PGIQ Rating · ratings as of June 2026 · data refreshed 24 Nov 2026
3

🇺🇸 MISO (Midwest)

Viable, with conditions, and the path is improving Reliability flags found
Tier 3 Workable · PGIQ Rating score 56/100, #29 of 79 markets (fundamentals 63, less a 7-point grid-reliability adjustment) · Outlook Positive · Med confidence · how we score

Cheap power and a real build pipeline across Ohio, Indiana, Chicago and Iowa, with the ERAS fast-track easing a deep connection queue. Getting connected is the main hurdle; low cost and steady demand are the strengths.

See live grid data →
One market,
four reads
Build56/100Build scoreSellGrade B (index 75/100)Offtake grade (index)PlanRisingLoad pressureMonitorWatch (44/100)Grid strength
The same market, four decisions. Open any lens to see this market ranked against the rest.
The same market, read four ways

MISO (Midwest) is a moderate market to sell power into

Grade B (Moderate)
Offtake score 75/100
Demand 48, build feasibility 56, combined into the score. For a seller: where buyers already pay, how tight supply is, and how feasible new build is here.
Price to beat
A 100 MW load on our standard case pays about $60/MWh delivered here. A competitive supply offer works against that level.
Forward capacity (firm supply promised for future years) price
about $217 per MW-day, annualized (2025/26 planning year); forward cost pressure High.
Queue depth (generation and storage)
About 382 GW in the interconnection queue (the line to connect to the grid), typical wait 50 months.
Regulatory momentum
Mixed, improving. FERC's 18 June 2026 Section 206 show-cause order pushes MISO to set clear large-load connection and cost-allocation rules, reinforcing reforms MISO was already developing for fast-growing Midwest data-centre demand.
See it on the Offtake grade →

MISO (Midwest): effectively full at system level, rising demand pressure

Effectively full 27/100
System-level room, not local capacity
Local capacity: not assessed. We have found no operator publication of area or substation capacity for this market, so whether the bus serving a candidate site can take the load is an open question. Absence of a finding here is not evidence that capacity exists.
Two reads for a grid planner: how much room the system as a whole looks to have (Effectively full), and how hard demand is already pushing (Rising). The first is a market-level estimate from connection ease, forward adequacy and reliability margin. It is not local deliverability. Capacity at a specific substation is not assessed for this market, and a market can look roomy while the bus you want has nothing available. Confirm local capacity with the utility before relying on it.
Generation and storage queue
382 GW requested; about 95.5 GW likely to reach operation after historical withdrawal. The gap is speculative pipeline. This counts generation and storage seeking to connect, not load.
Demand growth
Fast load growth in our read, the pull on your system.
Future firm supply
Future firm supply: tight for a large new load.
Load Pipeline Reality → Where demand is hungry → Connection friction →

Grid Risk Annex BETA

Watch
Needs structuring or mitigants · grid strength 44/100
A cited, dated grid-risk read on MISO (Midwest) for a capital provider, the banks and private-credit lenders, infrastructure funds and insurers holding or underwriting a power or data-centre exposure here. Drop it into a credit memo and watch each factor over the life of the exposure.
Read it against your asset. For a load asset (Buy), weight connection access and energization timing. For a generation or offtake asset (Sell), weight offtake demand, curtailment (being told to cut output or consumption) and cost realisation. For a grid or transmission asset (Move), weight load-pipeline reality and buildout risk.
Rating and track record
PGIQ Tier 3 Workable, outlook Positive, Med confidence. Scored on a public, dated, falsifiable record you can cite in a credit memo.
Delivery reliability
Reliability flags found in the bulk and local outage record we reviewed.
Future firm supply
Future firm supply: tight.
Cost certainty
Recurring cost $48 to $78/MWh for the standard 100 MW case, basis triangulated. Excludes connection capital.
Regulatory / stroke-of-pen
Mixed, improving. FERC's 18 June 2026 Section 206 show-cause order pushes MISO to set clear large-load connection and cost-allocation rules, reinforcing reforms MISO was already developing for fast-growing Midwest data-centre demand.
Execution risk
382 GW in the generation and storage queue, about 75% historically withdrawn, the risk the project or load actually energizes on time.
Ongoing monitor
Track this market's rating actions as a covenant-style monitor over the life of the exposure.
Monitoring plan
Covenant-style triggers to watch over the life of the exposure: a change in the PGIQ rating or outlook; a dated regulatory move (stroke-of-pen risk); a capacity-auction or cost-band shift; a forward firm-supply adequacy warning; and a rise in queue drop-out or connection friction. Track them on this market page, or as Analyst Desk alerts.
Sources: MISO ERAS
This is a directional grid-risk screen, not a credit rating, and not investment, engineering or procurement advice.
The formatted, cited Grid Risk Annex export is an Analyst Desk feature.See the Grid Exposure Monitor →

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$48 to $78 per MWh

Midpoint about $60 per MWh

How this band was built

triangulated

From 3 public fragments

Your load

See how the answer changes for a different load size
The band above stays the comparable figure.
Declared case only
We hold this market's cost for the declared case only (100 MW, 95% load factor, high-voltage service). We don't scale it: tariff classes, demand charges, capacity charges and connection limits change with size, so 500 MW is not five times 100 MW.
Show evidence

What builds the $60 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$35
$15
Wholesale energy$35
Transmission & delivery$15
Capacity (Planning Resource Auction)$6
Ancillary & other$4
All-in delivered$60 /MWh
Transmission & delivery is a bundled category. It currently combines transmission, distribution and applicable demand-related network charges in one line. Those elements have not been independently sourced or separately reconciled.
Capacity cross-check. Planning Resource Auction cleared at 126 USD per MW-day, annualized across the four seasons for 2026/27 planning year (MISO Planning Resource Auction 2026/27, annualized; North/Central zones), a measured observation. Converted to this archetype it is $5.53/MWh, using ($/MW-day x 365) / (8760 x load factor) at a 0.95 load factor (8,322 MWh per MW-year). That conversion is ours, not the operator's. No reserve-margin or peak-contribution gross-up is applied, because no cited multiplier is held for this market. The figure is therefore a FLOOR: the archetype's actual capacity obligation is at least this and probably higher. This is an auction clearing price converted to the archetype's consumption, not a tariff line a supplier would bill. Tariff research has not established an applicable charge for this market. The estimated allocation is consistent with the sourced floor.
How the $60/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. The Midwest is a moderate, generally low-cost market; the capacity charge is modest outside scarcity years, and transmission is the main non-energy cost. Anchored to published figures (MISO 2024 State of the Market (Potomac Economics)). How this is built →

Where the cost lands

$60
Low $48Midpoint $60High $78
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimized one. The midpoint is our best central read.
What is in the number: Real-time wholesale energy near $31 per MWh in 2024, plus transmission and delivery, a modest Planning Resource Auction capacity charge, and ancillary services.

The Midwest is a moderate, generally low-cost large-load market: cheap wholesale energy plus transmission and a modest capacity charge. Delivered cost sits below the coastal ISOs.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: MISO 2024 State of the Market (Potomac Economics) · Wholesale electricity prices (EIA).

Download the evidence pack (print-ready, free) →

Seller view: This delivered price is the level a competitive supply offer must beat, and the revenue ceiling a merchant plant works against here.

Forward cost anchor

Show evidence
Siting a load is a decade-long cost bet, so the forward cost of firm capacity matters more than today's spot price. This is the public capacity-auction clearing price, the market's own forward read, not a paywalled forward curve.

Forward cost pressure

High

Latest capacity clearing price

about $217 per MW-day, annualized

2025/26 planning year

Trend: Volatile: a record summer clearing price of $666.50 per MW-day, easing about 42% the following year but staying tight.

MISO's first seasonal, reliability-based auction produced a record summer clearing price of $666.50 per MW-day and an annualized level near $217; the following year eased toward $126 but the market stays structurally tight.

Source: MISO Planning Resource Auction (Modo Energy). A derived indicator: we publish the public clearing price and our read, never paywalled exchange data.

Download the evidence pack (print-ready, free) →

Seller view: This capacity clearing price is a direct revenue signal for new supply: a rising trend supports the build thesis, a falling one is a warning.
Connection wait for a large new load
25 to 75 months
Range 25 to 75 months (2 to 7 years) (modelled from the generation queue). Mark: modelled.
Modelled from the generation queue, not a measured load wait (wait-model-1.0). Inputs: the generation and storage queue's typical duration of 50 months (the centre), and its depth of 382 GW against an estimated peak of 84.1 GW (ratio 4.54), which sets the range at plus or minus 50%. No published large-load wait exists here to check it against. Ask the grid operator for its large-load study timeline. · Source: LBNL Queued Up 2026 · Compare connection waits across markets →

Interconnection queue

Show evidence
These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.

Active queue depth

382 GW

Typical wait

50 months

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centres, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

Download the evidence pack (print-ready, free) →

Seller view: A deep queue is both your own time-to-revenue and a moat against competing supply; what matters is the effective supply likely to complete after withdrawal, not the headline queue.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%50

Constrained access (deep queue), eased by the ERAS fast-track for priority projects.

Show evidence
Availability25%55

Moderate availability across a large footprint.

Cost25%85

Cheap power.

Momentum15%70

High momentum: a growing Midwest build (Ohio, Iowa).

Carbon5%52

Carbon moderate-high (~330 g).

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-centre build already underway, not just stated intentions.

Download the evidence pack (print-ready, free) →

Seller view: Read these the other way: momentum is your customer pipeline, cost is your revenue ceiling, and access is how hard it is to build and sell here, not only to connect.

Reliability overlay

Reliability adjustment: the five-pillar score of 63 is reduced to 56, a deduction of 7 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.
Show evidence

Historical bulk-system performance: Minor flags found

Exposed in Winter Storm Uri (Feb 2021), with rolling blackouts in the MISO South region during the extreme cold.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

event-based · FERC/NERC Feb 2021 cold weather final report

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 119.9 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 25 of 25 territories, 100% of customers, regional context only)

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. mixed methods: IEEE 92%; respondent-defined 8% of customers. Major event days are excluded throughout; the methods differ only in how those days are identified, a smaller difference than the spread between the utilities themselves. Constituents below carry their own standard. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

The territories inside this market

The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.

Territory operatorSAIDI min/yrCustomersMajor-event method
DTE Electric Company (MI)159.172,261,010IEEE 1366
Consumers Energy Co - (MI) (MI)154.971,889,301IEEE 1366
Northern States Power Co - Minnesota (MN)110.391,361,168IEEE 1366
Union Electric Co - (MO) (MO)94.01,283,126IEEE 1366
Ameren Illinois Company (IL)120.61,249,900IEEE 1366
Wisconsin Electric Power Co (WI)109.01,212,936IEEE 1366
Duke Energy Indiana, LLC (IN)112.89910,102IEEE 1366
MidAmerican Energy Co (IA)88.0740,347IEEE 1366
AES Indiana (IN)87.3525,000IEEE 1366
Wisconsin Power & Light Co (WI)67.52501,445own method
Interstate Power and Light Co (IA)99.35499,530own method
Northern Indiana Pub Serv Co (IN)169.0485,189IEEE 1366
Wisconsin Public Service Corp (WI)95.0469,161IEEE 1366
Northern States Power Co (WI)122.37260,234IEEE 1366
Madison Gas & Electric Co (WI)41.61166,686IEEE 1366
Southern Indiana Gas & Elec Co (IN)81.2155,822own method
ALLETE, Inc. (MN)119.9138,546IEEE 1366
Northern States Power Co - Minnesota (SD)63.63104,471IEEE 1366
Northern States Power Co - Minnesota (ND)54.5495,754IEEE 1366
MidAmerican Energy Co (IL)174.085,293IEEE 1366
Otter Tail Power Co (MN)141.6763,290IEEE 1366
Otter Tail Power Co (ND)129.659,761IEEE 1366
Otter Tail Power Co (SD)70.7811,930IEEE 1366
Northern States Power Co (MI)115.478,923IEEE 1366
MidAmerican Energy Co (SD)42.05,299IEEE 1366

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Tight

The only region NERC's 2024 assessment rates high-risk: coal retirements and delayed additions push reserve margins below reference levels from 2025, with a projected shortfall of about 2.7 GW by 2029.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

assessed · NERC 2024 Long-Term Reliability Assessment

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Download the evidence pack (print-ready, free) →

Seller view: Tight forward capacity is scarcity that firm generation and storage get paid for; an adequacy flag is a demand signal for new supply, not only a risk to a load.

Reliability metrics

Show evidence

Delivery reliability (measured)

The average customer loses about 119.9 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across 25 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 25 of 25 territories, 100% of customers, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Download the evidence pack (print-ready, free) →

Supply relief outlook

Show evidence
Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Fast load growth competing for the same capacity.
New supply in motion
About 95.5 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Can new supply arrive
Regulatory momentum mixed, improving.
Future firm supply
Future firm supply: tight.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Download the evidence pack (print-ready, free) →

Regulatory momentum

Show evidence
The regulatory and permitting environment is increasingly the binding variable for a new large load.
Mixed↑ improving

Why: FERC's 18 June 2026 Section 206 show-cause order pushes MISO to set clear large-load connection and cost-allocation rules, reinforcing reforms MISO was already developing for fast-growing Midwest data-centre demand.

What would change the read: MISO's Section 206 response becoming a durable, open large-load connection process rather than case-by-case treatment.

Download the evidence pack (print-ready, free) →

Grid conditions now

Structural baseline, June 2026Open the live map for MISO (Midwest) →
Average demand
58,000 MW
Structural baseline, June 2026
Average system demand across the market, not the peak.
Wholesale price (modelled)
$30/MWh
Structural baseline, June 2026
US dollars. Energy only, and always modelled: no live price feed exists in any market. This is not the delivered cost.
Carbon intensity
340 g/kWh
Structural baseline, June 2026
Derived from the fuel mix. Never directly measured.
Renewable and nuclear
50%
Structural baseline, June 2026
The low-carbon share: generation from wind, solar, hydro, geothermal, biofuel and nuclear. Biofuel is counted as low-carbon, not zero-emission. The read for a carbon target.
Show all 10 fields
Renewable only
30%
Structural baseline, June 2026
Wind, solar, hydro, geothermal and biofuel. Excludes nuclear, which is low-carbon but not renewable, so this is the read for an RE100-style renewable procurement mandate.
Installed capacity
140,000 MW
Structural baseline, June 2026
Firm capacity
not held
Structural baseline, June 2026
De-rated, system-level.
System firm margin
not held
Structural baseline, June 2026
Market-wide estimate of de-rated firm capacity less peak demand. This is a directional screen, not local connectable capacity at any point of delivery.
Imports
2,000 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.
Exports
2,000 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.

Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.

Outlook drivers

Show evidence

↑ Upgrade triggers

  • ERAS and queue reform shorten connection timelines.
  • Wind and solar additions lower carbon.

↓ Downgrade triggers

  • Queue backlog and study delays persist.
  • Coal-exit tightens availability.

Download the evidence pack (print-ready, free) →

Key risks

Peer comparison

Trades like
SPP (cheap, building)
Ahead
on momentum vs SPP
Behind
ERCOT on access

Evidence behind this rating

The real-world events that test our Tier 3 call for MISO (Midwest): 2 support it and 2 challenge it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Show evidence
DC Circuit vacates the DOE emergency order keeping the J.H. Campbell coal plant open ANNOUNCED ▲ Challenges the rating
Sep 2026AvailabilityMateriality: med

On 11 Sep 2026 a unanimous DC Circuit panel vacated the DOE order requiring Consumers Energy to run the J.H. Campbell plant in West Olive, Michigan past its approved retirement date, holding that Federal Power Act section 202(c) is a narrow last resort for genuine short term crises and not a substitute for state reliability planning. DOE had extended the order six times through Aug 2026. Michigan regulators and MISO had already approved the retirement and its replacement plan.

Power to a buyer: Supply comes off, on the schedule the state already approved. The plant returns to its retirement path rather than being held open by federal order, so a buyer should assume the replacement plan, not the coal unit. Timing depends on any appeal.
Source: Michigan Attorney General ↗
Wisconsin regulators send the line serving the Port Washington data centre back to the start ▲ Challenges the rating
Aug 2026AccessMateriality: med

The Public Service Commission of Wisconsin voted unanimously (6 Aug 2026) to rescind the completeness determination for American Transmission Company's high-voltage project, forcing a restart of the application after hundreds of design adjustments. Commissioners said the vote should not be read as a rejection of the project. ATC says it is the first such action in the PSC's history.

Power to a buyer: Later power for the Port Washington site: the high-voltage line that serves it restarts its application, so its in-service date moves out by an amount not yet stated.
Source: Wisconsin Watch ↗
MISO declares a maximum generation emergency in its second July heat dome ✓ Supports the rating
Jul 2026AvailabilityMateriality: med

A dayslong heat dome over the Midwest drove demand toward record levels and MISO invoked maximum generation emergency procedures (15 Jul 2026), its second emergency of the month.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: RTO Insider ↗
MISO forecasts sharp peak load growth by 2035 on data centres ✓ Supports the rating
Apr 2026MomentumMateriality: med

MISO's long-term forecast (13 Apr 2026) sees peak load rising substantially by 2035, led by data centres, with a first wave of data-centre load expected online in 2026-2027. MISO flags high uncertainty and signs of right-sizing.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Utility Dive / MISO ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Download the evidence pack (print-ready, free) →

🔔 Get alerts for MISO (Midwest)
Get an email when this market's rating, outlook or a material development changes. Market alerts are part of the Analyst Desk.

Rating history

Oct 2026
AffirmedCost-pillar score 88 to 85: now set by one published rule from the band midpoint ($60/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 57 to 56. Tier 3 Workable unchanged.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
Show evidence
Oct 2026
DowngradeTier 2 Strong to Tier 3 Workable under the published tier rules: a PGIQ Rating of 57 sits in the Tier 3 band. No pillar evidence changed; markets with the same score now sit in the same tier.
Trigger: Tier rules published with the Oct 2026 ratings release (equal scores, equal tiers)
Sep 2026
AffirmedTier holds. One unit returning to its state approved retirement date does not move the tier, and the replacement plan was already in the availability read. The wider point is that federal emergency authority can no longer be assumed to backstop marginal retirements in this footprint, which removes an upside the rating never scored. Watch whether reserve margin (the supply cushion above expected peak demand) assumptions relied on it.
Trigger: DC Circuit vacates the DOE section 202(c) order on J.H. Campbell, 11 Sep 2026
Aug 2026
AffirmedTier holds. The commission was explicit that this is a procedural reset rather than a rejection, and the underlying project is still expected. It does illustrate the state-level siting risk behind data-centre-driven transmission in MISO, where the delivery path runs through a state commission that can restart the clock.
Trigger: PSC of Wisconsin rescinds the ATC completeness determination, 6 Aug 2026
Jun 2026
AffirmedNamed in the FERC show-cause suite; reform process is preliminary and procedural. Tier holds, monitoring the 17 Aug response.
Trigger: FERC Section 206 show-cause order (18 Jun 2026)
Jul 2026
AffirmedTier holds. The 35% load-growth forecast confirms demand momentum without changing near-term access or availability.
Trigger: MISO long-term load forecast, 13 Apr 2026
Jul 2026
AffirmedEmergency procedures managed the heat dome without reported firm load shed. Consistent with the thin-margin availability profile already in the rating. Tier holds.
Trigger: Maximum generation emergency at ~122 GW demand, 15 Jul 2026
June 2026
New ratingNew rating: Tier 2 Strong assigned.
Show evidence
🔒 The full time series behind MISO (Midwest), how its score, recurring cost, and interconnection queue have moved month by month, is part of the Analyst Desk. The rating actions above are always free.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Download the evidence pack (print-ready, free) →

What this would mean for a project

Show evidence

100 MW contracted demand, 95% load factor, HV servicecalculated

A load of this shape consumes 832,200 MWh a year. At the delivered band of $48 to $78/MWh that is $39,945,600 to $64,911,600 a year in recurring power.

Wholesale energy is 58% of the delivered cost here. The other $25/MWh is transmission and delivery, Capacity (Planning Resource Auction), and ancillary and other charges. See the full build-up.

Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.

Download the evidence pack (print-ready, free) →

Data provenance and freshness

Show evidence
What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionMarket-level (M2)Good for comparing markets, not for a site
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are connection and reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

3 of 4 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 25 of 25 territories, 100% of customers, regional context only)
Forward costmeasured2025/26 planning yearFreshMISO Planning Resource Auction (Modo Energy)
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshLBNL Queued Up 2026
Realized costtriangulated2026FreshMISO 2024 State of the Market (Potomac Economics)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

Download the evidence pack (print-ready, free) →

What this market can and cannot answer yet

Show evidence
No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $48 to $78 per MWh, midpoint $60, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 119.9 minutes per year (2024)
  • Historical bulk-system performance (event-based)
  • Forward resource adequacy (assessed)
  • Typical interconnection wait about 50 months (generation and storage queue, not a load wait)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Substation-level capacity evidence

How service and connection are organized

Territories in this market, each with its own filed record: DTE Electric Company, Consumers Energy Co - (MI), Northern States Power Co - Minnesota, Union Electric Co - (MO), Ameren Illinois Company, Wisconsin Electric Power Co, Duke Energy Indiana, LLC, MidAmerican Energy Co. Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $48 to $78 per MWh, midpoint $60 (triangulated)
  • Schedule: interconnection queues here run about 50 months for generation and storage; a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Interconnection backlog.
  • Availability through the fossil transition.

Download the evidence pack (print-ready, free) →

Questions to put to the utility

Show evidence
These come from the gaps in our record for MISO (Midwest): the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/miso/gaps

Download the evidence pack (print-ready, free) →

Score history

How MISO (Midwest)'s reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.

Immutable monthly snapshots of the reliability-adjusted score, tier, outlook and recurring cost, oldest first. Dated when taken and never back-filled, so the series only compounds forward. Part of the Analyst Desk →

What next for MISO (Midwest)?

Add to shortlistTrack it alongside your other candidates.Compare with peersRank markets against each other on your own weights.Open the Analyst DeskEvery market side by side, with history and alerts.Retrieve it through the APIThe same read as JSON, with provenance on every field.

Done with MISO (Midwest)? Browse every market or see conditions across every region.

How does MISO (Midwest) compare to every other market?

This page is our full read on MISO (Midwest) alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.

With your Analyst Desk, compare MISO (Midwest) against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.

+ Add to your shortlist Recurring cost, ranked Connection friction, ranked Get the Analyst Desk →