Constrained, transmission-limited downstate with long queues. Workable in pockets, not a scale destination, and the access path is tightening.
See live grid data →$70 to $140 per MWh
Midpoint about $95 per MWh
New York is really two markets. Upstate, with cheap hydro and nuclear, sits near the bottom of the band; downstate, with a scarce capacity zone and among the highest delivery costs in the country, sits near the top. A large load's delivered cost depends heavily on where in the state it connects.
This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.
Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: NYISO capacity market · EIA New York electricity prices.
29 GW
60 monthsNYISO median, projects online 2018 to 2025
The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centres, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.
Severe access: 6-plus-year average queue, constrained downstate network, a large-load process still being written.
Tight downstate availability.
Mid-to-high cost.
Moderate momentum, mostly upstate.
Cleaner grid (~180 g), hydro and nuclear upstate.
Downstate delivery reliability is strong; the binding issue is forward capacity (firm supply promised for future years), not outages.
measured
Average customer interruption (SAIDI) of 71.99 minutes per year in 2024, excluding major event days as filed.
The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.
| Territory operator | SAIDI min/yr | Customers | Major-event method |
|---|---|---|---|
| Consolidated Edison Co-NY Inc (NY) | 14.95 | 3,686,348 | own method |
| Niagara Mohawk Power Corp. (NY) | 140.65 | 1,690,739 | IEEE 1366 |
| Long Island Power Authority (NY) | 59.29 | 1,151,740 | own method |
| New York State Elec & Gas Corp (NY) | 147.6 | 910,487 | own method |
| Rochester Gas & Electric Corp (NY) | 81.0 | 384,882 | own method |
| Central Hudson Gas & Elec Corp (NY) | 167.2 | 321,537 | IEEE 1366 |
| Orange & Rockland Utils Inc (NY) | 106.6 | 240,260 | own method |
| Village of Fairport - (NY) (NY) | 20.21 | 17,955 | IEEE 1366 |
| Village of Freeport - (NY) (NY) | 6.9 | 14,613 | IEEE 1366 |
| Town of Massena - (NY) (NY) | 17.4 | 9,328 | own method |
Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.
Statewide summer margins fall from 2,227 MW (17%) in 2019 to 417 MW (9%) in 2026, with 4.4 GW retired against 2.9 GW added since 2019; NYISO sees thin NYC margins from summer 2026 under the DEC peaker rule, a deficient Long Island BPTF from summer 2027, and NYC shortfalls by 2033-34.
What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.
assessed · NYISO 2025 Power Trends · NYC margins thin from 2026 (Utility Dive) · NYC shortfalls 2033-34 (Utility Dive)
We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.
Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.
The average customer loses about 71.99 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.
Averaged across 10 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.
What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.
Why: Executive Order 62 (14 Jul 2026) paused environmental permits for data centres of 50 MW and above for up to one year, on top of the FERC large-load order. The legislature's 20 MW bill remains unsigned.
What would change the read: A workable Community Investment Framework that reopens permitting, or the one-year pause lapsing.
For new supply: The proposed load moratorium does not stop generation, and new firm and storage supply is exactly what the adequacy gap needs, though siting meets the same local opposition.
Beyond the grid: Local consent is now a hard blocker: New York towns from Lysander to Perth to Dryden have passed data-centre moratoria or zoning bans over energy, water and noise, part of a wave in which local opposition delayed or blocked at least 75 US projects worth nearly 130 billion dollars in early 2026. Rockefeller Institute Inside Climate News
Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.
The real-world events that test our Tier 4 call for NYISO (New York): 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.
Executive Order 62 of 14 Jul 2026 directed Empire State Development to create and post a Community Investment Framework, with a deadline of 12 Sep 2026. As of 15 Sep 2026 the ESD page carries only the Policy Outline of 14 Jul and states that the completed framework will be released by mid-September. The moratorium on large data centres runs for one year, and this framework is the instrument through which host community terms are to be set.
Gov. Hochul signed an executive order (14 Jul 2026) pausing environmental permits for large data centres for up to one year while the state builds a regulatory framework covering energy, water and air impacts. The June legislature bill remains unsigned; the EO is in force now.
Legislature passed a one-year pause on permits for large data centres (4 Jun 2026); not yet signed by the Governor. Would add environmental, efficiency and ratepayer conditions.
Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.
100 MW contracted demand, 95% load factor, HV servicecalculated
A load of this shape consumes 832,200 MWh a year. At the delivered band of $70 to $140/MWh that is $58,254,000 to $116,508,000 a year in recurring power.
Wholesale energy is 55% of the delivered cost here. The other $43/MWh is installed capacity (ICAP), delivery and network, and ancillary and other charges. See the full build-up.
Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.
| Pillar | Evidence grade | What that means |
|---|---|---|
| Cost | Project-ready (M3) | Enough to price a project case |
| Connection | Market-level (M2) | Good for comparing markets, not for a site |
| Reliability | Market-level (M2) | Good for comparing markets, not for a site |
| Carbon | Market-level (M2) | Good for comparing markets, not for a site |
| Regulatory | Market-level (M2) | Good for comparing markets, not for a site |
| Local capacity | Not assessed | We hold no substation-level evidence |
High
2 of 3 data layers directly measured; the rest are triangulated or modelled
Full
3 of 3 dimensions: reliability, connection, cost
23 Oct 2026
per-layer vintages below
| Layer | Method | Vintage | Freshness | Source |
|---|---|---|---|---|
| PGIQ Rating opinion | opinion | June 2026 | Current | PGIQ methodology |
| Reliability | measured | 2024 | Fresh | EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 11 territories, 100% of customers, regional context only) |
| Interconnection queue | measured | end-2025 (LBNL 2026) | Fresh | LBNL Queued Up 2026 |
| Realized cost | triangulated | 2026 | Fresh | NYISO capacity market |
Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.
Territories in this market, each with its own filed record: Consolidated Edison Co-NY Inc, Niagara Mohawk Power Corp., Long Island Power Authority, New York State Elec & Gas Corp, Rochester Gas & Electric Corp, Central Hudson Gas & Elec Corp, Orange & Rockland Utils Inc, Village of Fairport - (NY). Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.
The same list as JSON: /api/v1/markets/nyiso/gaps
How NYISO (New York)'s reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.
Done with NYISO (New York)? Browse every market or see conditions across every region.
This page is our full read on NYISO (New York) alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.
With your Analyst Desk, compare NYISO (New York) against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.