What a large load pays for power, market by market
Every band is the recurring delivered cost for one declared customer: 100 MW at a 95% load factor, high-voltage service. It covers energy, network, capacity, taxes and levies. Connection capital is excluded and reported separately. This is not the wholesale price. 32 of the 84 rated market and regional views carry a band we compare here. Where no public rate exists for a new large load, we don't publish one and say why.
The declared case in full
- Load size: 100 MW maximum contracted demand.
- Load factor: 95%, about 832.2 GWh in a normal 8760-hour year, at a 0.95 lagging power factor.
- Voltage: high-voltage service at a disclosed point of delivery, with N-1 at the supplying substation, transfer within 30 minutes.
- Included: recurring energy, capacity, demand, transmission, distribution, loss, ancillary, reactive-power, tax, levy, carbon and commercial-supply charges, per MWh.
- Excluded: customer-funded connection, substation and network-upgrade capital. It is a separate one-off cost and is never netted in.
Markets with a comparable band
| Market | Band, low to high ($/MWh) one scale, $35 to $210 |
Where it sits of 32 | How built | Lines evidenced | Connection wait (free level) | Tier | Report |
|---|---|---|---|---|---|---|---|
| ๐บ๐ธ ERCOT Central (Houston & DFW) | $55 to $95 Midpoint $••• | Cheapest third | Triangulated | 0% verified layer | Low 1โ2 yr estimate | 2 Strong (Tier 2) | Report → |
| ๐บ๐ธ ERCOT West (West Texas & Panhandle) | $42 to $80 Midpoint $••• | Cheapest third | Triangulated | 0% verified layer | Low 1โ2 yr estimate | 2 Strong (Tier 2) | Report → |
| ๐ซ๐ฎ Finland | $42 to $78 Midpoint $••• | Cheapest third | Triangulated | 0% | Low 1โ3 yr estimate | 1 Prime (Tier 1) | Report → |
| ๐ฎ๐ฉ Indonesia | $62 to $90 Midpoint $••• | Cheapest third | Administered | no breakdown | Moderate 1โ2 yr (Batam) estimate | 3 Workable (Tier 3) | Report → |
| ๐บ๐ธ MISO (Midwest) | $48 to $78 Midpoint $••• | Cheapest third | Triangulated | 0% | High 2โ7 yr (modelled from the generation queue) modelled | 3 Workable (Tier 3) | Report → |
| ๐ณ๐ด Norway | $40 to $75 Midpoint $••• | Cheapest third | Modelled | 0% | Low 1โ3 yr estimate | 1 Prime (Tier 1) | Report → |
| ๐จ๐ฆ Ontario | $55 to $100 Midpoint $••• | Cheapest third | Triangulated | 0% | High 3โ5 yr estimate | 2 Strong (Tier 2) | Report → |
| ๐บ๐ธ SPP (Southwest Power Pool) | $42 to $68 Midpoint $••• | Cheapest third | Triangulated | 0% | High 2โ7 yr (modelled from the generation queue) modelled | 2 Strong (Tier 2) | Report → |
| ๐ธ๐ฆ Saudi Arabia | $50 to $58 Midpoint $••• | Cheapest third | Administered | no breakdown | Low 1โ3 yr estimate | 2 Strong (Tier 2) | Report → |
| ๐ธ๐ช Sweden North (Lulea, SE1/SE2) | $35 to $65 Midpoint $••• | Cheapest third | Modelled | 0% | Low 1โ3 yr estimate | 1 Prime (Tier 1) | Report → |
| ๐ฆ๐ช United Arab Emirates | $50 to $85 Midpoint $••• | Cheapest third | Modelled | no breakdown | Low 1โ3 yr estimate | 1 Prime (Tier 1) | Report → |
| ๐จ๐ฆ Alberta | $60 to $110 Midpoint $••• | Middle third | Triangulated | 0% | Severe 5โ8 yr (queue capped) measured | 2 Strong (Tier 2) | Report → |
| ๐ซ๐ท France | $88 to $122 Midpoint $••• | Middle third | Triangulated | 0% | Moderate 3โ4 yr (fast track) measured | 2 Strong (Tier 2) | Report → |
| ๐ฉ๐ช Germany North (Hamburg) | $100 to $145 Midpoint $••• | Middle third | Triangulated | 0% | High 5โ8 yr estimate | 2 Strong (Tier 2) | Report → |
| ๐ฎ๐ณ India | $75 to $125 Midpoint $••• | Middle third | Modelled | 0% | Moderate 2โ4 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐ฒ๐พ Malaysia | $90 to $115 Midpoint $••• | Middle third | Triangulated | 0% | Moderate 1โ3 yr (Green Lane) estimate | 3 Workable (Tier 3) | Report → |
| ๐บ๐ธ NYISO (New York) | $70 to $140 Midpoint $••• | Middle third | Triangulated | 0% | High 3โ7 yr (modelled from the generation queue) modelled | 4 Constrained (Tier 4) | Report → |
| ๐บ๐ธ Northern Virginia (PJM) | $82.63 (a point from the posted tariff) | Middle third | Administered | 100% | Severe 3โ9 yr (modelled from the generation queue) modelled | 3 Workable (Tier 3) | Report → |
| ๐ฟ๐ฆ South Africa | $92 to $128 Midpoint $••• | Middle third | Administered | no breakdown | High 3โ5 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐ช๐ธ Spain | $82 to $118 Midpoint $••• | Middle third | Triangulated | 0% | High permit-gated estimate | 2 Strong (Tier 2) | Report → |
| ๐ธ๐ช Sweden South (Malmo, SE4) | $70 to $115 Midpoint $••• | Middle third | Modelled | 0% | Moderate 2โ4 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐น๐ญ Thailand | $90 to $125 Midpoint $••• | Middle third | Administered | no breakdown | Moderate 2โ4 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐ฉ๐ช Germany South (Frankfurt/Munich) | $108 to $158 Midpoint $••• | Most expensive third | Triangulated | 0% | Severe 7โ10 yr measured | 4 Constrained (Tier 4) | Report → |
| ๐ฌ๐ง Great Britain | $118 to $168 Midpoint $••• | Most expensive third | Triangulated | 0% | High 2โ6 yr (modelled from the generation queue) modelled | 4 Constrained (Tier 4) | Report → |
| ๐ญ๐ฐ Hong Kong | $170 to $210 Midpoint $••• | Most expensive third | Administered | no breakdown | Moderate 2โ3 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐ฎ๐ช Ireland (Dublin) | $130 to $180 Midpoint $••• | Most expensive third | Modelled | 0% verified layer | High 3โ5 yr (modelled from the generation queue) modelled | 5 Largely closed (Tier 5) | Report → |
| ๐ฏ๐ต Japan East (Tokyo, 50Hz) | $135 to $190 Midpoint $••• | Most expensive third | Modelled | 0% | Severe 5โ10 yr measured | 4 Constrained (Tier 4) | Report → |
| ๐ฏ๐ต Japan West (Osaka, 60Hz) | $125 to $175 Midpoint $••• | Most expensive third | Modelled | 0% | High 4โ8 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐ณ๐ฑ Netherlands | $108 to $150 Midpoint $••• | Most expensive third | Triangulated | 0% | Severe 6โ10 yr measured | 4 Constrained (Tier 4) | Report → |
| ๐ต๐ญ Philippines | $140 to $210 Midpoint $••• | Most expensive third | Triangulated | 0% | Moderate 2โ4 yr estimate | 4 Constrained (Tier 4) | Report → |
| ๐ฐ๐ท South Korea | $120 to $150 Midpoint $••• | Most expensive third | Administered | no breakdown | High 3โ5 yr estimate | 3 Workable (Tier 3) | Report → |
| ๐น๐ผ Taiwan | $128 to $140 Midpoint $••• | Most expensive third | Administered | no breakdown | Severe 3โ5 yr estimate | 4 Constrained (Tier 4) | Report → |
No U.S.-wide average is published. Markets differ by utility and regulator, and an average would describe nowhere.
No national Canadian figure is published, for the same reason. Figures are in USD so every market compares on one scale. We don't publish a CAD conversion because we don't hold a dated exchange-rate source.
What this means for a siting shortlist
Cheapest bands in this view: Sweden North, Saudi Arabia and SPP. Widest uncertainty: Philippines ($140 to $210). 47 markets in this view have no published band: see why below.
Cheapest bands in this region: Sweden North, Norway and Finland. Widest uncertainty: Ireland ($130 to $180). 18 markets in this region have no published band: see why below.
Cheapest bands in this region: SPP, ERCOT West and MISO. Widest uncertainty: NYISO ($70 to $140). 5 markets in this region have no published band: see why below.
Cheapest bands in this region: Ontario and Alberta. Widest uncertainty: Alberta ($60 to $110). 7 markets in this region have no published band: see why below.
Cheapest bands in this region: Indonesia, India and Malaysia. Widest uncertainty: Philippines ($140 to $210). 1 market in this region has no published band: see why below.
Cheapest bands in this region: Saudi Arabia and United Arab Emirates. Widest uncertainty: United Arab Emirates ($50 to $85). 6 markets in this region have no published band: see why below.
Cheapest bands in this region: South Africa. Widest uncertainty: South Africa ($92 to $128). Every market in this region carries a published band.
Each market's own band, midpoint included, is free on its report. The full ranking with precise midpoints, every dated change and exports is the Analyst Desk.
Analyst Desk, $600/moFind any market's report from the ratings page. Enterprises can license the full feed via the design-partner brief.
Your Analyst Desk access shows each market's precise midpoint in the table above.
Selling or building power instead of buying it? See the same markets ranked by hunger for new supply on the Offtake grade →
Where we don't publish a band, and why
A market is out because its evidence does not yet support a like-for-like comparison, not because it is expensive or cheap.
No public rate a new large load can take.
- ๐บ๐ธ Pacific Northwest Structural: Federal hydro allocations are largely committed and a new customer would pay a market premium above the federal rate.
Details
From the record: The published band was derived from the Bonneville Power Administration priority-firm rate, which a new large load cannot obtain: federal hydro allocations are largely committed and a new customer would pay a market premium above the federal rate. A tariff the standard archetype cannot purchase may not set a delivered-cost band.
Band withdrawn: 20 August 2026.
What is missing:
- no delivered-cost basis is stated
- no published band
- no connection-voltage or serving-utility assumption is declared
- Cost here is set by a bilateral arrangement rather than a posted rate, so no standardized band can represent it.
- no figure stated in US dollars per MWh
Next action: Obtain evidence for a service the archetype could actually contract. The existing figures cannot be repaired by recalculation.
- ๐บ๐ธ US Southeast (Atlanta) Structural: Georgia closed its standard schedules to new large loads on 1 February 2025 and requires an individually negotiated contract instead.
Details
From the record: The band was anchored on a regulated bundled industrial tariff that a new 100 MW load cannot take: Georgia closed its standard schedules to new large loads on 1 February 2025 and requires an individually negotiated contract instead. The band's primary source was also EIA industrial monthly pricing, which may serve only as a lagged validation layer and not as the headline large-load price.
Band withdrawn: 20 August 2026.
What is missing:
- no delivered-cost basis is stated
- no published band
- no connection-voltage or serving-utility assumption is declared
- no figure stated in US dollars per MWh
Next action: Filed or executed contract terms, or a published contract-based rate. Searching for a tariff schedule will not close it.
A rate decision is pending.
- ๐บ๐ธ Desert Southwest (Phoenix) Structural: The Arizona Corporation Commission's decision is due by 31 December 2026.
Details
APS rate case seeking roughly +45% for extra-large load customers, alongside changes to the Extra High Load Factor rate that applies to data centres.
If approved, the effective cost for a new large load in APS territory rises materially. This is a dated, cited risk to a future band, and it is deliberately reported here rather than inside one.
From the record: The published band blended an effective regulated rate with APS's PROPOSED extra-large-load class of roughly +45%, which the Arizona Corporation Commission has not decided: the rate-case hearing closed 7 July 2026 and the Commission's vote is due by 31 December 2026. A pending proceeding may not set a current delivered cost. The band's primary source was also an ACC large-load workshop rather than a tariff.
Band withdrawn: 20 August 2026.
What is missing:
- no delivered-cost basis is stated
- no published band
- no connection-voltage or serving-utility assumption is declared
- no figure stated in US dollars per MWh
Next action: Obtain evidence for a service the archetype could actually contract. The existing figures cannot be repaired by recalculation.
Source: Arizona Corporation Commission, What's Next in the APS Rate Case (10 July 2026)
Cost is set by many utilities.
- ๐บ๐ธ ISO New England Structural: The regional transmission layer is uniform and verifiable, but local transmission, distribution and retail demand charges are set by 32 serving utilities across six states and five regulators.
Details
From the record: A single delivered-cost estimate cannot be defended at ISO-NE-wide scope. The regional transmission layer is uniform and verifiable, but local transmission, distribution and retail demand charges are set by 32 serving utilities across six states and five regulators. The superseded values are recorded in the correction record, not here.
Band withdrawn: 24 August 2026.
What is missing:
- no delivered-cost basis is stated
- Cost availability: depends on the state or province. A comparable band needs a standard published cost.
- no published band
- no connection-voltage or serving-utility assumption is declared
- no figure stated in US dollars per MWh
Next action: Narrow to one serving utility and interconnection point, then apply that utility's local transmission and distribution tariff. No region-wide document will close it, because no regional body sets these charges.
Evidence still being gathered.
- ๐บ๐ธ CAISO (California) Temporary: CAISO's cost read is under review, so its band is withheld until the review closes.
Details
Under review since: Jul 2026.
What is missing:
- Cost availability: cost still being decided. A comparable band needs a standard published cost.
Next action: Resolve the methodology from first principles, then populate. Not a data-collection problem.
- ๐จ๐ฆ Quebec Temporary: Quebec's cost review closed Affirmed, no change, on 31 Oct 2026; its band is held out of the comparison until the Rรฉgie decides R-4333-2026.
Details
What is missing:
- Awaiting the Regie decision on R-4333-2026: the data-centre rate is not decided, so the band is not comparable today
Next action: Revisit when the decision is issued.
- Europe (18): Portugal, Austria, Denmark, Belgium, Switzerland, Czech Republic, Romania, Lithuania, Italy, Poland, Latvia, Slovakia, Greece, Hungary, Bulgaria, Estonia, Croatia, Slovenia. No delivered-cost band has been compiled for these markets yet.
Details
Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.
- Canada (6): Temporary British Columbia, Manitoba, Newfoundland & Labrador, Saskatchewan, New Brunswick, Nova Scotia. No delivered-cost band has been compiled for these markets yet.
Details
What each is missing:
- no delivered-cost basis is stated
- no published band
- no connection-voltage or serving-utility assumption is declared
- no figure stated in US dollars per MWh
Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.
- Asia (1): Singapore. No delivered-cost band has been compiled for these markets yet.
Details
Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.
- Middle East (6): Qatar, Egypt, Kuwait, Turkey, Israel, Iraq. No delivered-cost band has been compiled for these markets yet.
Details
Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.
- Latin America (6): Brazil, Chile, Uruguay, Colombia, Argentina, Costa Rica. No delivered-cost band has been compiled for these markets yet.
Details
Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.
- Oceania (4): New Zealand, Australia NSW, Australia Victoria, Australia Queensland. No delivered-cost band has been compiled for these markets yet.
Details
Next action: Compile a delivered-cost band for the declared 100 MW case from sources a new large load could contract.
Structural means no amount of work here changes it. Temporary means evidence we have not finished gathering.
Of 12 U.S. markets assessed, 6 have a comparable band and 1 is an aggregate view of them (ERCOT (Texas)); 4 are excluded for structural reasons and 1 temporarily.
Of 9 Canadian markets assessed, 2 have a comparable band; 0 are excluded for structural reasons and 7 temporarily.
A market without a band stays in the product with its connection pathway, reliability and pending proceedings. Our API returns insufficient_evidence rather than a substitute figure.
What changed in cost
Dated changes to the delivered-cost record: cost-history events, rating actions on the cost pillar, corrections, withdrawn bands and decisions with a due date.
Decisions due
- Decision due Desert Southwest: Arizona Corporation Commission: APS rate case seeking roughly +45% for extra-large load customers, alongside changes to the Extra High Load Factor rate that applies to data centres. Source →
Recorded changes, newest first
- Rating action ISO New England: Affirmed: Affirmed, no change, 31 Oct 2026. Record →
- Cost history CAISO: A method change: the arithmetic moved, not the market. History (JSON) →
- Rating action United Arab Emirates: Affirmed: Affirmed, no change, 23 Oct 2026. Record →
- Rating action ISO New England: Under review: Review extended 2026-10-23. Record →
- Rating action ISO New England: Downgrade: Tier 3 Workable to Tier 4 Constrained under the published tier rules: a PGIQ Rating of 46 sits in the Tier 4 band. Record →
- Cost history SPP, Northern Virginia, NYISO, ERCOT West, ERCOT Central: A method change: the arithmetic moved, not the market; 2 other value changes held for an editor to classify.
- Cost history MISO: A method change: the arithmetic moved, not the market; 3 other value changes held for an editor to classify. History (JSON) →
- Correction ISO New England: ISO New England region-wide delivered-cost estimate withdrawn. Record →
- Cost history US Southeast: What can be published changed (a band withdrawn or restored, a breakdown withheld, or a review opened or closed). History (JSON) →
- Correction Northern Virginia: Northern Virginia recurring cost estimate corrected. Record →
- Band withdrawn US Southeast: The band was anchored on a regulated bundled industrial tariff that a new 100 MW load cannot take. Record →
- Band withdrawn Pacific Northwest: The published band was derived from the Bonneville Power Administration priority-firm rate, which a new large load cannot obtain. Record →
- Band withdrawn Desert Southwest: The published band blended an effective regulated rate with APS's proposed extra-large-load class of roughly +45%, which the Arizona Corporation Commission has not decided. Record →
- Rating action United Arab Emirates: Under review. Details in the market report. Record →
- Rating action Quebec: Under review. Details in the market report. Record →
- Rating action Northern Virginia: Under review: A statewide $0.011/kWh consumption tax stacks on capacity prices at the cap and DOE-ordered curtailment exposure; direction of the Cost pillar is clearly negative, tier impact under assessment. Record →
- Rating action CAISO: Under review. Details in the market report. Record →
No dated cost change is recorded for this region yet.
Cost history has been recorded since 21 August 2026 for 6 markets with a band, 28 changes in all. None of them is classified as a market move. Cost history not yet recorded for 26 markets with a band. This is a gap in our coverage, not a sign that costs were stable.
Cost history not yet recorded for 11 markets with a band. This is a gap in our coverage, not a sign that costs were stable.
Cost history has been recorded since 21 August 2026 for 6 U.S. markets with a band, 28 changes in all. None of them is classified as a market move.
Cost history not yet recorded for 2 markets with a band. This is a gap in our coverage, not a sign that costs were stable.
Cost history not yet recorded for 10 markets with a band. This is a gap in our coverage, not a sign that costs were stable.
Cost history not yet recorded for 2 markets with a band. This is a gap in our coverage, not a sign that costs were stable.
Cost history not yet recorded for 1 market with a band. This is a gap in our coverage, not a sign that costs were stable.
What changed, when, and which market moved are free. The figures before and after each change are on the Analyst Desk. Each market's full history: GET /api/v1/cost-history/{id}
Reading the table
Lines evidenced. A midpoint and a breakdown that adds up to it are not the same as evidence. Where the share is 0%, the band is the compiled result and the component lines apportion its midpoint; they sum exactly because they were built to, which proves nothing about the split. Where it is 100%, every line stands on its own cited, dated source. A verified layer tag means part of that market's delivered cost has also been checked line by line against filed rate documents; it is published beside the band, never inside it. The column sits on this page because that is where someone decides how much to trust a comparison. How a line earns its provenance →
- Administered: the market has no wholesale market, so the published, regulated tariff is the delivered cost and the band is tight.
- Triangulated: built from several public sources cross-checked against each other: wholesale energy prices, capacity-auction clearing prices, published network charges and regulator filings.
- Modelled: estimated from a model and structural indicators where direct published figures are limited.
Basis: shown per row (Administered, Triangulated or Modelled; definitions below). Where it sits places each band in the cheapest, middle or most expensive third of all 32 compared markets, by its midpoint. Connection wait is the free level shown on Connection friction, ranked.
Take the data
The same evidence behind every band, per market.
Each market's delivered-cost band and its per-line provenance (realized_cost).
GET /api/v1/ratings/{id}
The same rows, region by region, with the figure contract on every band.
GET /api/v1/cost?region=all
European day-ahead energy prices are published weekly on the price signal page. Energy is one part of a delivered bill, and it moves differently. European wholesale price signal →