Print view: light theme, the brief without folded evidence (the evidence pack prints it all). Use your browser's print to save a PDF.
PGIQ Rating · ratings as of June 2026 · data refreshed 24 Nov 2026
4

🇺🇸 NYISO (New York)

Possible, but expect friction, and access is getting harder Reliability flags found
Tier 4 Constrained · PGIQ Rating score 47/100, #58 of 79 markets (fundamentals 54, less a 7-point grid-reliability adjustment) · Outlook Negative · High confidence · how we score

Constrained, transmission-limited downstate with long queues. Workable in pockets, not a scale destination, and the access path is tightening.

See live grid data →
One market,
four reads
Build12/100Build scoreSellGrade C (index 26/100)Offtake grade (index)PlanRisingLoad pressureMonitorStressed (26/100)Grid strength
The same market, four decisions. Open any lens to see this market ranked against the rest.
The same market, read four ways

NYISO (New York) is a limited market to sell power into

Grade C (Limited)
Offtake score 26/100
Demand 50, build feasibility 12, combined into the score. For a seller: where buyers already pay, how tight supply is, and how feasible new build is here.
Price to beat
A 100 MW load on our standard case pays about $95/MWh delivered here. A competitive supply offer works against that level.
Queue depth (generation and storage)
About 29 GW in the interconnection queue (the line to connect to the grid), typical wait 60 months (NYISO median, projects online 2018 to 2025).
For new supply
The proposed load moratorium does not stop generation, and new firm and storage supply is exactly what the adequacy gap needs, though siting meets the same local opposition.
Regulatory momentum
Adverse, worsening. Executive Order 62 (14 Jul 2026) paused environmental permits for data centres of 50 MW and above for up to one year, on top of the FERC large-load order. The legislature's 20 MW bill remains unsigned.
Beyond the grid
Local consent is now a hard blocker: New York towns from Lysander to Perth to Dryden have passed data-centre moratoria or zoning bans over energy, water and noise, part of a wave in which local opposition delayed or blocked at least 75 US projects worth nearly 130 billion dollars in early 2026.
Scheduled to change
2026: Publication of the Community Investment Framework under Executive Order 62 (due 12 Sep 2026; published 15 Sep 2026) (Empire State Development).
See it on the Offtake grade →

NYISO (New York): effectively full at system level, rising demand pressure

Effectively full 19/100
System-level room, not local capacity
Local capacity: not assessed. We have found no operator publication of area or substation capacity for this market, so whether the bus serving a candidate site can take the load is an open question. Absence of a finding here is not evidence that capacity exists.
Two reads for a grid planner: how much room the system as a whole looks to have (Effectively full), and how hard demand is already pushing (Rising). The first is a market-level estimate from connection ease, forward adequacy and reliability margin. It is not local deliverability. Capacity at a specific substation is not assessed for this market, and a market can look roomy while the bus you want has nothing available. Confirm local capacity with the utility before relying on it.
Generation and storage queue
29 GW requested; about 7.2 GW likely to reach operation after historical withdrawal. The gap is speculative pipeline. This counts generation and storage seeking to connect, not load.
Demand growth
Moderate load growth in our read, the pull on your system.
Future firm supply
Future firm supply: tight for a large new load.
Load Pipeline Reality → Where demand is hungry → Connection friction →

Grid Risk Annex BETA

Stressed
Deep conditions or guarantees needed · grid strength 26/100
A cited, dated grid-risk read on NYISO (New York) for a capital provider, the banks and private-credit lenders, infrastructure funds and insurers holding or underwriting a power or data-centre exposure here. Drop it into a credit memo and watch each factor over the life of the exposure.
Read it against your asset. For a load asset (Buy), weight connection access and energization timing. For a generation or offtake asset (Sell), weight offtake demand, curtailment (being told to cut output or consumption) and cost realisation. For a grid or transmission asset (Move), weight load-pipeline reality and buildout risk.
Rating and track record
PGIQ Tier 4 Constrained, outlook Negative, High confidence. Scored on a public, dated, falsifiable record you can cite in a credit memo.
Delivery reliability
Reliability flags found in the bulk and local outage record we reviewed.
Future firm supply
Future firm supply: tight.
Cost certainty
Recurring cost $70 to $140/MWh for the standard 100 MW case, basis triangulated. Excludes connection capital.
Regulatory / stroke-of-pen
Adverse, worsening. Executive Order 62 (14 Jul 2026) paused environmental permits for data centres of 50 MW and above for up to one year, on top of the FERC large-load order. The legislature's 20 MW bill remains unsigned.
Execution risk
29 GW in the generation and storage queue, about 75% historically withdrawn, the risk the project or load actually energizes on time.
Ongoing monitor
Track this market's rating actions as a covenant-style monitor over the life of the exposure.
Monitoring plan
Covenant-style triggers to watch over the life of the exposure: a change in the PGIQ rating or outlook; a dated regulatory move (stroke-of-pen risk); a capacity-auction or cost-band shift; a forward firm-supply adequacy warning; and a rise in queue drop-out or connection friction. Track them on this market page, or as Analyst Desk alerts.
Sources: NYISO interconnection · Rockefeller Institute · Inside Climate News
This is a directional grid-risk screen, not a credit rating, and not investment, engineering or procurement advice.
The formatted, cited Grid Risk Annex export is an Analyst Desk feature.See the Grid Exposure Monitor →

Realized cost band

What a large electricity user pays for power here on one declared case, 100 MW contracted demand, 95% load factor, HV service, per megawatt-hour. Not the wholesale price and not the sticker tariff: energy plus the grid, delivery and other charges that land on the bill. It is a range, because real contracts vary, and it is labelled by how it was built.

Recurring cost, delivered

$70 to $140 per MWh

Midpoint about $95 per MWh

How this band was built

triangulated

From 3 public fragments

Your load

See how the answer changes for a different load size
The band above stays the comparable figure.
Declared case only
We hold this market's cost for the declared case only (100 MW, 95% load factor, high-voltage service). We don't scale it: tariff classes, demand charges, capacity charges and connection limits change with size, so 500 MW is not five times 100 MW.
Show evidence

What builds the $95 midpoint

Illustrative allocation of the compiled midpoint. Component lines are not separately sourced and should not be interpreted as observed tariff charges.
$52
$18
$22
Wholesale energy$52
Installed capacity (ICAP)$18
Delivery & network$22
Ancillary & other$3
All-in delivered$95 /MWh
How the $95/MWh figure is built up, component by component, for 100 MW contracted demand, 95% load factor, HV service. The allocation is our estimate; the total is the midpoint of the compiled band (triangulated). Recurring cost only: customer-funded connection capital is a separate one-off and is not included. New York is really two markets: downstate carries a scarce capacity zone and among the highest delivery costs in the country and sits at the top of the band, while upstate, with cheap hydro and nuclear, sits well below it. Anchored to published figures (NYISO capacity market). How this is built →

Where the cost lands

$95
Low $70Midpoint $95High $140
A band, not a single price: the cheaper end is a well-structured contract on favourable terms, the higher end a less optimized one. The midpoint is our best central read.
What is in the number: Wholesale energy near $52 per MWh, plus the NYISO installed-capacity (ICAP) charge and heavy delivery, which are far higher downstate. New York City and the lower Hudson Valley sit at the top of the band; upstate is materially cheaper.

New York is really two markets. Upstate, with cheap hydro and nuclear, sits near the bottom of the band; downstate, with a scarce capacity zone and among the highest delivery costs in the country, sits near the top. A large load's delivered cost depends heavily on where in the state it connects.

This market's band is free here; the ranked cross-market table with every market's precise midpoint is the Analyst Desk. See the ranked view.

Basis: Triangulated (built from several public data fragments cross-checked against each other, rather than one single measured figure). In US dollars per MWh delivered to a large high-load-factor load, excluding refundable taxes. Sources: NYISO capacity market · EIA New York electricity prices.

Download the evidence pack (print-ready, free) →

Seller view: This delivered price is the level a competitive supply offer must beat, and the revenue ceiling a merchant plant works against here.
Connection wait for a large new load
39 to 81 months
Range 39 to 81 months (3 to 7 years) (modelled from the generation queue). Mark: modelled.
Modelled from the generation queue, not a measured load wait (wait-model-1.0). Inputs: the generation and storage queue's typical duration of 60 months (the centre), and its depth of 29 GW against an estimated peak of 22.0 GW (ratio 1.32), which sets the range at plus or minus 35%. No published large-load wait exists here to check it against. Ask the grid operator for its large-load study timeline. · Source: LBNL Queued Up 2026 · Compare connection waits across markets →

Interconnection queue

Show evidence
These are generation and storage interconnection queues. They show how congested the interconnection system is. They do not measure how long a new large load waits, and their withdrawal rates are not load withdrawal rates. At the end of 2025, generation and storage projects totalling about 2,060 GW were actively waiting in United States queues, down 10% from a year earlier. Of the capacity that entered between 2000 and 2020, about 75% withdrew before connecting and only about 13% reached operation by end-2025. The typical project built in 2025 waited about 61 months from request to operation (Lawrence Berkeley National Laboratory, Queued Up 2026). Refresh cadence by layer. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Each figure is labelled measured or modelled.

Active queue depth

29 GW

Typical wait

60 monthsNYISO median, projects online 2018 to 2025

The full queue analysis for this market, which covers the share of projects that give up and leave the queue (the withdrawal rate), how much of the queue is data centres, and the sources, is part of the Analyst Desk (queue detail). API plans get the headline wait and its source; the depth and typical wait above are free. These are generation and storage queue figures: they show interconnection-system congestion, not a typical large-load connection wait.

Download the evidence pack (print-ready, free) →

Seller view: A deep queue is both your own time-to-revenue and a moat against competing supply; what matters is the effective supply likely to complete after withdrawal, not the headline queue.

The five pillars behind the tier

A
A
C
M
C
The pillar signature: Access, Availability, Cost, Momentum, Carbon, taller is stronger. The same shape repeats across every market so peers compare at a glance.
Access30%42

Severe access: 6-plus-year average queue, constrained downstate network, a large-load process still being written.

Show evidence
Availability25%50

Tight downstate availability.

Cost25%65

Mid-to-high cost.

Momentum15%55

Moderate momentum, mostly upstate.

Carbon5%73

Cleaner grid (~180 g), hydro and nuclear upstate.

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-centre build already underway, not just stated intentions.

Download the evidence pack (print-ready, free) →

Seller view: Read these the other way: momentum is your customer pipeline, cost is your revenue ceiling, and access is how hard it is to build and sell here, not only to connect.

Reliability overlay

Reliability adjustment: the five-pillar score of 54 is reduced to 47, a deduction of 7 points, reflecting the delivery-reliability and firm-supply risks flagged below. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.
Show evidence

Historical bulk-system performance: No reliability flags found

Downstate delivery reliability is strong; the binding issue is forward capacity (firm supply promised for future years), not outages.

measured

Historical utility-territory delivery performance: No reliability flags found

Average customer interruption (SAIDI) of 71.99 minutes per year in 2024, excluding major event days as filed.

measured · EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 11 territories, 100% of customers, regional context only)

A blend, not your supplier. This figure covers several distribution operators, so it describes an average customer rather than the operator that would serve your site. It is good for comparing markets and watching them move, it tops out at Comparable (M2), and it cannot carry a Project Case. mixed methods: IEEE 24%; respondent-defined 76% of customers. Major event days are excluded throughout; the methods differ only in how those days are identified, a smaller difference than the spread between the utilities themselves. Constituents below carry their own standard. It is a territory-wide history and is silent on: performance at a specific substation or feeder; transmission-level service, which is a different product from distribution service; the industrial or large-load customer class specifically; N-1 or other redundancy architecture at the supplying substation; contractual curtailment rights the utility may hold over the load; power quality and momentary interruptions, which this metric excludes by construction; on-site UPS, storage or generation; forward adequacy: it is a record of what happened, not a forecast.

The territories inside this market

The market figure above is an average across these territories. A project sits in one of them, not in the average. Each row is that operator’s own filed record; once a candidate site is matched to a territory, that row is the evidence that applies to it.

Territory operatorSAIDI min/yrCustomersMajor-event method
Consolidated Edison Co-NY Inc (NY)14.953,686,348own method
Niagara Mohawk Power Corp. (NY)140.651,690,739IEEE 1366
Long Island Power Authority (NY)59.291,151,740own method
New York State Elec & Gas Corp (NY)147.6910,487own method
Rochester Gas & Electric Corp (NY)81.0384,882own method
Central Hudson Gas & Elec Corp (NY)167.2321,537IEEE 1366
Orange & Rockland Utils Inc (NY)106.6240,260own method
Village of Fairport - (NY) (NY)20.2117,955IEEE 1366
Village of Freeport - (NY) (NY)6.914,613IEEE 1366
Town of Massena - (NY) (NY)17.49,328own method

Filed to EIA Form 861 for 2024, excluding major event days. Territory-wide averages: see the layer note above for what they do not establish.

Forward resource adequacy (assessed): Tight

Statewide summer margins fall from 2,227 MW (17%) in 2019 to 417 MW (9%) in 2026, with 4.4 GW retired against 2.9 GW added since 2019; NYISO sees thin NYC margins from summer 2026 under the DEC peaker rule, a deficient Long Island BPTF from summer 2027, and NYC shortfalls by 2033-34.

What this means: A large new load should expect genuine exposure to forced power cuts (curtailment), price spikes, and delays in getting connected, and should design in backup power or firm supply contracts.

assessed · NYISO 2025 Power Trends · NYC margins thin from 2026 (Utility Dive) · NYC shortfalls 2033-34 (Utility Dive)

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Download the evidence pack (print-ready, free) →

Seller view: Tight forward capacity is scarcity that firm generation and storage get paid for; an adequacy flag is a demand signal for new supply, not only a risk to a load.

Reliability metrics

Show evidence

Delivery reliability (measured)

The average customer loses about 71.99 minutes of power per year (2024). This is the standard regulator outage measure (SAIDI); lower means a more reliable grid.

Averaged across 10 territories. No single customer experiences this figure. The per-territory table in the reliability overlay above gives each operator’s own filed record, which is what a site-specific read needs.

Source: EIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 11 territories, 100% of customers, regional context only)

Hard, cited measures behind the reliability overlay above: the regulator outage series (SAIDI, measured, published with a lag) and the forward resource-adequacy assessment (a measured forecast). Framed as risk to a prospective large new load, not a verdict on any utility.

Download the evidence pack (print-ready, free) →

Supply relief outlook

Show evidence
Will the power crunch ease before your load energizes? This nets the demand racing for capacity against the new supply likely to arrive and the old supply leaving. A cross-side read, using the same data a seller sees the other way.
Tightening
Demand pressure
Moderate load growth competing for the same capacity.
New supply in motion
About 7.2 GW of the generation and storage queue is likely to reach operation after historical withdrawal.
Can new supply arrive
The proposed load moratorium does not stop generation, and new firm and storage supply is exactly what the adequacy gap needs, though siting meets the same local opposition.
Future firm supply
Future firm supply: tight.

What this means: The supply picture looks likely to tighten; a new load should lock firm supply early and expect competition for capacity.

Download the evidence pack (print-ready, free) →

Regulatory momentum

Show evidence
The regulatory and permitting environment is increasingly the binding variable for a new large load.
Adverse↓ worsening

Why: Executive Order 62 (14 Jul 2026) paused environmental permits for data centres of 50 MW and above for up to one year, on top of the FERC large-load order. The legislature's 20 MW bill remains unsigned.

What would change the read: A workable Community Investment Framework that reopens permitting, or the one-year pause lapsing.

For new supply: The proposed load moratorium does not stop generation, and new firm and storage supply is exactly what the adequacy gap needs, though siting meets the same local opposition.

Beyond the grid: Local consent is now a hard blocker: New York towns from Lysander to Perth to Dryden have passed data-centre moratoria or zoning bans over energy, water and noise, part of a wave in which local opposition delayed or blocked at least 75 US projects worth nearly 130 billion dollars in early 2026. Rockefeller Institute Inside Climate News

Download the evidence pack (print-ready, free) →

Grid conditions now

Structural baseline, June 2026Open the live map for NYISO (New York) →
Average demand
14,500 MW
Structural baseline, June 2026
Average system demand across the market, not the peak.
Wholesale price (modelled)
$52/MWh
Structural baseline, June 2026
US dollars. Energy only, and always modelled: no live price feed exists in any market. This is not the delivered cost.
Carbon intensity
195 g/kWh
Structural baseline, June 2026
Derived from the fuel mix. Never directly measured.
Renewable and nuclear
64%
Structural baseline, June 2026
The low-carbon share: generation from wind, solar, hydro, geothermal, biofuel and nuclear. Biofuel is counted as low-carbon, not zero-emission. The read for a carbon target.
Show all 10 fields
Renewable only
38%
Structural baseline, June 2026
Wind, solar, hydro, geothermal and biofuel. Excludes nuclear, which is low-carbon but not renewable, so this is the read for an RE100-style renewable procurement mandate.
Installed capacity
38,000 MW
Structural baseline, June 2026
Firm capacity
not held
Structural baseline, June 2026
De-rated, system-level.
System firm margin
not held
Structural baseline, June 2026
Market-wide estimate of de-rated firm capacity less peak demand. This is a directional screen, not local connectable capacity at any point of delivery.
Imports
2,000 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.
Exports
500 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.

Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.

Outlook drivers

Show evidence

↑ Upgrade triggers

  • Transmission build relieves the downstate constraint.
  • A dedicated large-load interconnection process clarifies the path.

↓ Downgrade triggers

  • Queue and transmission limits harden.
  • Downstate fossil retirements tighten supply.

Download the evidence pack (print-ready, free) →

Scheduled to change

Show evidence
Dated, already-announced events that will affect a large load sited here, in date order. These are published facts with sources, not our forecasts, and they matter most when your energization date is years out.
2026
Publication of the Community Investment Framework under Executive Order 62 (due 12 Sep 2026; published 15 Sep 2026)
Executive Order 62 (14 Jul 2026) paused permits for data centres of 50 MW and above for up to one year. The framework sets the host-community terms meant to reopen permitting; until it exists, the pause is the binding gate on siting in New York.

Download the evidence pack (print-ready, free) →

Key risks

Peer comparison

Trades like
CAISO (proven, constrained)
Ahead
on carbon
Behind
on access

Evidence behind this rating

The real-world events that test our Tier 4 call for NYISO (New York): 2 support it and 1 challenges it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Show evidence
The New York framework that is meant to end the moratorium has not been published ANNOUNCED ▲ Challenges the rating
Sep 2026AccessMateriality: med

Executive Order 62 of 14 Jul 2026 directed Empire State Development to create and post a Community Investment Framework, with a deadline of 12 Sep 2026. As of 15 Sep 2026 the ESD page carries only the Policy Outline of 14 Jul and states that the completed framework will be released by mid-September. The moratorium on large data centres runs for one year, and this framework is the instrument through which host community terms are to be set.

Power to a buyer: No change for a large load. The framework that is supposed to reopen permitting for large data centres does not exist, so the practical closure runs longer than the order's one-year term on its face. No supply moves either way.
Source: Empire State Development ↗
New York imposes the first US statewide data-centre moratorium by executive order ✓ Supports the rating
Jul 2026AccessMateriality: high

Gov. Hochul signed an executive order (14 Jul 2026) pausing environmental permits for large data centres for up to one year while the state builds a regulatory framework covering energy, water and air impacts. The June legislature bill remains unsigned; the EO is in force now.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Stateline ↗
New York passes first US statewide data-centre moratorium (awaiting signature) ✓ Supports the rating
Jun 2026AccessMateriality: med

Legislature passed a one-year pause on permits for large data centres (4 Jun 2026); not yet signed by the Governor. Would add environmental, efficiency and ratepayer conditions.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: NY Senate ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Download the evidence pack (print-ready, free) →

🔔 Get alerts for NYISO (New York)
Get an email when this market's rating, outlook or a material development changes. Market alerts are part of the Analyst Desk.

Rating history

Oct 2026
DowngradeCost-pillar score 71 to 65: now set by one published rule from the band midpoint ($95/MWh), not by analyst judgement. The band itself is unchanged. PGIQ Rating 48 to 47. Tier 3 Workable to Tier 4 Constrained.
Trigger: Cost-pillar scores set from delivered-cost bands by one published rule (cost-rescore-1.1), separate ratings release
Show evidence
Sep 2026
Under reviewReview continues and the resolution date has moved. The July entry said tier direction was uncertain pending the state's rules. Those rules have not arrived: the Community Investment Framework was due under the executive order on 12 Sep 2026 and is not published. A twelve month moratorium whose replacement framework is already late is a longer effective closure than the order's face value implies, and that is the Access read. Tier 3 holds; we are not moving on a delay alone.
Trigger: Community Investment Framework not published by the EO 62 deadline, 12 Sep 2026
Jun 2026
Under reviewA statewide 20 MW+ moratorium is one signature from law and would tighten access materially on top of the FERC order. Tier held pending the Governor's decision; downgrade path if signed. Update 14 Jul 2026: the Governor's Executive Order 62 paused environmental permits for data centres of 50 MW and above for up to one year. The 20 MW figure in the original call was the legislature's bill, which remains unsigned.
Trigger: NY Legislature data-centre moratorium passed (4 Jun 2026); FERC Section 206 order (18 Jun 2026)
Jul 2026
Under reviewA statewide permit pause at 50 MW+ is a direct hit to Access in force today. Duration and the shape of the successor framework are unclear; tier direction uncertain pending the state's rules.
Trigger: Executive order imposing a statewide data-centre moratorium, 14 Jul 2026
Oct 2026
AffirmedAffirmed, no change, 23 Oct 2026. Empire State Development published the Community Investment Framework on 15 Sep 2026, a few days after the order's deadline. It is voluntary guidance for host communities and does not lift the permit pause under Executive Order 62, which was already in the Access read. Tier and outlook held. Revisit when the pause ends or the Department of Public Service finalises its data-centre rules.
Trigger: NY Legislature moratorium bill (4 Jun 2026); Executive Order 62, 14 Jul 2026; Community Investment Framework published, 15 Sep 2026
June 2026
New ratingNew rating: Tier 3 Workable assigned.
Show evidence
🔒 The full time series behind NYISO (New York), how its score, recurring cost, and interconnection queue have moved month by month, is part of the Analyst Desk. The rating actions above are always free.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Download the evidence pack (print-ready, free) →

What this would mean for a project

Show evidence

100 MW contracted demand, 95% load factor, HV servicecalculated

A load of this shape consumes 832,200 MWh a year. At the delivered band of $70 to $140/MWh that is $58,254,000 to $116,508,000 a year in recurring power.

Wholesale energy is 55% of the delivered cost here. The other $43/MWh is installed capacity (ICAP), delivery and network, and ancillary and other charges. See the full build-up.

Recurring charges only. Customer-funded connection, substation and network-upgrade capital is quoted per project by the network operator and is not in this figure. A load factor materially below 95% raises the delivered rate per MWh, because demand and network charges are levied per MW; screen your own load to see whether the band still applies.

Download the evidence pack (print-ready, free) →

Data provenance and freshness

Show evidence
What we hold for this market, field by field. Each grade is set by the evidence we actually hold for that pillar. A low grade means we looked and the evidence is thin; it is not a verdict on the market.
PillarEvidence gradeWhat that means
CostProject-ready (M3)Enough to price a project case
ConnectionMarket-level (M2)Good for comparing markets, not for a site
ReliabilityMarket-level (M2)Good for comparing markets, not for a site
CarbonMarket-level (M2)Good for comparing markets, not for a site
RegulatoryMarket-level (M2)Good for comparing markets, not for a site
Local capacityNot assessedWe hold no substation-level evidence
Good enough for: screening and monitoring and comparing markets. Not yet good enough for: a priced project case, a project case with a carbon requirement, or site-level diligence. The weakest fields are connection and reliability.
Depth is not a rating strength, a confidence score or a feasibility conclusion. See the full coverage matrix. Version details: evidence-grade definitions v1.0.
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

2 of 3 data layers directly measured; the rest are triangulated or modelled

Coverage

Full

3 of 3 dimensions: reliability, connection, cost

Last reviewed

23 Oct 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliabilitymeasured2024FreshEIA Form 861, Schedules 3B and 3C (annual electric power industry report) (two major-event methods, IEEE; respondent-defined, customer-weighted blend of 10 of 11 territories, 100% of customers, regional context only)
Interconnection queuemeasuredend-2025 (LBNL 2026)FreshLBNL Queued Up 2026
Realized costtriangulated2026FreshNYISO capacity market

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

Download the evidence pack (print-ready, free) →

What this market can and cannot answer yet

Show evidence
No market-level read closes a project case on its own, and saying only that would waste the evidence we do hold. Below is what is established, what is open, and what to do next.

What is established

  • Recurring cost band $70 to $140 per MWh, midpoint $95, basis triangulated, against the 100 MW archetype
  • Historical utility-territory delivery performance 71.99 minutes per year (2024)
  • Historical bulk-system performance (measured)
  • Forward resource adequacy (assessed)
  • Typical interconnection wait about 60 months (generation and storage queue, not a load wait; NYISO median, projects online 2018 to 2025)

What is open

  • Contractual service terms (would change the answer)
  • Designed site resilience
  • Substation-level capacity evidence

How service and connection are organized

Territories in this market, each with its own filed record: Consolidated Edison Co-NY Inc, Niagara Mohawk Power Corp., Long Island Power Authority, New York State Elec & Gas Corp, Rochester Gas & Electric Corp, Central Hudson Gas & Elec Corp, Orange & Rockland Utils Inc, Village of Fairport - (NY). Which one serves a given site depends on where that site is.
How the connection process is organised: the applicable service and connection entities depend on the candidate location and the power pathway. We have not compiled the structure for this market; that is a gap in our wayfinding, not a fact about the market.

Credible ranges today

  • Cost $70 to $140 per MWh, midpoint $95 (triangulated)
  • Schedule: interconnection queues here run about 60 months for generation and storage (NYISO median, projects online 2018 to 2025); a large load follows a different process and we do not hold its measured distribution

What could disqualify this market

  • Downstate transmission constraint.
  • Long, suspension-prone queue.

Download the evidence pack (print-ready, free) →

Questions to put to the utility

Show evidence
These come from the gaps in our record for NYISO (New York): the decision points we have not assessed. Put each one to the utility, network operator or regulator before relying on this market for a project. A gap is not evidence that the risk is absent; it means we have not assessed it.
  1. What firm capacity is available at the substation we would connect to, and when? Needed for a project case
    Why it is open: no operator publication of area or substation capacity found for this market.

The same list as JSON: /api/v1/markets/nyiso/gaps

Download the evidence pack (print-ready, free) →

Score history

How NYISO (New York)'s reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.

Immutable monthly snapshots of the reliability-adjusted score, tier, outlook and recurring cost, oldest first. Dated when taken and never back-filled, so the series only compounds forward. Part of the Analyst Desk →

What next for NYISO (New York)?

Add to shortlistTrack it alongside your other candidates.Compare with peersRank markets against each other on your own weights.Open the Analyst DeskEvery market side by side, with history and alerts.Retrieve it through the APIThe same read as JSON, with provenance on every field.

Done with NYISO (New York)? Browse every market or see conditions across every region.

How does NYISO (New York) compare to every other market?

This page is our full read on NYISO (New York) alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.

With your Analyst Desk, compare NYISO (New York) against every market side by side, ranked on recurring cost and time-to-connect, with the full history and shortlist alerts.

+ Add to your shortlist Recurring cost, ranked Connection friction, ranked Get the Analyst Desk →