PGIQ Rating · ratings as of June 2026 · data refreshed 24 Nov 2026
1

🇸🇪 Sweden

Rated by region (Tier 1-3)
Tier 1 Prime · Rated by region: Tier 1-3 (open a region below for its rating) · Outlook Stable · High confidence · how we score
Tier
Tier 1-3
Rated by region
Delivered cost
Not published
Rated by region
Connection wait
By region
Open a regional rating below
Reliability and outlook
By region
Outlook Stable · High confidence

Cheap, clean, open Nordic power, but the national average hides a two-tier split: the northern zones (SE1/SE2, where Meta built in Lulea) are Prime, while the constrained, import-dependent south (SE4) sits two tiers lower. This overview links to both regional ratings.

See live grid data →
Regional overview. Sweden is rated by region: use the regional ratings below for siting. Rated regions: Sweden North (Lulea, SE1/SE2) · Sweden South (Malmo, SE4).
Your load. We don't publish a cost band for this market, so there is nothing to recompute for your load.

The five pillars behind the tier

Access30%70

Open and welcoming, with established northern clusters.

Show evidence
Availability25%75

High availability (hydro plus nuclear).

Cost25%80

Cheap power, among Europe's lowest in the north.

Momentum15%60

Moderate, real momentum.

Carbon5%99

Near-zero operational carbon (~10-40 g).

Default weights, which lean toward cost and access rather than carbon: Access 30 · Availability 25 · Cost 25 · Momentum 15 · Carbon 5. Momentum reflects the data-centre build already underway, not just stated intentions.

Download the evidence pack (print-ready, free) →

Reliability overlay

National reliability adjustment: the five-pillar score of 77 is reduced to 75, a deduction of 2 points. A national overview carries the average of its rated regions’ reliability adjustments (Sweden North (Lulea, SE1/SE2) 0, Sweden South (Malmo, SE4) 4), because a national view has to represent all of them, not only the strongest. The region pages carry the actionable ratings and their own adjustments. Reliability is reported as five separate layers, never as one combined label, because they answer different questions and a strong answer on one does not cover a gap in another: what has actually failed on the bulk system, what a forward assessment expects of firm supply, how the local network performs, what your contract actually promises, and what your site is designed to ride through. Any one of them can cap the tier.
Show evidence

Historical bulk-system performance: Minor flags found

North-to-south transfer is a growing bottleneck (interzone capacity around 7,000 MW): most new wind is in the north while southern nuclear has been phased out, so the load-heavy south leans on imports in low-wind hours.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

measured · Svenska kraftnat grid capacity (AFRY)

Historical utility-territory delivery performance: No reliability flags found

Forward resource adequacy (assessed): Adequacy flagged

Svenska kraftnat's analysis finds rising demand without large new flexibility becomes hard to serve from about 2035, with growing dependence on flexibility and imports at peak.

What this means: A large new load faces occasional exposure here. Monitor conditions and keep a contingency plan.

assessed · Svenska kraftnat grid capacity (AFRY)

Contractual service terms: not assessed

We have not compiled what firm service actually promises here: whether it is firm, non-firm or interruptible, the conditions under which you can be curtailed, the redundancy required of you, and the transfer time behind any N-1 commitment. Treat this as an open diligence item, not as an indication that service is firm.

Ask the utility for the tariff or service agreement terms before relying on firm supply.

Designed site resilience: not applicable at market level

Utility feeds, UPS, storage, on-site generation, islanding, black start and the residual energy you still expect to lose are properties of a specific site design, not of a market. This layer only exists once there is a site, and we never assert it for you.

Confidence: Med-High. Each input is labelled as measured, modelled, or drawn from a specific event, and is framed as a risk to a prospective large new load, not as a verdict on any utility or grid operator. Forward adequacy is an assessment of what is expected, not a measurement of what has happened; it is a forecast and is labelled as one.

Download the evidence pack (print-ready, free) →

Grid conditions now

Structural baseline, June 2026Open the live map for Sweden →
Average demand
17,000 MW
Structural baseline, June 2026
Average system demand across the market, not the peak.
Wholesale price (modelled)
$32/MWh
Structural baseline, June 2026
US dollars. Energy only, and always modelled: no live price feed exists in any market. This is not the delivered cost.
Carbon intensity
45 g/kWh
Structural baseline, June 2026
Derived from the fuel mix. Never directly measured.
Renewable and nuclear
100%
Structural baseline, June 2026
The low-carbon share: generation from wind, solar, hydro, geothermal, biofuel and nuclear. Biofuel is counted as low-carbon, not zero-emission. The read for a carbon target.
Show all 10 fields
Renewable only
70%
Structural baseline, June 2026
Wind, solar, hydro, geothermal and biofuel. Excludes nuclear, which is low-carbon but not renewable, so this is the read for an RE100-style renewable procurement mandate.
Installed capacity
42,000 MW
Structural baseline, June 2026
Firm capacity
not held
Structural baseline, June 2026
De-rated, system-level.
System firm margin
not held
Structural baseline, June 2026
Market-wide estimate of de-rated firm capacity less peak demand. This is a directional screen, not local connectable capacity at any point of delivery.
Imports
500 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.
Exports
5,000 MW
Structural baseline, June 2026
Modelled. No live interchange feed exists.

Every field above carries its own source and freshness. Price, imports and exports are modelled in every market because no feed supplies them. Carbon intensity is derived from the fuel mix.

Outlook drivers

Show evidence

↑ Upgrade triggers

  • Build scales beyond the current Nordic clusters.
  • Continued cheap clean power attracts firm tenants.

↓ Downgrade triggers

  • Northern-grid or political limits.
  • Cold-snap demand peaks.

Download the evidence pack (print-ready, free) →

Key risks

Peer comparison

Trades like
Norway / Finland (cheap clean Nordic)
Ahead
on openness
Behind
ERCOT on momentum

Evidence behind this rating

The real-world events that test our Tier 1 call for Sweden: 1 supports it. Each is dated and cited, so you can check the rating against what is actually happening on the ground.

Show evidence
Meta runs its first non-US hyperscale campus in Sweden, on hydropower ✓ Supports the rating
2025MomentumMateriality: high

Meta's three-building Lulea campus in northern Sweden, its first hyperscale data centre outside the US, runs almost entirely on Lule River hydropower and was sited for some of the lowest, cleanest electricity in Europe. That is exactly the low-cost, low-carbon, firm-supply profile behind this rating.

Power to a buyer: not assessed. This entry was logged before we added this line.
Source: Meta Data Centers ↗
Cited, dated developments tagged to the pillar they bear on, and whether they support or challenge the current tier. A material item flags the market for analyst review and may drive a rating action.

Dispute this rating. If you have evidence we’ve missed or misread, email hello@powergridiq.com. We log every dispute and reply within 10 business days.

Download the evidence pack (print-ready, free) →

🔔 Get alerts for Sweden
Get an email when this market's rating, outlook or a material development changes. Market alerts are part of the Analyst Desk.

Rating history

Show evidence
Jul 2026
AffirmedNational score moves 78 to 76 as the overview now carries the average of its regions' reliability adjustments (North 0, South 4) instead of an unapplied national reliability adjustment. Tier 1 affirmed; the region ratings are unchanged.
Trigger: Overview reliability-adjustment consistency (methodology note, Jul 2026)
June 2026
New ratingNew rating: Tier 2 Strong assigned (borderline Tier 1).
🔒 The full time series behind Sweden, how its score, recurring cost, and interconnection queue (the line to connect to the grid) have moved month by month, is part of the Analyst Desk. The rating actions above are always free.
Every rating action is dated and explained, and the log is only ever added to, never edited. Reviews happen on a regular schedule and whenever a significant event occurs. "Affirmed" means we reviewed a development and the tier held; "Under review" means a significant item is being assessed and the rating could change.

Download the evidence pack (print-ready, free) →

Data provenance and freshness

Show evidence
How solid the data behind this rating is, on two separate axes plus recency. Source strength is how measured the numbers are, as opposed to triangulated or modelled. Coverage is how many of the decision-relevant data dimensions (reliability, connection, and cost) are compiled for this market. The two are kept apart because they answer different questions: a market can have strong sources on the little that is covered, or broad coverage that still leans on models. Neither grades the rating itself. The rating is a cited opinion, graded separately and falsifiably by the public track record and baseline measurement plan.

Source strength

High

All 1 data layers are directly measured

Coverage

Partial

1 of 3 dimensions: reliability, connection, cost

Last reviewed

June 2026

per-layer vintages below

LayerMethodVintageFreshnessSource
PGIQ Rating opinionopinionJune 2026CurrentPGIQ methodology
Reliability reviewmeasured2025FreshSvenska kraftnat grid capacity (AFRY)

Freshness reflects each layer's refresh cadence. Queue snapshots: weekly (ledger). Connection-wait bands: quarterly. Capacity-auction results: yearly. Reliability statistics: annual to every three years. Tariffs: every year or two. The full cross-market freshness dashboard is at /data-quality.

Download the evidence pack (print-ready, free) →

Score history

How Sweden's reliability-adjusted score and tier have moved, month by month. Part of your Analyst Desk.

Immutable monthly snapshots of the reliability-adjusted score, tier, outlook and recurring cost, oldest first. Dated when taken and never back-filled, so the series only compounds forward. Part of the Analyst Desk →

What next for Sweden?

Add to shortlistTrack it alongside your other candidates.Compare with peersRank markets against each other on your own weights.Open the Analyst DeskEvery market side by side, with history and alerts.Retrieve it through the APIThe same read as JSON, with provenance on every field.

Done with Sweden? Browse every market or see conditions across every region.

How does Sweden compare to every other market?

This page is our full read on Sweden alone, and it is free. To decide where a large load should actually go, you need every market side by side, ranked on recurring cost and time-to-connect, with the history and alerts when your shortlist moves. That is the Analyst Desk.