access rounds) ↗estimate
🇨🇦 British ColumbiaCanadaLevel not rated3 to 5 years (allocation-gated) ↗estimate
🇨🇱 ChileLatin AmericaLevel not rated3 to 5 years (to first circuit) ↗estimate
🇨🇿 Czech RepublicEuropeLevel not rated5 to 15 years (from pre-contract; substation-dependent) ↗measured
🇩🇰 DenmarkEuropeLevel not rated5 to 10 years (very large connections) ↗measured
🇪🇪 EstoniaEuropeLevel not rated1 to 3 years (construction, from first fee payment) ↗measured
🇮🇹 Italy (Milan, North)EuropeLevel not rated6 to 8 years (request to full operation) ↗estimate
🇨🇦 ManitobaCanadaLevel not rated2 to 5 years (supply-gated) ↗estimate
🇨🇦 New BrunswickCanadaLevel not rated2 to 4 years (capacity-gated) ↗estimate
🇳🇿 New ZealandOceaniaLevel not rated1 to 3 years (simple to large; large complex can exceed 3) ↗measured
🇵🇹 PortugalEuropeLevel not rated2 to 5 years ↗estimate
🇨🇦 SaskatchewanCanadaLevel not rated1 to 2 years (transmission; new data centres self-supply) ↗estimate
🇨🇭 SwitzerlandEuropeLevel not rated3 to 10 years (from application) ↗measured
Queue context: These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.
Each year band is derived from the market's month range on its rating page, by one rule: the low end rounded down to whole years, the high end rounded up. It is a typical case for a large new load, not a firm quote, and partial or temporary supply can sometimes start earlier. A generation and storage queue measures how congested the grid is, not how long a large load waits. Multi-year waits are real in saturated grids: in Northern Virginia, Dominion has said large data centres over 100 MW can wait up to seven years, and parts of the Netherlands and Ireland are quoted at similar or longer horizons.

◆ Your Analyst Desk access shows the precise typical wait in months for every market above, in place of the free year bands.

🔒 Precise waits in months are the Analyst Desk

Everything above is free, and each market's full connection story stays free on its rating page. The Desk sharpens this table: the precise typical wait in months instead of a year band, how each queue has moved, and alerts when one changes.

Get the Analyst Desk $600/mo

Each market's friction level and wait band stay free on its rating page. Withdrawal rates and data-centre share are the enterprise Connection Friction Feed; this free view is a current snapshot. Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly.