PGIQ Rating · ratings as of June 2026 · data refreshed 24 Nov 2026
3

🇭🇰 Hong Kong

Viable, with conditions, holding steady
Tier 3 Workable · PGIQ Rating score 49/100, #52 of 79 markets · Outlook Stable · Med-High confidence · how we score

A government-supported finance and cloud data hub with a strong measured delivery record, but among the most expensive power anywhere, on a small, land-constrained system, which keeps it a friction market for a new large load.

Live grid telemetry is not published for this market yet, so it does not appear on the map. The rating, cost and connection assessment on this page do not depend on it. See the markets that are covered →
One market,
four reads
Build65/100Build scoreSellGrade A (index 85/100)Offtake grade (index)PlanLightLoad pressureMonitorRobust (70/100)Grid strength
The same market, four decisions. Open any lens to see this market ranked against the rest.
The same market, read four ways

Hong Kong is a strong market to sell power into

Grade A (Strong)
Offtake score 85/100
Demand 51, build feasibility 65, combined into the score. For a seller: where buyers already pay, how tight supply is, and how feasible new build is here.
Price to beat
A 100 MW load on our standard case pays about $188/MWh delivered here. A competitive supply offer works against that level.
Connection
Connection difficulty Moderate, typical wait 2-3 years.
See it on the Offtake grade →

Hong Kong: room to spare at system level, light demand pressure

Room to spare 72/100
System-level room, not local capacity
Local capacity: not assessed. We have found no operator publication of area or substation capacity for this market, so whether the bus serving a candidate site can take the load is an open question. Absence of a finding here is not evidence that capacity exists.
Two reads for a grid planner: how much room the system as a whole looks to have (Room to spare), and how hard demand is already pushing (Light). The first is a market-level estimate from connection ease, forward adequacy and reliability margin. It is not local deliverability. Capacity at a specific substation is not assessed for this market, and a market can look roomy while the bus you want has nothing available. Confirm local capacity with the utility before relying on it.
Demand growth
Moderate load growth in our read, the pull on your system.
Load Pipeline Reality → Where demand is hungry → Connection friction →

Grid Risk Annex BETA

Robust
Standard terms likely · grid strength 70/100
A cited, dated grid-risk read on Hong Kong for a capital provider, the banks and private-credit lenders, infrastructure funds and insurers holding or underwriting a power or data-centre exposure here. Drop it into a credit memo and watch each factor over the life of the exposure.
Read it against your asset. For a load asset (Buy), weight connection access and energization timing. For a generation or offtake asset (Sell), weight offtake demand, curtailment (being told to cut output or consumption) and cost realisation. For a grid or transmission asset (Move), weight load-pipeline reality and buildout risk.
Rating and track record
PGIQ Tier 3 Workable, outlook Stable, Med-High confidence. Scored on a public, dated, falsifiable record you can cite in a credit memo.
Delivery reliability
Reviewed; no delivery reliability flags found in the bulk and local outage record.
Future firm supply
Reviewed; firm supply ample.
Cost certainty
Recurring cost $170 to $210/MWh for the standard 100 MW case, basis administered. Excludes connection capital.
Regulatory / stroke-of-pen
Not assessed.
Execution risk
Connection friction Moderate, the risk the project or load actually energizes on time.
Ongoing monitor
Track this market's rating actions as a covenant-style monitor over the life of the exposure.
Monitoring plan
Covenant-style triggers to watch over the life of the exposure: a change in the PGIQ rating or outlook; a dated regulatory move (stroke-of-pen risk); a capacity-auction or cost-band shift; a forward firm-supply adequacy warning; and a rise in queue drop-out or connection friction. Track them on this market page, or as Analyst Desk alerts.
Sources: CLP and HK Electric 2026 tariffs (HK Government) · CLP supply reliability about 99.999% · Developing data centres in Hong Kong (HK Government)
This is a directional grid-risk screen, not a credit rating, and not investment, engineering or procurement advice.
The formatted, cited Grid Risk Annex export is an Analyst Desk feature.See the Grid Exposure Monitor →

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$170 to $210 per MWh

Midpoint about $188 per MWh

How this band was built

administered

From 1 public fragment

Your load

See how the answer changes for a different load size
The band above stays the comparable figure.
Declared case only
We hold this market's cost for the declared case only (100 MW, 95% load factor, high-voltage service). We don't scale it: tariff classes, demand charges, capacity charges and connection limits change with size, so 500 MW is not five times 100 MW.
Show evidence

What sets this band

There is no wholesale spot market here, so the band is not an energy-plus-network stack. It is set by the regulated tariff levels below.
$180
$209
$170$210
CLP Power net tariff (Kowloon & New Territories)$180 /MWh
About 140.6 HK cents per kWh for 2026 under the Scheme of Control, roughly $180 per MWh. CLP serves most of Hong Kong, including the data-centre clusters.
HK Electric net tariff (Hong Kong Island)$209 /MWh
About 163.3 HK cents per kWh for 2026, roughly $209 per MWh, the pricier of the two regulated utilities.
These are the regulated tariff levels that define the band, not an additive cost stack. Hong Kong has no wholesale market; two vertically integrated utilities set regulated Scheme-of-Control tariffs, so the band spans the two providers. Anchored to published figures (CLP and HK Electric 2026 tariffs (HK Government)).

Where the cost lands

$188
Low $170Midpoint $188High $210
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimized one. The midpoint is our best central read.
What is in the number: Regulated Scheme-of-Control net tariffs from the two utilities: CLP Power at about 140.6 HK cents per kWh and HK Electric at about 163.3 HK cents per kWh for 2026, roughly $180 to $210 per MWh. There is no wholesale market.

Hong Kong's realized cost is the regulated Scheme-of-Control tariff of whichever of the two utilities serves the site, among the highest in the region. There is no wholesale market, so the tariff is the delivered cost.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Administered (a single regulated or state-set tariff, so the figure is the delivered cost and moves only on a regulator decision). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: CLP and HK Electric 2026 tariffs (HK Government) · CLP 2026 tariff tables.

Download the evidence pack (print-ready, free) →

Seller view: This delivered price is the level a competitive supply offer must beat, and the revenue ceiling a merchant plant works against here.
Connection wait for a large new load
24 to 36 months
Range 24 to 36 months (2 to 3 years). Mark: estimate.
Application & CLP / HK Electric study 6mo · Supply agreement 6mo · Network works 12mo · Construction & energization 6mo
Our estimate of the total wait for a large new load. The source does not say exactly which milestones it measures from and to, so treat it as approximate. Partial or temporary supply can sometimes start earlier. A typical case, not a firm quote. · Source: Hong Kong data-centre power supply (government) · Compare connection waits across markets →

Connection friction

How hard it is to connect a large new load here, and how long it takes. Part of the PowerGridIQ Connection Friction Feed. Labelled estimate; confidence Med.

Friction level

Moderate

Show evidence

This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.

CLP and HK Electric supply an orderly but land- and power-constrained market adding about 400 MW by 2026.

Hong Kong's two vertically integrated utilities, CLP and HK Electric, run an orderly connection process, and the city already hosts about 1.42 GW of data-centre IT load with more than 400 MW more due by end-2026. The constraint is land and long-run generation capacity in a dense city, not a chaotic queue.

What builds the 30-month wait

6
6
12
6
Application & CLP / HK Electric study6 mo
Supply agreement6 mo
Network works12 mo
Construction & energization6 mo
Typical time to energization30 months
How the typical connection wait breaks down by stage. Stages overlap in practice and vary by project; the split is our estimate anchored to the operator process, and the total is the representative time to energization. Anchored to the operator process (Hong Kong data-centre power supply (government)).

Data-centre share of demand pressure: High. Sources: Hong Kong data-centre power supply (government) · CLP apply for grid connection. The full cross-market connection dataset is available through the Connection Friction Feed.

Download the evidence pack (print-ready, free) →

Seller view: Connection difficulty is both your own time-to-revenue and a barrier limiting competing supply from reaching this market.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%42

Constrained access: severe land scarcity and a small system, though the government facilitates data centres and is upgrading the Northern Metropolis grid for AI density.

Show evidence
Availability25%55

Strong local delivery record: CLP reports about 99.999% supply reliability, roughly 2.6 minutes of unplanned outage a year, on a ~7.2 GW system.

Cost25%35

Very high cost: regulated Scheme-of-Control net tariffs run about 141 to 163 HK cents per kWh (~$180 to $210 per MWh).

Momentum15%58

Moderate momentum: an established banking and cloud hub plus a government AI Supercomputing Centre, but a small overall market.

Carbon5%40

Moderate-high carbon: gas and coal, with imported nuclear from Daya Bay.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-centre build already underway, not just stated intentions.

Download the evidence pack (print-ready, free) →

Seller view: Read these the other way: momentum is your customer pipeline, cost is your revenue ceiling, and access is how hard it is to build and sell here, not only to connect.

Reliability overlay

Reliability reviewed: no material concerns were found, so the rating is unchanged. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.
Show evidence

Historical bulk-system performance: No reliability flags found

Historical utility-territory delivery performance: No reliability flags found

Strong local delivery record on the utility's own published measure: CLP reports about 99.999% supply reliability, roughly 2.6 minutes of unplanned outage a year, on a small, dense system. This describes distribution performance, not the terms of a firm service contract.

measured · CLP supply reliability and power quality

Forward resource adequacy (assessed): No adequacy flags

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Download the evidence pack (print-ready, free) →

Seller view: Tight forward capacity (firm supply promised for future years) is scarcity that firm generation and storage get paid for; an adequacy flag is a demand signal for new supply, not only a risk to a load.

Supply relief outlook

Show evidence
Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Balanced
Demand pressure
Moderate load growth competing for the same capacity.

What this means: Supply and demand look broadly balanced; the outcome hinges on the drivers below.

Download the evidence pack (print-ready, free) →

Grid conditions now

Live grid coverage is not available for Hong Kong.

PowerGridIQ does not hold an operator feed for Hong Kong. The structural market assessment is unaffected.

The structural market assessment on this page is unaffected by it. A gap in coverage is not a finding about the market.

Outlook drivers

Show evidence

↑ Upgrade triggers

  • Northern Metropolis grid upgrades unlock AI-density sites.
  • More gas and imported low-carbon power lower the grid average.

↓ Downgrade triggers

  • Land scarcity and high cost cap large new builds.
  • Tariffs stay among the highest in the region.

Download the evidence pack (print-ready, free) →

Key risks

Peer comparison

Trades like
Singapore and Taiwan (pricey, constrained hubs)
Ahead
on reliability
Behind
on cost and scale

Evidence behind this rating

The real-world events that test our Tier 3 call for Hong Kong: 2 support it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Show evidence
Hong Kong utilities report very high supply reliability as data-centre demand grows ✓ Supports the rating
2025AvailabilityMateriality: med

CLP reports very high supply reliability with little unplanned outage a year, and both utilities say they hold adequate capacity and backup. That is a strong local delivery record on the utility's own published measure, and a real strength for a large load, even as high cost and land scarcity constrain the rating. It describes distribution performance, not the terms of a firm service contract.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: CLP ↗
Government builds a 3,000-petaflop AI Supercomputing Centre and upgrades the Northern Metropolis grid ✓ Supports the rating
2025MomentumMateriality: low

Hong Kong is standing up a government AI Supercomputing Centre and CLP is upgrading the Northern Metropolis grid for kilowatt-density AI load, real but modest momentum on a small, land-constrained system.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Developing data centres in Hong Kong (HK Government) ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Download the evidence pack (print-ready, free) →

🔔 Get alerts for Hong Kong
Get an email when this market's rating, outlook or a material development changes. Market alerts are part of the Analyst Desk.

Rating history

Show evidence
Oct 2026
UpgradeCost-pillar score 25 to 35: now set by one published rule from the band midpoint ($188/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 46 to 49. Tier 4 Constrained to Tier 3 Workable.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
June 2026
New ratingNew rating: Tier 4 Constrained assigned.
🔒 The full time series behind Hong Kong, how its score, recurring cost, and interconnection queue (the line to connect to the grid) have moved month by month, is part of the Analyst Desk. The rating actions above are always free.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Download the evidence pack (print-ready, free) →

Data provenance and freshness

Show evidence
What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostMarket-level (M2)Good for comparing markets, not for a site
ConnectionBroad (M1)Directional: good for screening and monitoring
ReliabilityBroad (M1)Directional: good for screening and monitoring
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryNot assessedWe hold no evidence for this yet
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are connection and reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

Moderate

2 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmeasured2025FreshCLP supply reliability and power quality
Connection frictionproxy2025/26FreshHong Kong data-centre power supply (government)
Realized costmeasured2026FreshCLP and HK Electric 2026 tariffs (HK Government)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

Download the evidence pack (print-ready, free) →

What this market can and cannot answer yet

Show evidence
No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $170 to $210 per MWh, midpoint $188, basis administered, against the 100 MW archetype

What is open

  • Forward resource adequacy (assessed)
  • Historical utility-territory delivery performance (would change the answer)
  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Regulatory evidence
  • Substation-level capacity evidence

How service and connection are organized

Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $170 to $210 per MWh, midpoint $188 (administered)

What could disqualify this market

  • Very high power cost.
  • Land and space scarcity on a small system.

Download the evidence pack (print-ready, free) →

Questions to put to the utility

Show evidence
These come from the gaps in our record for Hong Kong: the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What is the measured outage record (SAIDI) for the network that would serve our site, as filed with the regulator, and for which years? Needed for a project case
    Why it is open: no regulator outage series compiled for this market yet.
  2. What is the average carbon intensity of the grid supply we would draw, for which year, and is it measured or derived from the fuel mix?
    Why it is open: no grid snapshot compiled for this market yet.
  3. Are the connection rules for large loads changing? What has been proposed or decided, and when does it take effect?
    Why it is open: no dated regulatory read compiled for this market yet.
  4. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/hong-kong/gaps

Download the evidence pack (print-ready, free) →

Score history

How Hong Kong's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.

Immutable monthly snapshots of the reliability-adjusted score, tier, outlook and recurring cost, oldest first. Dated when taken and never back-filled, so the series only compounds forward. Part of the Analyst Desk →

What next for Hong Kong?

Add to shortlistTrack it alongside your other candidates.Compare with peersRank markets against each other on your own weights.Open the Analyst DeskEvery market side by side, with history and alerts.Retrieve it through the APIThe same read as JSON, with provenance on every field.

Done with Hong Kong? Browse every market or see conditions across every region.

How does Hong Kong compare to every other market?

This page is our full read on Hong Kong alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.

With your Analyst Desk, compare Hong Kong against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.

+ Add to your shortlist Recurring cost, ranked Connection friction, ranked Get the Analyst Desk →