A cheap, clean nuclear-and-hydro base, but availability is tightening through the nuclear-refurbishment cycle and Bill 40 introduces managed, economic-benefit-prioritized connections for large data centres. Strong, but getting more selective.
See live grid data →$55 to $100 per MWh
Midpoint about $78 per MWh
Ontario's low wholesale price is misleading on its own: the province recovers most of its generation cost through the Global Adjustment, not the spot price, so the wholesale figure alone understates the true cost by a wide margin. A large load pays wholesale plus Global Adjustment plus transmission, well above the wholesale number but below a residential all-in rate, and a large Class A load can lower the Global Adjustment by shifting demand off the top five annual system peaks.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: Ontario wholesale price and Global Adjustment (IESO) · Regulated Price Plan price report (OEB).
High
This market's friction level, wait band and full story are free here. Every market's wait in months, ranked side by side, is the Analyst Desk.
Any load above 10 MW connecting to the IESO-controlled grid needs both an IESO System Impact Assessment and a transmitter Connection Impact Assessment, which alone can run more than 12 months, then a multi-year queue for line upgrades and new substations. Bill 40 (2025) creates a separate class for data centres and lets the province prioritise or condition their connections, so access is becoming managed rather than first-come.
Data-centre share of demand pressure: Rising. Sources: Torys: connecting data centres in Ontario · Data centre regulation in Ontario (BLG). The full cross-market connection dataset is available through the Connection Friction Feed.
Managed access: Bill 40 (2025) lets the Minister prioritize large data-centre connections by economic benefit; approved projects proceed, new ones face selection.
Tightening availability: nuclear-refurbishment outages and demand growth are narrowing the practical margin.
Cost: wholesale energy is cheap (about $18/MWh), but the Global Adjustment (about $48/MWh) and delivery charges take the delivered cost to about $78/MWh, roughly 4 times the wholesale price.
Moderate momentum: a real and growing Toronto-area market.
Carbon: low, 65 gCO2e/kWh (national inventory, 2024), led by nuclear and hydro.
Distribution reliability (rural feeders, storm exposure) is moderate and not the binding concern here.
What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.
modelled
Large firm baseload leaving as demand climbs: Pickering Units 5-8 (about 2,000 MW) came out of service in September 2026 for refurbishment into the mid-2030s, and Unit 4 was permanently retired on 31 Dec 2024. IESO planning shows needs emerging as data-centre demand rises. Steps down if replacement firm capacity clears procurement.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
assessed · CNSC approves Pickering to end-2026 (NucNet) · Pickering-4 permanently shut (NucNet)
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.
Why: Bill 40 lets the Minister prioritize and approve large data-centre connections by economic benefit, so access is becoming managed and selective rather than open.
What would change the read: A clear, open large-load connection pathway rather than case-by-case selection.
For new supply: Ontario is procuring new firm supply and building transmission with First Nations equity partners; replacement capacity for the Pickering refurbishment is the near-term opening.
Beyond the grid: Indigenous consultation is central to new transmission and is increasingly structured as equity partnership rather than a late-stage veto risk: Ontario directed Hydro One to build the Red Lake Transmission Line under a model giving proximate First Nations a 50 percent equity stake, and signed a memorandum of understanding with five First Nations on the Barrie-to-Sudbury line. Hydro One Global News
Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.
The real-world events that test our Tier 2 call for Ontario: 2 challenge it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
IESO notice of 1 Oct 2026. Citing facility maintenance requested from this winter through 2027 and 2028, the IESO secured a firm import for this winter from Alpha Generation, a past capacity auction participant, starting 1 Nov 2026, and raised its targets for the 2026/2027 capacity auction (summer 2027 and winter 2027/28), reopening pre-qualification to 9 Oct 2026. The notice does not name the facilities under maintenance or where the imported power comes from. CBC News reported on 17 Oct 2026 that the power comes from New York state, and that the IESO told it Ontario remains a net exporter of power. The IESO has not linked the contract to Pickering; that link is press inference.
The Ontario Ministry of Energy and Mines said on 21 Sep 2026 that site construction on the Pickering refurbishment had begun and that Units 5 to 8 (Pickering B) would be removed from service by the end of September 2026. Reactor refurbishment work waits on final approval from the Canadian Nuclear Safety Commission, which the province expects in January 2027. The province approved OPG's refurbishment plan in November 2025. The CNSC's station page now lists Units 5 to 8 as shut down.
The Act lets the Minister prioritize and approve large data-centre connections by economic benefit; approved projects proceed, new ones face selection.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
100 MW contracted demand, 95% load factor, HV servicecalculated
A load of this shape consumes 832,200 MWh a year. At the delivered band of $55 to $100/MWh that is $45,771,000 to $83,220,000 a year in recurring power.
Wholesale energy is 23% of the delivered cost here. The other $60/MWh is Global Adjustment, network and delivery, and other and regulatory charges. See the full build-up.
Typical connection wait is 3 to 5 years, at Med confidence.
Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Broad (M1) | Directional: good for screening and monitoring |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
Limited
None of the 3 data layers is directly measured; they are triangulated or modelled
Full
3 of 3 dimensions: reliability, connection, cost
June 2026
per-layer vintages below
Source strength is limited: none of the 3 data layers is directly measured; they are triangulated or modelled. Confidence in the rating (High) is a separate judgement about the opinion as a whole, set in review; source strength grades only how directly the numbers underneath were measured.
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability review | assessed | 2025 | Fresh | CNSC approves Pickering to end-2026 (NucNet) |
| Connection friction | proxy | 2025/26 | Fresh | Torys: connecting data centres in Ontario |
| Realized cost | triangulated | 2026 | Fresh | Ontario wholesale price and Global Adjustment (IESO) |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
Not compiled for this market. Identify the serving operator before relying on any figure here, because a market-level read is an average over territories.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
The same list as JSON: /api/v1/markets/ontario/gaps
How Ontario's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.
Done with Ontario? Browse every market or see conditions across every region.
This page is our full read on Ontario alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.
With your Analyst Desk, compare Ontario against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.
Since 28 Sep 2026 we serve Canada's national inventory figure for Ontario: 65 gCO2e/kWh (2024, generation basis, preliminary). Where a live feed is available, the carbon figure in the live conditions on this page can differ: we derive that one hourly from the current fuel mix, so it moves through the day. Carbon intensity does not feed the PGIQ Rating.
Boundary: operational combustion, CO2-equivalent, per kWh delivered to the grid. Main activity producers only. ECCC National Inventory Report, Annex 7 →