PGIQ Rating · ratings as of June 2026 · data refreshed 24 Nov 2026
3

🇨🇦 Newfoundland & Labrador

Viable, with conditions, holding steady Minor flags found
Tier 3 Workable · PGIQ Rating score 58/100, #22 of 79 markets (fundamentals 61, less a 3-point grid-reliability adjustment) · Outlook Stable · Med confidence · how we score
Tier
3Workable
#22 of 79 markets
Delivered cost
Not published
No band compiled for this market yet
Connection wait
Not yet estimated
No connection timing held
Reliability and outlook
−3 pts
Outlook → Stable · Med confidence

The headline hydro surplus is misleading: Churchill Falls output is largely contracted and exported, the island grid is separate and remote, and Muskrat Falls has been troubled. Deliverable power for a new island load is limited despite the paper surplus.

See live grid data →
One market,
four reads
Build52/100Build scoreSellGrade C (index 49/100)Offtake grade (index)PlanLightLoad pressureMonitorNot coveredSiting screen only
The same market, four decisions. Open any lens to see this market ranked against the rest.
The same market, read four ways

Newfoundland & Labrador is a limited market to sell power into

Grade C (Limited)
Offtake score 49/100
Demand 27, build feasibility 52, combined into the score. For a seller: where buyers already pay, how tight supply is, and how feasible new build is here.
Scheduled to change
End 2026: Definitive binding agreements on Churchill Falls and Gull Island targeted (VOCM).
See it on the Offtake grade →

Newfoundland & Labrador: little room at system level, light demand pressure

Little room 47/100
System-level room, not local capacity
Local capacity: not assessed. We have found no operator publication of area or substation capacity for this market, so whether the bus serving a candidate site can take the load is an open question. Absence of a finding here is not evidence that capacity exists.
Two reads for a grid planner: how much room the system as a whole looks to have (Little room), and how hard demand is already pushing (Light). The first is a market-level estimate from connection ease, forward adequacy and reliability margin. It is not local deliverability. Capacity at a specific substation is not assessed for this market, and a market can look roomy while the bus you want has nothing available. Confirm local capacity with the utility before relying on it.
Demand growth
Slow load growth in our read, the pull on your system.
Future firm supply
Future firm supply: adequacy flagged for a large new load.
Load Pipeline Reality → Where demand is hungry → Connection friction →

Newfoundland & Labrador is not yet covered for a held exposure

SITING SCREEN ONLY
Newfoundland & Labrador is not yet monitored. Full monitoring needs reviewed reliability, connection-queue data and a compiled cost band; this market has only a subset, so we show it as a siting screen. We deepen coverage market by market.
See the markets we cover →
Your load. We don't publish a cost band for this market, so there is nothing to recompute for your load.
Connection-wait indicator, not a wait time
Strength BCapacity scarcity
In Labrador East and West, new load additions above 200 kW have been restricted since 2019 and each needs the regulator's exemption; the transmission capacity of the Labrador West system has not increased since. This applies to Labrador, not the island.
Source: Board of Commissioners of Public Utilities, Order P.U. 31(2026), published 28 Sep 2026.
No published source gives a connection wait for a large new load here. Ask the grid operator for its large-load study timeline. How indicators are graded →

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%52

Limited access: remote, separate island grid; Labrador hydro is contracted/exported.

Show evidence
Availability25%55

Constrained deliverable availability despite a large paper surplus.

Cost25%93

Cheap power.

Momentum15%22

Little momentum.

Carbon5%99

Near-zero operational carbon (~10 g), hydro.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-centre build already underway, not just stated intentions.

Download the evidence pack (print-ready, free) →

Seller view: Read these the other way: momentum is your customer pipeline, cost is your revenue ceiling, and access is how hard it is to build and sell here, not only to connect.

Reliability overlay

Reliability adjustment: the five-pillar score of 61 is reduced to 58, a deduction of 3 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.
Show evidence

Historical bulk-system performance: No reliability flags found

Historical utility-territory delivery performance: No reliability flags found

Forward resource adequacy (assessed): Adequacy flagged

Modelled read: hydro-heavy but small and isolated, with a Muskrat Falls commissioning history.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

modelled

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Low. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Download the evidence pack (print-ready, free) →

Seller view: Tight forward capacity (firm supply promised for future years) is scarcity that firm generation and storage get paid for; an adequacy flag is a demand signal for new supply, not only a risk to a load.

Supply relief outlook

Show evidence
Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Slow load growth competing for the same capacity.
Future firm supply
Future firm supply: adequacy flagged.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Download the evidence pack (print-ready, free) →

Grid conditions now

Structural baseline, June 2026Open the live map for Newfoundland & Labrador →
Average demand
1,700 MW
Structural baseline, June 2026
Average system demand across the market, not the peak.
Wholesale price
No wholesale market
Administered rates set by the regulator, not a market price. This is not the delivered cost.
Carbon intensity
16 g/kWh
Structural baseline, June 2026
Derived from the fuel mix. Never directly measured.
Renewable and nuclear
98%
Structural baseline, June 2026
The low-carbon share: generation from wind, solar, hydro, geothermal, biofuel and nuclear. Biofuel is counted as low-carbon, not zero-emission. The read for a carbon target.
Show all 10 fields
Renewable only
98%
Structural baseline, June 2026
Wind, solar, hydro, geothermal and biofuel. Excludes nuclear, which is low-carbon but not renewable, so this is the read for an RE100-style renewable procurement mandate.
Installed capacity
8,800 MW
Structural baseline, June 2026
Firm capacity
not held
Structural baseline, June 2026
De-rated, system-level.
System firm margin
not held
Structural baseline, June 2026
Market-wide estimate of de-rated firm capacity less peak demand. This is a directional screen, not local connectable capacity at any point of delivery.
Imports
50 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.
Exports
900 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.

Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.

Outlook drivers

Show evidence

↑ Upgrade triggers

  • Churchill Falls contract changes free deliverable surplus (post-2041).
  • Grid and transmission investment improves deliverability.

↓ Downgrade triggers

  • Continued contracted/exported hydro.
  • Island-grid reliability issues.

Download the evidence pack (print-ready, free) →

Scheduled to change

Show evidence
Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
End 2026
Definitive binding agreements on Churchill Falls and Gull Island targeted
The 17 Aug 2026 agreement is non-binding. Execution is what triggers the Major Projects Office referral, the federal loan guarantee for Gull Island and the provincial electricity rebate.
By Oct 2026
Quebec general election, a live risk to the counterparty's position
The Parti Quebecois government, sworn in on 21 Oct 2026, says it will review the agreement and bring it to the National Assembly. A change of government in Quebec before binding agreements are signed is the single largest execution risk to the deal.
On binding agreements
$1 billion federal commitment to a Labrador West transmission line
Stated as necessary to open new mining and industrial projects in the Labrador Trough. This, not Gull Island, is the near-term item that would change what a large load can actually connect to in Labrador.
Through the early 2040s
Gull Island and associated build, on Ottawa's own GDP timeline
The 14,000 MW figure is a multi-decade construction programme, not near-term supply. A load siting in the next few years should price the existing system, not the announcement.
No date set
Churchill Falls expansion (CFX) feasibility study on expanding the Churchill Falls plant
The expansion was removed from the agreement and has no commercial arrangements; treat it as optionality, not capacity.

Download the evidence pack (print-ready, free) →

Key risks

Peer comparison

Trades like
remote hydro provinces
Ahead
on raw clean power
Behind
on deliverable access

Evidence behind this rating

The real-world events that test our Tier 3 call for Newfoundland & Labrador: 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Show evidence
Newfoundland and Labrador House of Assembly backs the Churchill Falls and Gull Island resolution; the agreement stays non-binding NON-BINDING
Sep 2026AvailabilityMateriality: med

On 17 Sep 2026, after four days of debate, the House of Assembly voted in favour of a resolution on the Definitive Cooperation and Implementation Agreement for Churchill Falls and Gull Island, the Premier said in a statement that evening. The vote is political approval, not a contract. The agreement signed on 17 Aug 2026 by Newfoundland and Labrador Hydro, Hydro-Québec and Churchill Falls (Labrador) Corporation says it is not legally binding apart from a few procedural sections; the parties aim to sign definitive agreements by 31 Dec 2026, and the agreement ends on 31 Mar 2027 unless extended. Hydro-Québec's Gull Island project page (undated) gives 2034 as the planned commissioning year, so no Gull Island power is planned before then.

Power to a buyer: Nothing changes for a buyer. The vote does not make the agreement binding, and Hydro-Québec plans Gull Island commissioning for 2034, outside any current outlook window.
Source: Government of Newfoundland and Labrador ↗
Churchill Falls and Gull Island agreement replaces the 1969 contract; the province retains more of the output NON-BINDING ✓ Supports the rating
Aug 2026AvailabilityMateriality: high

Announced 17 Aug 2026 in St. John's by the Prime Minister with the premiers of Newfoundland and Labrador and Quebec. The agreements terminate the 1969 Churchill Falls power contract and replace the December 2024 MOU. Federal financing supports Churchill Falls upgrades, developing Gull Island, co-investment with the Innu of Labrador in a Labrador onshore wind project, and associated transmission. Newfoundland and Labrador retains more of the output than under the 2024 MOU, plus a share of the wind project's output and a transmission portfolio into New York, New England and Ontario markets, which holds only if the non-binding agreement becomes definitive. TWO QUALIFIERS: the agreement is non-binding, with definitive agreements targeted by end-2026, and the Churchill Falls expansion itself (CFX) was removed from it, leaving a feasibility study with no commercial arrangements in place. The near-term physical change for a load siting in this province is the Labrador West transmission line.

Power to a buyer: Nothing before the 2030s. Ottawa's own GDP timeline runs to the early 2040s; the near-term item is the Labrador West transmission line, not the headline capacity.
Source: Government of Newfoundland and Labrador ↗
Labrador Trough corridor referred to the federal Major Projects Office to unlock mining load ANNOUNCED ✓ Supports the rating
Aug 2026AccessMateriality: high

The federal government referred the Labrador Trough Clean Power, Critical Minerals and Infrastructure Corridor to the Major Projects Office, which coordinates federal financing and accelerates permitting. Pre-development funding under the First and Last Mile Fund covers a Labrador West transmission expansion to connect western Labrador mining operations to the grid, and planning work for the Kami iron ore project near Wabush. The province separately reports a federal funding commitment to the Labrador West line. Lack of power has been the stated constraint on developing the region, so transmission is the binding item for any large industrial load there.

Power to a buyer: Pre-development funding only. The Labrador West line is the item that would let a new industrial load in western Labrador connect at all; it is committed on paper and unbuilt.
Source: Prime Minister of Canada ↗
Churchill Falls expansion (CFX) removed from the agreement; feasibility study only ANNOUNCED ▲ Challenges the rating
Aug 2026AvailabilityMateriality: med

VOCM reports that CFX, the expansion of the Churchill Falls generating station itself, has been taken out of the new agreement. A feasibility study will be completed but commercial arrangements are not in place. The headline capacity therefore rests on Gull Island, the wind project and existing Churchill Falls capacity rather than on an expansion of the plant. Recorded separately from the announcement because the distinction between a committed project and a study is the whole question for anyone pricing future supply.

Power to a buyer: No capacity from CFX at any date. A feasibility study with no commercial arrangements is optionality, not supply.
Source: VOCM ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Download the evidence pack (print-ready, free) →

🔔 Get alerts for Newfoundland & Labrador
Get an email when this market's rating, outlook or a material development changes. Market alerts are part of the Analyst Desk.

Rating history

Show evidence
Oct 2026
AffirmedAffirmed, no change, 23 Oct 2026. The agreement remains non-binding and no definitive agreement has been signed. Quebec's incoming Parti Quebecois government has said it will review the deal and take it to the National Assembly rather than scrap it. Gull Island is planned for the next decade, outside the outlook window, so under our outlook guard rules a non-binding announcement does not move the tier or the outlook. Revisit when definitive agreements are executed.
Trigger: Churchill Falls and Gull Island Definitive Cooperation and Implementation Agreement, 17 Aug 2026 (non-binding); House of Assembly resolution, 17 Sep 2026; Quebec general election, 5 Oct 2026
June 2026
New ratingNew rating: Tier 3 Workable assigned (corrected from a naive surplus read).
🔒 The full time series behind Newfoundland & Labrador, how its score, recurring cost, and interconnection queue (the line to connect to the grid) have moved month by month, is part of the Analyst Desk. The rating actions above are always free.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Download the evidence pack (print-ready, free) →

Data provenance and freshness

Show evidence
What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostNot assessedWe hold no evidence for this yet
ConnectionNot assessedWe hold no evidence for this yet
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryNot assessedWe hold no evidence for this yet
Local capacityNot assessedWe hold no substation-level evidence
Not yet good enough for any decision use. The weakest fields are cost and connection.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Low

None of the 1 data layers is directly measured; they are triangulated or modelled

Coverage

Partial

1 of 3 dimensions: reliability, connection, cost

Last reviewed

23 Oct 2026

per-layer vintages below

Source strength is low: none of the 1 data layers is directly measured; they are triangulated or modelled. Confidence in the rating (Med) is a separate judgement about the opinion as a whole, set in review; source strength grades only how directly the numbers underneath were measured.

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmodelled2025Freshon the market page

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

Download the evidence pack (print-ready, free) →

What this market can and cannot answer yet

Show evidence
No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Forward resource adequacy (assessed)

What is open

  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Cost evidence (would change the answer)
  • Connection evidence (would change the answer)
  • Regulatory evidence
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • No cost or schedule range is compiled for this market.

What could disqualify this market

  • Contracted hydro and deliverability.
  • Remoteness and island-grid constraints.

Download the evidence pack (print-ready, free) →

Questions to put to the utility

Show evidence
These come from the gaps in our record for Newfoundland & Labrador: the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What would a 100 MW load at a 95% load factor, on high-voltage service, pay per MWh all in, under the tariff it would actually be served on? Needed for a project case
    Why it is open: no compiled cost band for this market yet.
  2. How long is it from a complete application being accepted to full firm energization of the MW we need, and which milestones (initial, phased, temporary or conditional energization) would come first? Needed for a project case
    Why it is open: no countable queue or operator-published process for this market.
  3. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  4. Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?
    Why it is open: no dated regulatory read compiled for this market yet.
  5. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/newfoundland/gaps

Download the evidence pack (print-ready, free) →

Score history

How Newfoundland & Labrador's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.

Immutable monthly snapshots of the reliability-adjusted score, tier, outlook and recurring cost, oldest first. Dated when taken and never back-filled, so the series only compounds forward. Part of the Analyst Desk →

What next for Newfoundland & Labrador?

Add to shortlistTrack it alongside your other candidates.Compare with peersRank markets against each other on your own weights.Open the Analyst DeskEvery market side by side, with history and alerts.Retrieve it through the APIThe same read as JSON, with provenance on every field.

Done with Newfoundland & Labrador? Browse every market or see conditions across every region.

How does Newfoundland & Labrador compare to every other market?

This page is our full read on Newfoundland & Labrador alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.

With your Analyst Desk, compare Newfoundland & Labrador against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.

+ Add to your shortlist Recurring cost, ranked Connection friction, ranked Get the Analyst Desk →

Official carbon intensity

Since 28 Sep 2026 we serve Canada's national inventory figure for Newfoundland and Labrador: 16 gCO2e/kWh (2024, generation basis, preliminary). Where a live feed is available, the carbon figure in the live conditions on this page can differ: we derive that one hourly from the current fuel mix, so it moves through the day. Carbon intensity does not feed the PGIQ Rating.

Boundary: operational combustion, CO2-equivalent, per kWh delivered to the grid. Main activity producers only. ECCC National Inventory Report, Annex 7 →